City of Yelm Inspection Form 2 Storm Sewer Trump Plat City of Yelm CONSTRUCTION PROGRESS AND INSPECTION REPORT Date: 6/14/07 Day: Thursday Time: 10:00 a.m.  Project Name: Trump Plat Project Number SUB-05-0345-YL  Project Description: Subdivision Contractor's Name: Capital Septic and Excavating  1. Brief Weather Summary: (On earthwork jobs include soil conditions) Sunny, Cool. Soil conditions are rocky,  2. Contract Time: No. Days Charged To Date Last Working Day Charged (Date)  Description of Construction Phases (Include items such as clearing, grading, drainage, base, paving, surface, utilities, curb and gutter, sidewalk, etc.) Contractor working on 12”ADS storm conveyance system. CSE called requesting a change to storm c.b. # 7 due to utilility conflict, they want to move it 5’ to 6’ to the east to avoid conflict with existing utility. This change has gone through the engineer who made a drawing of change and has submitted to the city for approval. This change is o.k. with the city.  4. Summary of Field Testing (Note failing tests and any retests. Condition of material) Contractor working on installing storm drainage.  Sketch or Paste Pictures Below:    Date 6/14/07 Typed or Printed Name and Title Steve Harrington Signature