City of Yelm Inspection Form 12 Placing Ballast on Roadway
City of Yelm
CONSTRUCTION PROGRESS AND INSPECTION REPORT
Date: 5/1/07
Day: Tuesday
Time: 3:00 a.m.
Project Name:
Forrester Heights
Project Number
SUB-05-0345-YL
Project Description:
Subdivision
Contractor's Name:
RDG (Rainier Development Group)
1. Brief Weather Summary: (On earthwork jobs include soil conditions)
Sunny, Cool. Soil conditions are rocky,
2. Contract Time: No. Days Charged To Date Last Working Day Charged (Date)
Description of Construction Phases (Include items such as clearing, grading, drainage, base, paving, surface, utilities, curb and gutter, sidewalk, etc.) Contractor working
on placing ballast , grading and compacting roadway. Tony called me late this afternoon for proof roll on the ballast for the roadway, they are planning on placing top rock tomorrow
morning. Roger was present during the proof roll. I rejected approximately 160’ of road way. This area is the area that got saturated by the hydrant test. These area’s were marked
and Roger will fix them tomorrow morning. I will go out in the morning to verify that they are satisfactorily fixed and will pass before rocking the area.
4. Summary of Field Testing (Note failing tests and any retests. Condition of
material) Contractor working on placing ballast on roadway.
Sketch or Paste Pictures Below:
Date
5/1/07
Typed or Printed Name and Title
Steve Harrington
Signature