04-0180 RMS Walk Thru 110107
Ridgeline Middle School Walk Thru November 1, 2007
Grant: Nisha and I went out to Ridgeline Middle School to check the 2 items from our department on the punchlist. They have not completed these two punchlist items per plans. There
are callouts on these items that appear to refer to the wrong drawing sheets for details. These two items that remain to be completed are as follows:
Maintenance Driveway Entrance to South Ball Fields from Parking Lot is not complete.
Explanation: Maintenance Road Plan is on sheet C 1.5 not sheet C 2.14
Parking Lot Striping is not per plans, they are not per scale and do not match.
Explanation: Drawing Plan Sheet C 4.0 calls for a quantity of 20 parking stalls measuring 9’ wide x 20’ long. These 20 stalls have been striped correctly. They measure 9’ wide x 18’
long (not per plan). There is a note referring to striping detail (C 2.10) there is no detail (C 2.10) however there is a striping detail (4-24) on sheet C 1.5
Sheet C 1.2 gives the layout for the parking lot striping. Parking lot stalls are not sized per plan.