8295 Proj Rev Date MemoCity of Yelm
Community Development Department
P.O. Box 479
Yelm, WA 98597
(360) 458-3835
(360) 458-3144 FAX
Memorandum
To: SPRC
From: Roberta Allen, Administrative Assistant
Date: October 31, 2001
Re: SPR-01-8295-YL – Project Review Schedule for City of Yelm Animal Shelter
Attached is the application packet for the above referenced project. After your initial review of the information submitted, if you need additional information from the applicant, please
let me know as soon as possible. The following is the tentative review schedule for the project.
October 31 – Notice of Application distributed – begin 15 day comment period.
November 28 – SPRC project review. Department comments/conditions of approval for staff report.
December 6 – Letter of Approval completed.