City of Yelm Inspection Form 11 Dry Utility Trench and Funky Curbing Trump Plat City of Yelm CONSTRUCTION PROGRESS AND INSPECTION REPORT Date: 8/21/07 Day: Tuesday Time: 10:40 a.m.  Project Name: Trump Plat Project Number SUB-05-0456-YL  Project Description: Subdivision Contractor's Name: Capital Septic and Excavating  1. Brief Weather Summary: (On earthwork jobs include soil conditions) Sunny, Cool. Soil conditions are rocky,  2. Contract Time: No. Days Charged To Date Last Working Day Charged (Date)  Description of Construction Phases (Include items such as clearing, grading, drainage, base, paving, surface, utilities, curb and gutter, sidewalk, etc.) Contractor working on curb & gutter. Placing dry utility trench.  4. Summary of Field Testing (Note failing tests and any retests. Condition of material) Contractor working on installing Dry Utilities  Sketch or Paste Pictures Below:    Date 8/21/07 Typed or Printed Name and Title Steve Harrington Signature