SUB-05-0456 Engineering 020608 From: Steve Harrington Sent: Wednesday, February 06, 2008 9:30 AM To: Karen Bennett Subject: Trump Plat Punchlist acKaren:  The following are the items that I have found at the Trump Plat that need to be completed. Landscaping needs to be completed through out the entire plat. Finish grading needs to be completed through out the plat. Landscape timbers need to be placed around street trees through out the entire plat. Root barrier needs to be put in place behind curb (15’) and front of sidewalk (15’) at every street tree. Clean up left over material and debris through out entire plat. Patch trench in road at the intersection of Trump Ave. & Stella Ct.  This is to be completed per City of Yelm Standards. Fine Grade behind sidewalk, 1” below top of sidewalk elevation. Handicap ramps need curbing on both sides.  Per City of Yelm Standards. Completion of utilities and backfill trenches. Clean sidewalks. Hydroseed the required areas of plat per plans. Hydroseed storm pond area per plans. Place fence around storm pond and 1- 3’ wide walk through gate with padlock. Place fence around storm pond and 1- 10’ double gate with padlock. Fix driveway to existing house. Place an asphalt ramp at end of sidewalk to the street on Longmire around sta. 10+00. Clean out all storm sewer catch basins. Clean and sweep streets. Fix cracks in curbs at various locations on plat. Complete open spaces, play ground and pic nic areas. Storm Pond Outlet Protection needs to be completed per plans. Thanks, Steve Harrington Engineering / Civil Inspector City of Yelm Office (360) 458-8423 / Field (360) 561-4264