City of Yelm Inspection Form 10 Dry Utility Trench and Funky Curbing Trump Plat
City of Yelm
CONSTRUCTION PROGRESS AND INSPECTION REPORT
Date: 8/1/07
Day: Wednesday
Time: 10:45 a.m.
Project Name:
Trump Plat
Project Number
SUB-05-0456-YL
Project Description:
Subdivision
Contractor's Name:
Capital Septic and Excavating
1. Brief Weather Summary: (On earthwork jobs include soil conditions)
Sunny, Cool. Soil conditions are rocky,
2. Contract Time: No. Days Charged To Date Last Working Day Charged (Date)
Description of Construction Phases (Include items such as clearing, grading, drainage, base, paving, surface, utilities, curb and gutter, sidewalk, etc.) Contractor working
on curb & gutter. Jon Edwards and I are out on the project site talking to contractor and looking at the curb & gutter going in.
4. Summary of Field Testing (Note failing tests and any retests. Condition of
material) Contractor working on installing Curbing.
Sketch or Paste Pictures Below:
Date
8/1/07
Typed or Printed Name and Title
Steve Harrington
Signature