Loading...
City of Yelm Inspection Form 5 City of Yelm CONSTRUCTION PROGRESS AND INSPECTION REPORT Date: 10/03/06 Day: Tuesday Time: 4:00 p.m.  Project Name: Willow Glenn III Project Number SUB-05-0345-YL  Project Description: Subdivision Contractor's Name: Yelm Property Development  1. Brief Weather Summary: (On earthwork jobs include soil conditions) Partly cloudy, warm, overcast. Soil conditions are rocky, dry and dusty  2. Contract Time: No. Days Charged To Date Last Working Day Charged (Date)  3. Description of Construction Phases (Include items such as clearing, grading, drainage, base, paving, surface, utilities, curb and gutter, sidewalk, etc.) Contractor is setting Type 1 storm catch basins @ Sta.12+65.49, 18.50’LT & Sta.31+62.57, 11.75’RT & Sta. 31+62.57, 11.75’LT & Sta.15+61.76, 18.5’RT, Sta.15+61.89, 18.5’LT, Sta.17+96.48, 18.50’RT, Sta.18+11.58, 18.5’RT Sta.18+11.58, 18.5’RT with 12” Ductile Iron storm line for road way crossing in traffic area. Install 12” ADS storm lines.  4. Summary of Field Testing (Note failing tests and any retests. Condition of material) Sand bedding. Type 1 c.b.’s backfilled with pee gravel.  5. Sketch or Paste Pictures Below:    Date 10/03/06 Typed or Printed Name and Title Steve Harrington Signature