RE: Ridgeline Junior High School -Updated Punchlist Items
Yelm High School -Updated Punchlist
Dear Rocky:
This letter is updates the status of the remaining punchlist items at Ridgeline Junior
High School and Yelm High School and as a reminder that the Temporary certificates of
occupancy expire at the end of October.
Enclosed please find the status of the punchlist items provided the District in August of
2006 and updated on September 11, 2007, for both Ridgeline Junior High and Yelm
High School. The temporary Certificates of Occupancy issued prior to the start of
school for these projects expire on October 31, 2007. The remaining items need to be
resolved prior to issuance of any further occupancy permits for either project, except as
noted below.
Items that have been completed, inspected, and approved by the City are marked as ^D,
items that have been deferred are marked as Q and items that are incomplete and must
be addressed prior to October 31St are marked with ^.
Ridgeline Junior High School
Water System
^D The water valve box located at the Carter Street entrance has a sewer lid on it,
which needs to be replaced with a water lid.
^D The valve box for the fire hydrant at station 5+82.89 needs to be cleaned out.
^D The valve box at station 7+17.05 needs to be cleaned out.
^D The fire hydrant height, Sta. 3+00.00 and next to the domestic water meter,
needs to be verified that it will not be too low after landscaping has been
installed.
(360) 458-8438
(360) 458-3144 FAX
www.ci.yelm.wa.us
^D The fire hydrant at station 13+12.45 needs to have bollards installed to protect it
from damage.
^D The bollards need to be installed around the air release.
^D The air release needs to be raised to final grade of the landscape.
^D The existing Mill Pond School fire hydrant located in back by the play ground
needs to be modified, as it is too tall now that the grading has been completed
and is unusable for fire protection purposes and can not be serviced by the
Public Works Department.
^D Mill Pond School requires a Reduced Pressure Backflow Assembly.
^D The City recommends that you connect the Reduced Pressure Backflow hot box
to an electrical source.
Sewer System
^D The STEP sewer circuit breakers inside the building are not labeled as required
to allow service personnel to disconnect the power.
^ One of the gravity sewer manholes before the step tank remains to be vacuum
tested.
^D Ground water wells (pyzometers) were required as part of the solution to high
ground water and the STEP tank, but have yet to be installed.
This requirement was rescinded by the Community Development Department.
^D Both 110 volt wiring and low voltage wiring (control wires) were installed in the
same conduit, and must be separated in individual conduits. While this appears
to have been corrected, there is no indication (such as asphalt/concrete patches)
that another conduit installed. The contractor will have to provide evidence that
another conduit was installed.
^D The pumps in the STEP tanks have run continuously shortly after the start of
School and will now have to be replaced prior acceptance by the City.
^ The floats are not operating according to specifications.
^D The alternating relay within the pump control panel is not working correctly or is
not wired correctly.
^D Both 110 volt and control wires are protruding out of the conduits and exposed
next to the tank riser.
General Comments
Q The storm pond and swales need to have debris removed.
To be completed at the time of football field completion.
Q The slopes of the storm pond need to be hydro-seeded.
To be completed at the time of football field completion)
Page 2 of 6
Q The landscaping and fencing is not complete around south end of the ball fields.
To be completed at the time of football field completion.
^ The maintenance driveway entrance to south ball fields from parking lot is not
complete and the sidewalk at this location is not complete.
While the contractor notes that this improvement was part of an alternate bid, the
civil plans approved by the City (see attached copy of page from approved
construction plans) clearly show the sidewalk and driveway approach being part
of the base bid. The City approved the plans based on this information.
^D The planter strips along the southeast fencing between the School and the
homes 107th loop need to be cleaned.
^D The area between the property line fence and baseball field needs to be
reseeded.
^D The area at the north east property line needs to be hydro-seeded.
^D A portion of fencing for the storm pond in the Hawks Landing subdivision, located
at the north entrance to the school, needs to be replaced.
^D Property owners in the Hawks Landing Subdivision, located at the north property
line, have noted that there is a gap at the bottom of the fence and the ground and
that there is construction debris graded material on their property from the School
construction.
^ The parking lot striping does not match the approved plans and appears to
contain more compact spaces than allowed.
While the contractor notes that the existing striping meets City requirements, this
is not the case. The civil plans approved by the City show a total of 196 spaces,
with 46 compact stalls. A total of 49 (25%) maybe compact stalls per City Code,
while there are at least 68 compact stalls on the site.
Q Required improvements to SR 507 must be completed no later than July 31,
2007.
Prior to October 31St, 2007, the District shall provide copies of WSDOT approved
Plans for Approval and construction plans to the City, along with a schedule
which includes bidding the project, construction, and completion of construction
by July 14, 2007.
Documentation
^D The deferral agreement for frontage improvements along Mill Road has not been
submitted.
^D The dedication of sewer and water lines and appurtenances has not been
submitted.
^D Easements for sewer and water systems have not been provided.
Page 3 of 6
^D The stormwater maintenance agreement needs to be recorded.
