Proj Rev Date MemoCity of Yelm
Community Development Department
P.O. Box 479
Yelm, WA 98597
(360) 458-3835
(360) 458-3144 FAX
Memorandum
To: SPRC
From: Tami Merriman, Assistant Planner
Date: September 19, 2003
Re: ZON-03-8349-YL – Project Review Schedule for Yelm Community School Rezone
Attached is the application packet for the above referenced project. After your initial review of the information submitted, if you need additional information from the applicant, please
let me know as soon as possible. The following is the tentative review schedule for the project.
September 19, 2003 – Notice of Application distributed, begin 15 day comment period.
October 1 and 8 – SPRC project review. Department comments/conditions of approval for staff report.
October 10 – Complete staff recommendation to Planning Commission
October 6 – Notice of Public Hearing to paper, 300’ and post site.
October 14 - Mail Staff report
October 20 - Public Hearing before Planning Commission
November 5 – Planning Commission recommendation report to City Council
November 12 – City Council Meeting.