8262-040102-NorbergApril 1, 2002 Bo Norberg 2000 Group LLC PO Box 1177 Puyallup, Washington 98371 RE: Van Norhop Estates – Final Construction Punch list City of Yelm Project No. SUB-00-8262-YL Dear Mr. Norberg: On Friday March 29, 2002 I reinspected the above referenced site. The following is a list of items that need to be resolved before the final punch list will be completed. Roadway and Grading: Completed Sewer System: The end of line clean out needs to be completed. See detail on the plans for the required information. (The covers need to be stamped sewer not water. I did tell NW Cascade this when they were working on the irrigation system.) All service boxes must be cleaned of all sand to access the valves etc. (lot 15 needs to be cleaned out) Stormwater System: It appears that the silt tees and inverted elbows have not been installed in the required catchbasins. During the inspection I was unable to determine if the catchbasin sumps have been cleaned out or not. Please clean out the catchbasin sumps. (This has not been completed.) Landscaping: Completed Water System: Completed Misc. Information: As-built drawings must be submitted to the city for review and approval. (A set of mylars need to be submitted) The final engineering and inspection review fees need to be paid. After you have completed this construction punch list, I will reinspect this project. If you have any questions please call me at (360) 458-8438. Respectfully City of Yelm Community Development Jim Gibson Development Engineer Cc: Cathie Carlson Tim Peterson