City of Yelm Inspection Form 8 Ballast grading and compacting
City of Yelm
CONSTRUCTION PROGRESS AND INSPECTION REPORT
Date: 4/20/07
Day: Friday
Time:8:40 a.m.
Project Name:
Forrester Heights
Project Number
SUB-05-0345-YL
Project Description:
Subdivision
Contractor's Name:
RDG (Rainier Development Group) / W.C.C.I. (Concrete Curbing)
1. Brief Weather Summary: (On earthwork jobs include soil conditions)
Sunny, Cool. Soil conditions are rocky,
2. Contract Time: No. Days Charged To Date Last Working Day Charged (Date)
Description of Construction Phases (Include items such as clearing, grading, drainage, base, paving, surface, utilities, curb and gutter, sidewalk, etc.) Contractor working
on over exxing area that was saturated by water during hydrant testing. Contractor is over exxing, rocking and compacting fixed roadway area’s for completion of curb & Gutter on Forrester
Heights. Wilson Concrete Construction Inc. to begin curb & gutter on Monday 4/23/07.
4. Summary of Field Testing (Note failing tests and any retests. Condition of
material) Contractor working on placing ballast on roadway and along where curb & Gutter will be placed.
Sketch or Paste Pictures Below:
Date
4/20/07
Typed or Printed Name and Title
Steve Harrington
Signature