Loading...
05-0091 Review 4 Ltr 111308 City of Yelm Community Development Department 105 Yelm Avenue West P.O. Box 479 Yelm, WA 98597   November 14, 2008 Mike Beach Pacland 606 Columbia St NW Olympia, WA 98501 RE: Wal-Mart – Project Number SPR-05-0091-YL 4nd Review of STEP Tank System Dear Mike, The City of Yelm has completed the third review of the proposed Wal-Mart Step Tank revisions. Your application included: Construction Plans We have reviewed the construction plans for compliance with the City of Yelm Development Guidelines, the Department of Ecology Criteria or Sewage Works Design Manual and National Electrical Code. Review Comments: Include tie-down and footing details to be included on plans. See attached detail for 6,000 gallon step tank. Need to supply Yelm Sewer Dept. with full submittal on new proposed tank that includes: Location of all (3) risers Length of inlet “T” ‘down pipe’ Method of supporting inlet ‘T’ Invert elevation of inlet pipe Elevation of top of traffic bearing cover over inlet to tank. Method of supporting new outlet “T” in existing tank, as this “T” will need to be located below the existing riser. Baffle in new tank to have 3, 6” holes located 40” above floor of tank, not 12” as shown. Inlet and outlet “T” in both tanks to be extended up to top of tank, just below the risers. A Fernco rubber adapter (or equal) should be installed in the pipe connecting these 2 tanks to prevent breakage due to any tank settling. Please review the above comments and submit updated plans. If you have any additional questions or comments please do not hesitate to call or contact me at steveh@ci.yelm.wa.us. Community Development Department Respectfully, Steve Harrington Civil Inspector