WalMart - Step Tank Review Ltr #4 (2)IPM.Note
WalMart - Step Tank Review Ltr #4
Steve Harrington
Karen Bennett
Steve Harrington
EX
/O=CITYOFYELM/OU=FIRST ADMINISTRATIVE GROUP/CN=RECIPIENTS/CN=KARENB
WalMart - Step Tank Review Ltr #4
EX
/O=CITYOFYELM/OU=FIRST ADMINISTRATIVE GROUP/CN=RECIPIENTS/CN=STEVEH
EX
/O=CITYOFYELM/OU=FIRST ADMINISTRATIVE GROUP/CN=RECIPIENTS/CN=STEVEH
Karen Bennett
EX
/O=CITYOFYELM/OU=FIRST ADMINISTRATIVE GROUP/CN=RECIPIENTS/CN=KARENB
Steve Harrington
WalMart - Step Tank Review Ltr #4
S, please take a good look at the letter (read it carefully) and see if
it’s ready to go out. Thanks and Smile, K
Karen T. Bennett
City of Yelm
105 Yelm Avenue West
PO Box 479
Yelm, WA 98597
(360)458-3835
Fax (360)458-3144
<DC90029353CCCD468AA2A2858FFCD8F584C2C0@server1.ci.yelm.wa.us>
WalMart - Step Tank Review Ltr %234.EML
Steve Harrington
11.0
05-0091 Review 4 Ltr 111308
05-0091 Review 4 Ltr 111308
Steve Harrington
EX
/O=CITYOFYELM/OU=FIRST ADMINISTRATIVE GROUP/CN=RECIPIENTS/CN=Steveh
steveh@ci.yelm.wa.us
Steve Harrington
458-8423
Community Development
Steve Harrington
Steve Harrington
Steveh
05-0091 Review 4 Ltr 111308.doc
City of Yelm
Community Development Department
105 Yelm Avenue West
P.O. Box 479
Yelm, WA 98597
November 14, 2008
Mike Beach
Pacland
606 Columbia St NW
Olympia, WA 98501
RE: Wal-Mart – Project Number SPR-05-0091-YL
4nd Review of STEP Tank System
Dear Mike,
The City of Yelm has completed the third review of the proposed Wal-Mart Step Tank revisions. Your application included:
Construction Plans
We have reviewed the construction plans for compliance with the City of Yelm Development Guidelines, the Department of Ecology Criteria or Sewage Works Design Manual and National Electrical
Code.
Review Comments:
Include tie-down and footing dtails to be included on plans.
See attached detail for 6,000 gallon step tank.
Need to supply Yelm Sewer Dept. with full submittal on new proposed tank that includes:
Location of all (3) risers
Length of inlet “T” ‘down pipe’
Method of supporting inlet ‘T’
Invert elevation of inlet pipe
Elevation of top of traffic bearing cover over inlet to tank.
Method of supporting new outlet “T” in existing tank, as this “T” will need to be located below the existing riser.
Baffle in new tank to have 3, 6” holes located 40” above floor of tank, not 12” as shown.
Inlet and outlet “T” in both tanks to be extended up to top of tank, just below the risers.
A Fernco rubber adapter (or equal) should be installed in the pipe connecting these 2 tanks to prevent breakage due to any tank settling.
Please review the above comments and submit updated plans. If you have any additional questions or comments please do not hesitate to call or contact me at steveh@ci.yelm.wa.us.
Community Development Department
Respectfully,
Steve Harrington
Civil Inspector
May 28, 2008 Page 2 of 2
(360) 458-8438
(360) 458-3144 FAX
www.ci.yelm.wa.us
.doc
05-009~1.DOC
05-0091 Review 4 Ltr 111308.doc
image001.jpg
.jpg
image001.jpg
image001.jpg
image/jpeg
image001.jpg@01C94641.414C2E60