City of Yelm Inspection Form 14 Grading Top Course on Roadway Forming for Sidewalk City of Yelm CONSTRUCTION PROGRESS AND INSPECTION REPORT Date: 5/10/07 Day: Thursday Time: 8:30 a.m.  Project Name: Forrester Heights Project Number SUB-05-0345-YL  Project Description: Subdivision Contractor's Name: RDG (Rainier Development Group) Lakeside Industries  1. Brief Weather Summary: (On earthwork jobs include soil conditions) Sunny, Cool. Soil conditions are rocky,  2. Contract Time: No. Days Charged To Date Last Working Day Charged (Date)  Description of Construction Phases (Include items such as clearing, grading, drainage, base, paving, surface, utilities, curb and gutter, sidewalk, etc.) Contractor working on forming for sidewalk and placing utilities in trench. Working on grading of roadway.  4. Summary of Field Testing (Note failing tests and any retests. Condition of material) Contractor working on placing ballast on roadway.  Sketch or Paste Pictures Below:    Date 5/10/07 Typed or Printed Name and Title Steve Harrington Signature