City of Yelm Inspection Form 8 Drainage - Gallery City of Yelm CONSTRUCTION PROGRESS AND INSPECTION REPORT Date: 10/19/06 Day: Wednesday Time: 11:30 a.m.  Project Name: Willow Glenn III Project Number SUB-05-0345-YL  Project Description: Subdivision Contractor's Name: Yelm Property Development  1. Brief Weather Summary: (On earthwork jobs include soil conditions) Partly cloudy, warm, overcast. Soil conditions are rocky, dry and dusty  2. Contract Time: No. Days Charged To Date Last Working Day Charged (Date)  3. Description of Construction Phases (Include items such as clearing, grading, drainage, base, paving, surface, utilities, curb and gutter, sidewalk, etc.) Contractor has set 12” Perferated ADS storm lines in bioswales, underdrains and rock galleries. All drainage pipes and galleries are covered with washed drain rock and filter fabric per plans. Storm water facilities are are placed at the following locations. Oak Ct. & Birch Ct. and in between lots # 11, 13 and 14 and at the end of Fir Ct. and in between lot # 28 and Grove Rd.  4. Summary of Field Testing (Note failing tests and any retests. Condition of material) Approved 12’ ADS Perf Pipe, Washed Rock and Filter Fabric.  5. Sketch or Paste Pictures Below:    Date 10/19/06 Typed or Printed Name and Title Steve Harrington Signature