05-0498-YL Punchlist 1 123008
City of Yelm
Community Development Department
105 Yelm Avenue West
P.O. Box 479
Yelm, WA 98597
December 30, 2008
Eric Stark
Schwiesow Construction Inc.
920 Fair Street
Centralia, WA 98531
RE: Twin Star Credit Union – City of Yelm Project No. SPR-05-0498-YL
Construction Punchlist No. 1
Mr. Stark:
Please see below punchlist items that were noted during a Primary project walk-thru. This is a comprehensive list that includes all necessary departments from within the City.
Sewer Department:
Reclaimed water meter box needs purple “Reclaimed Water” box lid.
Sewer gate valve box must be set in concrete, per sewer spec. Drawing No. 7-21.
Two bollards must be set in place to protect valve and meter box.
There must be a “Reclaimed Water” sign put in place at the meter.
Sewer Dept. does not inspect past the meter box. You will need to contact Tony Reese @ (360) 458-8412 for any reclaimed water (Irrigation) concerns beyond the meter.
Per Section 11 of the reclaimed user’s agreement and state law governing the use of reclaimed water, appropriate public notification of the use of reclaimed must be provided through
the use of signage which is available at the public works dept. The public works Dept is located at 901 Rhoton Road. It is anticipated that 4-5 signs will be needed throughout the property
to adequately cover notification needs. The Public Works director will be responsible for approving signage.
Water Department:
Reduce Pressure Backflow Assembly is to low MUST have a minimum of twelve inch’s to the bottom of the assembly. See detail on the prints.
Reduce Pressure Backflow Assembly need to be raised and retested and a copy of the report sent to the water department at 901 Rhoton Road. (After the assembly has been raised)
There is not a lid on the Reclaimed meter setter.
Page Two
December 30, 2008
Twin Star Credit Union
Engineering Comments:
Landscape needs to be completed.
Irrigation needs to be completed.
Complete the roof drains.
Hydroseed disturbed areas.
Grade all disturbed areas to finish grade.
Complete the water system (Get sign off from Water Dept.)
Complete the sewer system (Get sign off from Sewer Dept.)
Clean up all construction debris, garbage and left over materials from project site.
Bring landscape up to finish grade.
Place all high utilities at the proper grade or elevation.
Put sign back in place.
Fill in holes in landscape and open area.
If you have any questions or would like to have a meeting on site to discuss these comments please contact Steve Harrington at (360) 458-8423 or email at steveh@ci.yelm.wa.us.
Community Development Department
Respectfully,
Steve Harrington
Engineering / Civil Inspector