Proj Rev Date MemoCity of Yelm
Community Development Department
P.O. Box 479
Yelm, WA 98597
(360) 458-3835
(360) 458-3144 FAX
Memorandum
To: SPRC
From: Tami Merriman, Assistant Planner
Date: December 31, 2003
Re: SPR-03-8356-YL & SHO-03-8357-YL– Project Review Schedule for Christensen’s Furniture
Attached is the application packet for the above referenced project. After your initial review of the information submitted, if you need additional information from the applicant, please
let me know as soon as possible. The following is the tentative review schedule for the project.
December 31 – Notice of Application distributed – begin 30 day comment period.
February 4 – SPRC Environmental review. Department comments/mitigation requirements for Environmental Review.
February 10 – Environmental Determination Issued. Begin 14-day comment period, followed by a 7-day appeal period.
March 2, Environmental Determination Appeal time expired.
February 18 and February 25 – SPRC project review. Department comments/conditions of approval for staff report.
February 28 – Complete staff report for public hearing.
March 8 – Public hearing notice to the paper, mailing/post site.
March 22 – Public Hearing in front of the Hearing Examiner.