City of Yelm Inspection Form 7 Ballast grading and compacting
City of Yelm
CONSTRUCTION PROGRESS AND INSPECTION REPORT
Date: 4/16/07
Day: Monday
Time:9:30 a.m.
Project Name:
Forrester Heaghts
Project Number
SUB-05-0345-YL
Project Description:
Subdivision
Contractor's Name:
RDG (Rainier Development Group)
1. Brief Weather Summary: (On earthwork jobs include soil conditions)
Sunny, Cool. Soil conditions are rocky,
2. Contract Time: No. Days Charged To Date Last Working Day Charged (Date)
Description of Construction Phases (Include items such as clearing, grading, drainage, base, paving, surface, utilities, curb and gutter, sidewalk, etc.) Contractor working
on placing, grading and compacting ballast on roadway of Forrester Heights.
4. Summary of Field Testing (Note failing tests and any retests. Condition of
material) Contractor working on placing ballast on roadway.
Sketch or Paste Pictures Below:
Date
4/16/07
Typed or Printed Name and Title
Steve Harrington
Signature