City of Yelm Inspection Form 16 Proof Roll of Ballast
City of Yelm
CONSTRUCTION PROGRESS AND INSPECTION REPORT
Date: 12/26/06
Day: Tuesday
Time: 1:15 p.m.
Project Name:
Willow Glenn III
Project Number
SUB-05-0345-YL
Project Description:
Subdivision
Contractor's Name:
Yelm Property Development
1. Brief Weather Summary: (On earthwork jobs include soil conditions)
Cloudy, Heavy Rain. Soil conditions are rocky, wet
2. Contract Time: No. Days Charged To Date Last Working Day Charged (Date)
Description of Construction Phases (Include items such as clearing, grading, drainage, base, paving, surface, utilities, curb and gutter, sidewalk, etc.) Contractor placing
ballast for roadway. Grading and compacting. I had to talk to contractor about removing some bigger rocks in some areas.
Note: I did not get to proof roll ballast on all sections of roadway before the contractor applied topcourse. Subgrade was o.k. and done on prior date.
4. Summary of Field Testing (Note failing tests and any retests. Condition of
material) Rocky and hard on roadway. Proof Roll completed with weighted fully loaded rock 12 yard dump truck, fully loaded with rock.
5. Sketch or Paste Pictures Below:
No Pictures taken today, camera not working at the time
Date
12/26/06
Typed or Printed Name and Title
Steve Harrington
Signature