Re: SPR-03-8362-YL – Project Review Schedule for Yelm High School Addition
Attached is the application packet for the above referenced project. After your initial review of the information submitted, if you need additional information from the applicant, please
let me know as soon as possible. The following is the tentative review schedule for the project.
January 2 – Notice of Application distributed – begin 15 day comment period.
January 21 – SPRC Environmental Review. Department comments/mitigation requirements for Environmental Review.
January 26 – Environmental Determination issued by Planning Department. Begin 14 day comment period followed by 7 day appeal period.
February 11 and February 18 – SPRC project review. Department comments/conditions of approval for staff report.
February 17 – Environmental Determination appeal time expired.
February 25 – Final approval letter completed.