Loading...
City of Yelm Inspection Form Tahoma Terra FairWay Multi-Family#6 City of Yelm CONSTRUCTION PROGRESS AND INSPECTION REPORT Date: 4/08/08 Day: Tuesday Time: 2:00 p.m.  Project Name: Tahoma Terra / FairWay Multi-Family Project Number SPR-05-0750-YL  Project Description: Subdivision Contractor's Name: RGD Rainier General Development / KPFF  1. Brief Weather Summary: (On earthwork jobs include soil conditions) Sunny, cool, clear. Clear, Cool, Sunny  2. Contract Time: No. Days Charged To Date Last Working Day Charged (Date)  3. DeRainscription of Construction Phases (Include items such as clearing, grading, drainage, base, paving, surface, utilities, curb and gutter, sidewalk, etc.) Contractor RGD is working roadway grading and clearing land for the TT Fairway Multi-Family project. Placing utilities.  4. Summary of Field Testing (Note failing tests and any retests. Condition of material) RGD is working roadway into TT Fairway Multi Family Project and clearing land. Placing utilities.  5. Sketch or Paste Pictures Below:    Date 4/8/08 Typed or Printed Name and Title Steve Harrington Signature