RE Willow Glenn 3 Water Items (4)IPM.Note
RE: Willow Glenn 3 Water Items
RE:
Steve Harrington
EX
/O=CITYOFYELM/OU=FIRST ADMINISTRATIVE GROUP/CN=RECIPIENTS/CN=STEVEH
Willow Glenn 3 Water Items
Steve Harrington
EX
/O=CITYOFYELM/OU=FIRST ADMINISTRATIVE GROUP/CN=RECIPIENTS/CN=STEVEH
John Ivey
Willow Glenn 3 Water Items
00000002SERVER1/o=CITYOFYELM/ou=first administrative group/cn=Recipients/cn=stevehMicrosoft Exchange Server
00000002SERVER1/o=CITYOFYELM/ou=first administrative group/cn=Recipients/cn=stevehMicrosoft Exchange Server
Yes. You are correct, it was raise the water meter setters. Skook already took care of it, it is complete.
Thanks,
Steve
_____
From: John Ivey
Sent: Thursday, July 12, 2007 1:21 PM
To: Steve Harrington
Subject: RE: Willow Glenn 3 Water Items
Steve, I believe the meter setters are what needs to be raised, not the boxes, please check the last punch list. John
_____
From: Steve Harrington
Sent: Wednesday, July 11, 2007 1:59 PM
To: Edward Smith; John Ivey
Subject: Willow Glenn 3 Water Items
Smitty & Jon: Contractor said all items are complete. The only construction items from water were the meter boxes needed to be raised on lots 42 & 43, also have you had a chance to
see that the water service line for the office has been disconnected from the well and is connected at the new service for that lot? Contractor is hoping this will be all checked off
before Friday July 12, 2007. I know you are very busy these days, Is this possible?
Thanks,
Steve
<DC90029353CCCD468AA2A2858FFCD8F528F841@server1.ci.yelm.wa.us>
<DC90029353CCCD468AA2A2858FFCD8F51F11B0@server1.ci.yelm.wa.us>
RE%3A Willow Glenn 3 Water Items.EML
Steve Harrington
Steve Harrington
11.0
Microsoft Exchange Server
00000002SERVER1/o=CITYOFYELM/ou=first administrative group/cn=Recipients/cn=JohnI
John Ivey
EX
/O=CITYOFYELM/OU=FIRST ADMINISTRATIVE GROUP/CN=RECIPIENTS/CN=JohnI
JohnI@ci.yelm.wa.us
JohnI
John Ivey
John Ivey