Amended Proj Rev Date MemoCity of Yelm Community Development Department P.O. Box 479 Yelm, WA 98597 (360) 458-3835 (360) 458-3144 FAX Memorandum To: SPRC From: Roberta Allen, Administrative Assistant Date: December 6, 2006 Re: SPR-05-0017-YL – Project Review Schedule for AMENDED Burnett Road Commercial Park Phase 2 Attached is the application packet for the above referenced project. After your initial review of the information submitted, if you need additional information from the applicant, please let me know as soon as possible. The following is the tentative review schedule for the project. December 6, 2006 – Amended Notice of Application distributed – begin 15 day comment period. December 27, 2006 and January 3, 2007 – SPRC Project review of Amended Phase 2 Site Plan Approval Letter completed.