05-0091 Sewer Punchlist No 1 060807CITY OF YELM SEWER DEPARTMENT
July 5, 2007
Re: Wal-Mart offsite Punch List
At Sta. # 117+00 a concrete pad is needed on the valve box. (6”X24”X24”)
The Air Release Assembly at Sta # 117+00 needs an insulated lid, lid screws and toning wire.
The Air Release Assembly at Sta. #130 +70 needs an insulated lid, lid screws, and a traffic bearing ring and cover.
The End of Line Clean-Out at Sta. #130 +10 needs to have the Blow-off and toning wire brought up as high as possible, and the lid needs to say “Sewer” not “Water”
At Sta. # 167+25, on Yelm Ave. E. The End of Line Clean Out (including the toning wire) needs to be extended up as high as possible. Rocks need to be removed from this stand pipe and
a 3’-4’ valve extension added.
At Sta. # 53+00 the gate valve stand-pipe seems to be separated and the valve nut cannot be accessed. This needs to be corrected.
At Sta. # 171+25 The Air release Assembly is missing parts. Additionally, an insulated lid and lid screws are needed. This also must conform with H-20 (traffic bearing) requirements.