Loading...
Proj Rev Date MemoCity of Yelm Community Development Department P.O. Box 479 Yelm, WA 98597 (360) 458-3835 (360) 458-3144 FAX Memorandum To: SPRC From: Roberta Allen, Administrative Assistant Date: September 5, 2002 Re: SUB-02-8317-YL – Project Review Schedule for Willow Glen Phase II Attached is the application packet for the above referenced project. After your initial review of the information submitted, if you need additional information from the applicant, please let me know as soon as possible. The following is the tentative review schedule for the project. SEPTEMBER 5 – Notice of Application distributed – begin 15 day comment period. SEPTEMBER 25 – SPRC Environmental Review with TIA Review. Department comments/mitigation requirements for Environmental Review. SEPTEMBER 27 – Environmental Determination issued by Planning Department. Begin 14 day comment period followed by 7 day appeal period. OCTOBER 16 & OCTOBER 23 SPRC Project review. Department comments/conditions of approval for staff report. OCTOBER 21 – Public Hearing Notice to Paper/Mailing/Post site. OCTOBER 18 – Environmental Determination appeal time expired. OCTOBER 25 – Complete Staff report for public hearing. NOVEMBER 4– Public Hearing NOVEMBER 14 – Hearing Examiner Decision