City of Yelm Inspection Form 13 Placing Top Course on Roadway
City of Yelm
CONSTRUCTION PROGRESS AND INSPECTION REPORT
Date: 5/2/07
Day: Wednesday
Time: 8:30 a.m.
Project Name:
Forrester Heights
Project Number
SUB-05-0345-YL
Project Description:
Subdivision
Contractor's Name:
RDG (Rainier Development Group) Lakeside Industries
1. Brief Weather Summary: (On earthwork jobs include soil conditions)
Sunny, Cool. Soil conditions are rocky,
2. Contract Time: No. Days Charged To Date Last Working Day Charged (Date)
Description of Construction Phases (Include items such as clearing, grading, drainage, base, paving, surface, utilities, curb and gutter, sidewalk, etc.) Contractor working
on grading and utility ditches. Lakside Industries on site placing top rock. There is one approximate 20’ area that I have rejected due to pumping and did not pass proof roll. Berry
of Lakeside told Roger they are going to rock it per Lakeside suggestion and let it set up for 1 or 2 weeks to firm up. If it does not firm up and still fails proof roll, Roger of RGD
said they will fix it.
4. Summary of Field Testing (Note failing tests and any retests. Condition of
material) Contractor working on placing ballast on roadway.
Sketch or Paste Pictures Below:
Date
5/2/07
Typed or Printed Name and Title
Steve Harrington
Signature