^D Construction as-builts need to be submitted and approved.
Yelm High School
Sewer System
^D Inlet baffles must be installed in tanks A and B (32" "down pipe" off the "T" and an
"up pipe" into the riser.
^D All risers in tanks A and B need to have a smooth top edge to ensure a good seal
with the riser lid.
^D The floats in tanks A and B are not positioned correctly on the float trees.
~~i° ~niiro nnnnon~innc in ~onLc 4 onr! R ~nii~hin +ho I_hnv in +ho ~ioi il~c noon! fn ho
mono i in ~nii+h hoo+ chrinL nnnnon~nrc onr! mol~or! nmm~lo~ohi
The Public Works Department has researched your position that this requirement
is not in compliance with the National Electric Code and has waived the
requirement.
^D Then service disconnects for tanks A and B handles in tanks A and B must be
lockable and able to accept a City of Yelm lock.
^ The service disconnects for tanks A and B need to have one additional fuse
installed to separate the three circuits (2 pump and 1 control circuit).
^D All mainline gate valves in the sewer main lines must have traffic bearing rings
and covers and a concrete pad per the Yelm Development Guidelines.
^D The clean-out cap in the side sewer for building 300 could not be located (Sta.
4+76.00)
^D The valve box containing the service line ball valve and service line for the tank
at building 400 must have toning wire brought to the surface.
^ The tank originally proposed to be retrofitted for use for building 400 did not pass
the leak test and needs to be replaced.
^ The 10,000 gallon tank serving buildings 300 and 500 needs additional bollards
placed to prevent vehicles from parking on the tank or the lid, as it is non-traffic
bearing.
The fencing was apparently removed from this area and the STEP lids have
been broken. Bollards (not fencing or ecology blocks) need to be installed
around the tank to protect it from traffic. The broken lid must be repaired and all
damage repaired.
^ A punctured butt connector needs to be replaced in the "J" box in the riser
^ A wire nut was used to "make up" the connections in the "J" box in the riser.
Only heat shrink butt connectors are allowed.
Page 4 of 6
^ The remote disconnect switch must be drilled to allow placement of a city
padlock when the switch is in the "on" position.
~~~~~nlncin n nrnnf " I" hnv i icor! fnr +ho ni imn ~niiroc ~nii~hin +ho ni imn ~roi ~I+ of +ho
#
onL hoc ~nii s "mon
ro m
n
n
°
~~ o i in" ~nii~h ~niiro ni i~c~;oco ~niiro ni i~c noorl~c
~
ronlonor! ~nii+ i
-rr
-r
c
r
h hoo+ chrinL hi i~~ nn nnon~nrc
The Public Works Department has researched your position that this requirement
is not in compliance with the National Electric Code and has waived the
requirement.
Note: The four comments above apply to the 1500 Gallon STEP Tank at Auto
Shop, which was not installed at the time of the first or second inspections in
August 2006 and May of 2007.
General Comments
^D Landscaping is not completed at the 93rd Street entrance, and along the north
property line.
^D If the portables have been connected to water and sewer, plans need to be
submitted and inspections completed.
^D The sidewalks do not meet ADA requirements as they do not have truncated
domes.
The sidewalks do NOT have truncated domes as noted by the contractor, they
are stamped in a diamond pattern. Truncated domes were required as part of
the civil plans approved by the City (see attached copy from Sheet C2.11 of
approved construction plans and referenced standard specifications).
Because the requirement for truncated domes was placed on the approved civil
plans by the School Districts engineer, the City will require the stamped concrete
to be placed at this time. However, the District should be aware that it changed a
requirement of the civil engineering plans and created a situation that does not
meet the current standards of the Americans with Disabilities Act. The City
understands that the District will take take responsibility for these decisions.
^D The old Yelm High School sign on Yelm Avenue West (SR 510) must be
removed.
^D The stormwater swale along Yelm Avenue West (SR 510) needs to be cleaned of
debris.
^D The required ADA stall has been painted over and does not meet ADA
standards.
Q Required frontage improvements along Yelm Avenue West (SR 510) will be
completed through the Districts participation in the Killion Road Local
Improvement District.
Page 5 of 6
D The right-of-way required for frontage improvements as part of the LID needs to
be dedicated to the City. The City will provide the required deeds and
dedications for the right of way.
Documentation
D The dedication of sewer and water lines and appurtenances has not been
submitted.
D Easements for sewer and water systems have not been provided.
D The stormwater maintenance agreement needs to be recorded.
D Construction as-builts need to be submitted and approved.
When all required improvements are complete, please contact Steve Harrington of the
Community Development Department at 458-8423 to schedule a re-inspection.
S incur .,~-~a .~
unity Development Department
c. Shelly Badger, City Administrator
Tim Peterson, Public Works Director
Jon Yanasak, Re-use System Manager
Jim Gibson, Development Review Engineer
Alan Burke, Yelm Community Schools Superintendent
Page 6 of 6