City of Yelm Inspection Form 14 Sidewalk Trump Plat
City of Yelm
CONSTRUCTION PROGRESS AND INSPECTION REPORT
Date: 11/20/07
Day: Tuesday
Time: 9:30 a.m.
Project Name:
Trump Plat
Project Number
SUB-05-0456-YL
Project Description:
Subdivision
Contractor's Name:
Capital Septic and Excavating
1. Brief Weather Summary: (On earthwork jobs include soil conditions)
Sunny, Cool. Soil conditions are rocky,
2. Contract Time: No. Days Charged To Date Last Working Day Charged (Date)
Description of Construction Phases (Include items such as clearing, grading, drainage, base, paving, surface, utilities, curb and gutter, sidewalk, etc.) Contractor working
on placing sidewalk forms on and ramps on Van Trump, inside of plat. Sidewalk being poured on Van Trump up to ramps forms. Curb was staked wrong and I could not pass the inspection
on the ramp forms. Contractor had to remove section of curb and restake due to bad survey staking. Scott Ritter was on site and is aware of this. New forms for curb & gutter and sidewalk
in correctly.
4. Summary of Field Testing (Note failing tests and any retests. Condition of
material) Contractor working on sidewalk.
Sketch or Paste Pictures Below:
Date
11/20/07
Typed or Printed Name and Title
Steve Harrington
Signature