Loading...
City of Yelm Inspection Form 13 Drainage Facility City of Yelm CONSTRUCTION PROGRESS AND INSPECTION REPORT Date: 11/16/06 Day: Thursday Time: 11:15 a.m.  Project Name: Willow Glenn III Project Number SUB-05-0345-YL  Project Description: Subdivision Contractor's Name: Yelm Property Development  1. Brief Weather Summary: (On earthwork jobs include soil conditions) Partly cloudy, warm, overcast. Soil conditions are rocky, wet  2. Contract Time: No. Days Charged To Date Last Working Day Charged (Date)  3. Description of Construction Phases (Include items such as clearing, grading, drainage, base, paving, surface, utilities, curb and gutter, sidewalk, etc.) Contractor working on sewer and water connections on Grove Rd. Yelm Water Dept and Sewer Dept. on site for inspections.  4. Summary of Field Testing (Note failing tests and any retests. Condition of material)  5. Sketch or Paste Pictures Below:    Date 11/16/06 Typed or Printed Name and Title Steve Harrington Signature