Re: VAR-03-8348-YL – Project Review Schedule for Yelm Community School Variance
Attached is the application packet for the above referenced project. After your initial review of the information submitted, if you need additional information from the applicant, please
let me know as soon as possible. The following is the tentative review schedule for the project.
August 27 and September 3, 2003 – SPRC project review. Department comments/conditions of approval for staff report.
September 15 – Complete staff recommendation to Hearing Examiner
September 15, 2003 – Notice of Public Hearing to paper, 300’ and post site.
September 17, 2003 - Mail Staff report
September 29, 2003 - Public Hearing.