SUB-05-0456 Civil_JimG 022108 From: Jim Gibson
Sent: Thursday, February 21, 2008 11:02 AM
To: Steve Harrington
Cc: Karen Bennett
Subject: RE: Trump Plat As Built Plans Review and Comments
????HSteve
Please list the comments that you have on the plans now. I want to get a letter to them with the comments. If we have more comments on the second review then that is ok.
Jim Gibson
P.E.
City of
Yelm, Development Review Engineer
PO Box 479
Yelm,WA. 98597
Ph. 360.458.8438 Fx. 360.458.3144
jimg@ci.yelm.wa.us
From:
Steve Harrington
Sent: Wednesday, February 20, 2008 4:57 PM
To: Karen BennettCc: Jim GibsonSubject: Trump Plat As Built Plans Review and Comments
The following are my concerns with the submitted asbuilts for the Trump Plat. There are still several outstanding punchlist items that have not been completed, these are shown on
asbuilts, yet are not complete and should not be on the asbuilts yet. Furthermore there are some items that are not put in per plans but have been asbuilt and will function just
fine. I have been in contact with the owner, engineer and contractor to have punchlist issues completed, they are trying to take care of them, I feel that these items should be
completed before a more accurate asbuilt can be done. These are my comments.