RE Questions on Sewer Items for Plan Review on Today's DentalIPM.Note
RE: Questions on Sewer Items for Plan Review on Today's Dental
RE:
Steve Harrington
Jon Yanasak
Steve Harrington
EX
/O=CITYOFYELM/OU=FIRST ADMINISTRATIVE GROUP/CN=RECIPIENTS/CN=JONY
Questions on Sewer Items for Plan Review on Today's Dental
EX
/O=CITYOFYELM/OU=FIRST ADMINISTRATIVE GROUP/CN=RECIPIENTS/CN=STEVEH
EX
/O=CITYOFYELM/OU=FIRST ADMINISTRATIVE GROUP/CN=RECIPIENTS/CN=STEVEH
Jon Yanasak
EX
/O=CITYOFYELM/OU=FIRST ADMINISTRATIVE GROUP/CN=RECIPIENTS/CN=JONY
Steve Harrington
Questions on Sewer Items for Plan Review on Today's Dental
00000002SERVER1/o=CITYOFYELM/ou=first administrative group/cn=Recipients/cn=jonyMicrosoft Exchange Server
00000002SERVER1/o=CITYOFYELM/ou=first administrative group/cn=Recipients/cn=jonyMicrosoft Exchange Server
Steve,
Item #3 – Duplex pumping systems come from the factory with a tank riser
that has two 1” holes with grommets. These two lines are plumbed
together (with a “T”) into a 2” service line, just outside the riser.
Only one 2” service line goes out to the Main.
Item #4 – This tank would need to be replaced with an H-20 rated tank if
parking is allowed above.
Item #8 – Yes a “Hot Tap” would be allowed.
Item #9 – I don’t understand the question, however, our Spec. indicates
that no tank shall be allowed with an invert elevation (inlet to the
tank) greater than 5’ below the uppermost tank riser lid.
Hope this helps,
Jon Yanasak
City of Yelm Sewer Dept. Mgr
Po Box 479
Yelm Wa 98597
Phone 360-458-8411
Fax 360-458-8166
jony@ci.yelm.wa.us
________________________________
From: Steve Harrington
Sent: Wednesday, July 02, 2008 1:34 PM
To: Jon Yanasak
Subject: Questions on Sewer Items for Plan Review on Today's Dental
Jon or Randy: The Engineer called me and has some questions on your
comments on the review letter. The questions are from the attached
review letter and are as follows:
Item # 3: Purpose of dual lines? Dual lines out of step tank pumping
system, can they go to a single line out of pumping system from step
tank? They would like to place 2 lines.
Item # 4: What needs to be done to existing step tank to retrofit it to
a traffic rated tank, so it can be placed in parking area?
Item # 8: Can they hot tap & saddle rather than placing a Tee in the
line.
Item # 9: They provided detail “D”. What do you need to see or want
for depth? They show 2 different phases 1& 3 with bury depth.
Steve Harrington
Engineering / Civil Inspector
City of Yelm
Office (360) 458-8423 / Field (360) 561-4264
<DC90029353CCCD468AA2A2858FFCD8F5397EED@server1.ci.yelm.wa.us>
<DC90029353CCCD468AA2A2858FFCD8F579A632@server1.ci.yelm.wa.us>
<DC90029353CCCD468AA2A2858FFCD8F579A632@server1.ci.yelm.wa.us>
RE%3A Questions on Sewer Items for Plan Review on Today's Dental.EML
Steve Harrington
11.0
Microsoft Exchange Server
00000002SERVER1/o=CITYOFYELM/ou=first administrative group/cn=Recipients/cn=jony
Steve Harrington
EX
/O=CITYOFYELM/OU=FIRST ADMINISTRATIVE GROUP/CN=RECIPIENTS/CN=Steveh
steveh@ci.yelm.wa.us
steveh
458-8423
Community Development
Steve Harrington
Steve Harrington