05-0770 Civil # 3 022908 From: Steve Harrington
Sent: Friday, February 29, 2008 4:21 PM
To: Karen Bennett
Subject: PRD-05-0770-YL Samantha Ridge Review # 3 Comments
Follow Up Flag: Follow up
Flag Status: Red
?????????Karen: The following are my Samantha Ridge Review # 3 comments:
1. This is a note for Jim G. to look into. Jim The Contech Vortech Storm Water Treatment System will treat the storm water and the detention pond would provide treatment
as well. This should be sufficient treatment to allow for discharge to Yelm Creek.
2. The City of Yelm will need all permits approved by D.O.E.
3. The irrigation and the fire system cannot share the same water meter. These systems will need to have individual meters.
4. Have the Landscape Plans been submitted to the City of Yelm Planning Department yet.
5. I did not see any detail for constructing storm pond access road, or a call out for material the type of material to construct it with.
Thank you,
Steve Harrington
Engineering / Civil Inspector
City of Yelm
Office (360) 458-8423 / Field (360) 561-4264