City of Yelm Inspection Form # 2 Dels Farm Supply
City of Yelm
CONSTRUCTION PROGRESS AND INSPECTION REPORT
Date: 4/8/08
Day: Tuesday
Time: 4:00 p.m.
Project Name:
Dels Farm Supply
Project Number
SPR-05-0673-YL
Project Description:
Commercial
Contractor's Name:
Wood & Son / Hatton, Godat & Pantier
1. Brief Weather Summary: (On earthwork jobs include soil conditions)
Sunny, Cool. Soil conditions are rocky and muddy
2. Contract Time: No. Days Charged To Date Last Working Day Charged (Date)
Description of Construction Phases (Include items such as clearing, grading, drainage, base, paving, surface, utilities, curb and gutter, sidewalk, etc.) Contractor working
on clearing and grubbing of project. Cutting down grade and removal of non usable material.
4. Summary of Field Testing (Note failing tests and any retests. Condition of
material) Clearing and Grubbing and exxing for storm pond facility.
Sketch or Paste Pictures Below:
Date
4/7/08
Typed or Printed Name and Title
Steve Harrington
Signature