04-0180 Eng Review No 1 22805City of Yelm Community Development Department 105 Yelm Avenue West P.O. Box 479 Yelm, WA 98597 March 8, 2005 Bob Tauscher Jerome W. Morrissette and Assoc. 1700 Cooper Point Road SW #B2 Olympia, Washington 98502 RE: Ridgeline Middle School - SPR-04-0180-YL Initial Review of Civil -Site Construction Documents Mr. Tauscher: The City of Yelm has completed the initial review of the proposed junior high school referred to as Ridgeline Middle School. Your application included: • Civil Engineering Plans dated 12/22/04 • Landscape Plans dated 12/17/04 • Preliminary Drainage and Erosion Control Report, Nov 2004 • STEP Calculations We have reviewed the plans for compliance with the City of Yelm Development Guidelines, the DOE Stormwater Manual and general standards of civil engineering practice. The following comments need to be addressed before the plans may be approved for construction. The plans have been reviewed as submitted. If you have made any changes to the plans since the initial submittal they should be shown the revised plans. Our comments are summarized below: Site Plan (sheet C1.2): 1. Please add the structural sections for the maintenance access roads. 2. The parking stalls do not meet the City of Yelm standards. Please review city details and revise as necessary. 3. Please add sidewalk details to the plans. 4. The alignment of the access road at 107t" Ave needs to be realigned. The driveway should be aligned closer to a perpendicular angle. 5. The stormwater facility needs to be removed from the Y2 Corridor per the Conditions of Approval. 6. The Conditions of Approval requires there to be a turnaround at the end of Carter Street before the school gates. (360) 458-8438 (360) 458-3144 FAX www.ci.yelm.wa.us Erosion Control Details and Notes (sheets C1.1, 1.3): 7. The property lines need to be staked by a surveyor every 200 feet. At all corners and every 200 feet there needs to be a stake placed to delineate the property line. stormwater and Grading Plan (sheet C2.0, 2.1, 2.2, 2.3, 2.4, 2.5, 2.6, and 2.8): 8. The stormwater pond does not meet the setback requirements. The toe or top of the slope must be setback 10 feet from the property line, tract or right of way line. This measurement is taken from the property line to the catch point of the grading. 9. The stormwater conveyance system needs to be shown in profile view. 10. It appears that the separation between water and storm is not being met in certain locations. Please verify that there is at least 5 feet horizontally and 18" vertically are maintained. 11. Without profiles the vertical separation has not be reviewed. 12. Are the football field and baseball fields going to have stormwater drainage? 13. The entrance from Carter St appears to be graded flat or sloping toward Carter St. Please verify the stormwater will be retained onsite and not run off site to Carter St. 14. The callouts for CB 25 appear in error. 15. The 107t" St connection is required to be made utilizing a driveway apron. The driveway will be designed as a cement concrete approach, City of Yelm detail 4- 9, type 1. See comment from site plan section concerning alignment. 16. Verify that stormwater is not being discharged offsite due to the proposed grades. 17.Any ladders in type 2 catch basins need to have a minimum of 2 feet of clearance between them and adjacent objects. Please verify this and review the standard notes to reflect this. Detail Sheet (sheet C2.9) 18. The ADA curb ramp detail is not current. Please add the appropriate WSDOT curb ramp details to the plans. 19. Please make the following note on the utility trench: This detail is not being approved by the city. STEP Plan (sheets C3.1, 3.4, 3.5, 3.7): 20. The `End of Line Clean Out' identified on the end of the new 3" force main should also have a 3" gate valve and clean out. 21. The type 3-48" manhole must be constructed in such a way as to prevent any infiltration from entering the system. Please identify this method. 22. The new 50,000-gallon STEP Tank will need to be H-20 rated. 23.A submittal will be required on this new tank, to identify the location of the baffle wall and the inlet type and size. 24. A hose bib will be required within 40' of this STEP tank for maintenance. 25. Page C3.1 shows side sewers coming from future portables? Please label this on the plans. 26. Please identify the size of the proposed Grease interceptor. February 8, 2005 Page 2 of 4 27. This grease Interceptor appears to be within the building. This tank will need to be leak tested and the Sewer Department will need access to monitor grease levels. Water Plan (sheets C3.0, 3.2, 3.3): The water plan and fire system has been reviewed as submitted. It is apparent that the design is being changed and will be reviewed when submitted with the revisions. 28. The water meter will be required to be a compound meter meeting City standards. 29. A Reduced Pressure Backflow Assembly will be required after the water meter. 30. A double check valve will be required after the irrigation meter. 31. The water connections for the portables are considered private. Please label the plans showing the connection between portables and building being responsibility of the school district. 32. Water usage calculations are required. Please submit these calculations with the next submittal. stormwater Report: 33. The stormwater report does not appear to have been updated when the design changed. Please verify the report matches the design when resubmitted. 34. Much of the report refers to the separate Mill Pond School gallery. The plan does not show this gallery. 35. The proposed Vortechnics stormwater treatment system may be allowed if the following provisions can be met: a. The sizing of the vault is in compliance with the Department of Ecology's Use Designation. b. The Vortechnics is installed following a flow splitter. This splitter should be designed with stand pipes and separating the 6 month flows from the 100 year flows. c. The appropriate stormwater model should be used to size this application. Landscape Plan: 36. Please refer to Tami Merriman's redlined plans for the comments. Conditions of Approval: 37. Please verify that you have addressed all the land use conditions of approval on the civil engineering plans. I have not reviewed them and will not review them until the second review. Please review and revise the plans to address the above referenced comments. When the project is resubmitted you will need to submit 4 sets of plans, 2 stormwater reports. The project engineer should include a written response with the resubmittal, indicating how all the review comments above have been addressed or responded to. This will significantly expedite our review of the project. If you have any additional questions or comments please do not hesitate to call or contact me at jimg@ci.yelm.wa.us. February 8, 2005 Page 3 of 4 Community Development Department Respectfully, Jim Gibson Development Review Engineer Cc Grant Beck, Tami Merriman, Gary Carlson, City of Yelm Rocky Birkland, Yelm Schools enc. Redlined Landscape Plans February 8, 2005 Page 4 of 4