Proj Rev Date MemoCity of Yelm Community Development Department P.O. Box 479 Yelm, WA 98597 (360) 458-3835 (360) 458-3144 FAX Memorandum To: SPRC From: Tami Merriman, Assistant Planner Date: August 18, 2003 Re: VAR-03-8348-YL – Project Review Schedule for Yelm Community School Variance Attached is the application packet for the above referenced project. After your initial review of the information submitted, if you need additional information from the applicant, please let me know as soon as possible. The following is the tentative review schedule for the project. August 27 and September 3, 2003 – SPRC project review. Department comments/conditions of approval for staff report. September 15 – Complete staff recommendation to Hearing Examiner September 15, 2003 – Notice of Public Hearing to paper, 300’ and post site. September 17, 2003 - Mail Staff report September 29, 2003 - Public Hearing.