City of Yelm Inspection Form Jonhs Meadow
City of Yelm
CONSTRUCTION PROGRESS AND INSPECTION REPORT
Date: 9/20/06
Day: Wednesday
Time: 8:30 a.m.
Project Name:
Johns Meadow / Griffin Subdivision
Project Number
SUB-04-0175-YL
Project Description:
Subdivision
Contractor's Name:
Les Russell Construction
1. Brief Weather Summary: (On earthwork jobs include soil conditions)
Cool, cloudy. Soil conditions are rocky, dry and dusty
2. Contract Time: No. Days Charged To Date Last Working Day Charged (Date)
Description of Construction Phases (Include items such as clearing, grading, drainage, base, paving, surface, utilities, curb and gutter, sidewalk, etc.)
Contractor has subgrade and Ballast ready for curbing machine. I have inspected the ballast compaction and uniformity for curb and gutter only. The grade and compaction is o.k. (Pass)
Road is not ready for inspect. Road way still needs to be graded and good ballast material added. Grade of road is not uniform or up to proper grade. Not to standard specifications.
4. Summary of Field Testing (Note failing tests and any retests. Condition of
material) No test on native material at this time
5. Sketch or Paste Pictures Below:
Date
9/20/06
Typed or Printed Name and Title
Steve Harrington
Signature