City of Yelm Inspection Form 10 Drainage Facility
City of Yelm
CONSTRUCTION PROGRESS AND INSPECTION REPORT
Date: 10/23/06
Day: Monday
Time: 9:30 a.m.
Project Name:
Willow Glenn III
Project Number
SUB-05-0345-YL
Project Description:
Subdivision
Contractor's Name:
Yelm Property Development
1. Brief Weather Summary: (On earthwork jobs include soil conditions)
Partly cloudy, warm, overcast. Soil conditions are rocky, dry and dusty
2. Contract Time: No. Days Charged To Date Last Working Day Charged (Date)
3. Description of Construction Phases (Include items such as clearing, grading, drainage, base, paving, surface, utilities, curb and gutter, sidewalk, etc.) Contractor
placing ecology blocks for storm drainage. For storm facility between Oak st. and Birch Ct. Placing 12” under drain for bio swale for storm between Lots # 11, 13 and 14
4. Summary of Field Testing (Note failing tests and any retests. Condition of
material)
5. Sketch or Paste Pictures Below:
Date
10/23/06
Typed or Printed Name and Title
Steve Harrington
Signature