Proj Rev Date MemoCity of Yelm
Community Development Department
P.O. Box 479
Yelm, WA 98597
(360) 458-3835
(360) 458-3144 FAX
Memorandum
To: SPRC
From: Roberta Allen, Administrative Assistant
Date: February 5, 2002
Re: SPR-02-8306-YL – Project Review Schedule for Jack in the Box
Attached is the application packet for the above referenced project. After your initial review of the information submitted, if you need additional information from the applicant, please
let me know as soon as possible. The following is the tentative review schedule for the project.
February 13 – Notice of Application distributed – begin 15 day comment period.
March 6 & March 13– SPRC project review. Department comments/conditions of approval for staff report.
March 22 – Letter of Approval completed.