CONSTRUCTION PROGRESS AND INSPECTION REPORT
Date: 4/10/08
Day: Thursday
Time: 11:00 a.m.
Project Name:
Twin Star Credit Union
Project Number
SPR-05-0498-YL
Project Description:
Commercial Remodel
Contractor's Name:
General: Schwiesow Construction / Sub: Capital Septic and Excavating
1. Brief Weather Summary: (On earthwork jobs include soil conditions)
Sunny, Cool. Soil conditions are rocky, Contractor has placed and tied rebar for column footings.
2. Contract Time: No. Days Charged To Date Last Working Day Charged (Date)
Description of Construction Phases (Include items such as clearing, grading, drainage, base, paving, surface, utilities, curb and gutter, sidewalk, etc.) Contractor working
on setting up footings and columns for Drive up teller.
4. Summary of Field Testing (Note failing tests and any retests. Condition of
material) Contractor working on Drive thru footings and columns.
Sketch or Paste Pictures Below:
Date
4/10/08
Typed or Printed Name and Title
Steve Harrington