Loading...
Proj Rev Date MemoCity of Yelm Community Development Department P.O. Box 479 Yelm, WA 98597 (360) 458-3835 (360) 458-3144 FAX Memorandum To: SPRC From: Roberta Allen, Administrative Assistant Date: July 15, 2003 Re: SUB-03-8346-YL – **REVISED** Project Review Schedule for Buckhorn Estates Attached is the application packet for the above referenced project. After your initial review of the information submitted, if you need additional information from the applicant, please let me know as soon as possible. The following is the tentative review schedule for the project. July 16, 2003 – Notice of Application distributed – begin 15 day comment period. August 6, 2003 – SPRC Environmental Review. Department comments/mitigation requirements for Environmental Review. August 11, 2003 – Environmental Determination issued by Planning Department. Begin 14 day comment period followed by 7 day appeal period. September 2, 2003 – Environmental Determination appeal time expired. September 3 & September 10, 2003 – SPRC project review. Department comments/conditions of approval for staff report. September 15, 2003 – Public Hearing Notice to Paper/Mailing/Post site. September 19 2003 – Complete Staff report for public hearing. September 29, 2003 – Public Hearing in front of Hearing Examiner October 10, 2003 – Hearing Examiner Decision Complete