City of Yelm Inspection Form 5 Twin Star Credit Union City of Yelm CONSTRUCTION PROGRESS AND INSPECTION REPORT Date: 4/17/08 Day: Thursday Time: 11:07 a.m.  Project Name: Twin Star Credit Union Project Number SPR-05-0498-YL  Project Description: Commercial Remodel Contractor's Name: General: Schwiesow Construction / Sub: Capital Septic and Excavating  1. Brief Weather Summary: (On earthwork jobs include soil conditions) Sunny, Cool. Soil conditions are rocky, Footings are poured, Rebar put in place and tied for column for drive thru. Concrete poured for columns.  2. Contract Time: No. Days Charged To Date Last Working Day Charged (Date)  Description of Construction Phases (Include items such as clearing, grading, drainage, base, paving, surface, utilities, curb and gutter, sidewalk, etc.) Contractor working on setting up footings and columns for Drive up teller.  4. Summary of Field Testing (Note failing tests and any retests. Condition of material) Contractor working constructing footings and columns.  Sketch or Paste Pictures Below:    Date 4/17/08 Typed or Printed Name and Title Steve Harrington Signature