City of Yelm Inspection Form 5 Storm Sewer Trump Plat City of Yelm CONSTRUCTION PROGRESS AND INSPECTION REPORT Date: 7/12/07 Day: Thursday Time: 10:10 a.m.  Project Name: Trump Plat Project Number SUB-05-0456-YL  Project Description: Subdivision Contractor's Name: Capital Septic and Excavating  1. Brief Weather Summary: (On earthwork jobs include soil conditions) Sunny, Cool. Soil conditions are rocky,  2. Contract Time: No. Days Charged To Date Last Working Day Charged (Date)  Description of Construction Phases (Include items such as clearing, grading, drainage, base, paving, surface, utilities, curb and gutter, sidewalk, etc.) Contractor working on Storm System. Jon Edwards and I are out on the project site talking to contractor about schedule and placing the storm water infiltration system. Jon and I looked at the infilitration corregated aluminum pipe. Contractor has placed sorm pipe to wet pond and infiltration pond. Both ponds are excavated.  4. Summary of Field Testing (Note failing tests and any retests. Condition of material) Contractor working on installing storm drainage.  Sketch or Paste Pictures Below:    Date 7/12/07 Typed or Printed Name and Title Steve Harrington Signature