FW Wal-Mart & Yelm High School project as-builtsIPM.Note
FW: Wal-Mart & Yelm High School project as-builts
FW:
Steve Harrington
Grant Beck
Steve Harrington
Wal-Mart & Yelm High School project as-builts
Jon Yanasak
Jon Yanasak
EX
/O=CITYOFYELM/OU=FIRST ADMINISTRATIVE GROUP/CN=RECIPIENTS/CN=GRANT
EX
/O=CITYOFYELM/OU=FIRST ADMINISTRATIVE GROUP/CN=RECIPIENTS/CN=JONY
EX
/O=CITYOFYELM/OU=FIRST ADMINISTRATIVE GROUP/CN=RECIPIENTS/CN=JONY
Wal-Mart & Yelm High School project as-builts
Tim Peterson
Grant Beck
EX
/O=CITYOFYELM/OU=FIRST ADMINISTRATIVE GROUP/CN=RECIPIENTS/CN=STEVEH
EX
/O=CITYOFYELM/OU=FIRST ADMINISTRATIVE GROUP/CN=RECIPIENTS/CN=STEVEH
Grant Beck
EX
/O=CITYOFYELM/OU=FIRST ADMINISTRATIVE GROUP/CN=RECIPIENTS/CN=GRANT
Steve Harrington; Karen Bennett
Wal-Mart & Yelm High School project as-builts
Do we have any records of these two as-builts? If they are back in the
applicant's hands since the dates Jon indicates, we need to bug them to
resubmit.
Let's discuss at our SPR status meeting (if Karen is feeling better,
which I hope so since I'm starting to worry).
Grant
________________________________
From: Jon Yanasak
Sent: Tue 7/15/2008 4:22 PM
To: Grant Beck
Cc: Tim Peterson
Subject: Wal-Mart & Yelm High School project as-builts
Grant,
The last review done by the Sewer Department for the WalMart off-site
work was November of 2007. At that time we had a list of comments. We
have never received corrected as-built drawings.
The same applies to WalMart On-site however as you are aware, the work
is not completed.
The same applies to the Yelm High School Project. The last review of the
As-Builts was done by our department in October 2007, we submitted a
list of corrections, and again we have never received corrected
as-builts.
Having correct record drawings is very important to us here at the Sewer
Department as it directly impacts our ability to maintain the system.
Any help would be greatly appreciated.
Jon Yanasak
City of Yelm Sewer Dept. Mgr
Po Box 479
Yelm Wa 98597
Phone 360-458-8411
Fax 360-458-8166
jony@ci.yelm.wa.us
<DC90029353CCCD468AA2A2858FFCD8F5039D45@server1.ci.yelm.wa.us>
<DC90029353CCCD468AA2A2858FFCD8F5397EF2@server1.ci.yelm.wa.us>
message/rfc822
FW%3A Wal-Mart %26 Yelm High School project as-builts.EML
Steve Harrington
Steve Harrington
EX
/O=CITYOFYELM/OU=FIRST ADMINISTRATIVE GROUP/CN=RECIPIENTS/CN=Steveh
Steve Harrington
Karen Bennett
EX
/O=CITYOFYELM/OU=FIRST ADMINISTRATIVE GROUP/CN=RECIPIENTS/CN=KarenB
Karen Bennett