2020.0103.BPP0008 0040 - D1.1 DEMOLITION DETAILS - 3705SALESCONTINUOUS SEALANTAGAINST PLATEDEMO AREAROOF DECKCOORDINATE W/SPECIFICATION SECTION 01500.ANCHOR AT 24" OC2x4 AT 24" OCWALL TOBE REMOVEDINSTALL CONTINUOUS LAYER 6 MIL POLY SHEETS TAPE ALL JOINTSSEALANT UNDERBOTTOM PLATE1/2" CD PLYWOOD 4'-0"X8'-0" HORIZONTAL PROVIDE 2x4 NAILER AT ALL JOINTSCONTINUE PLYWOODTO DECKDO NOT USE DUST WALL TO SHORE ROOF JOISTS6'-0" LOAD BEARING4'-0" ELSEWHERENOTES:1. INSTALL TEMPORARYWALL IN SECTIONS APPROX 40'-0" PER DAY (COORDINATE WITH STORE MANAGER AND WALMART CONSTRUCTION MANAGER)2. LOCATE VERTICAL 2x4'SAS NOT TO INTERFERE WITH CEILING GRID OR LIGHT FIXTURES3. LOCATE HORIZONTAL 2x4AT 2" ABOVE CEILING EXCEPT LIGHT FIXTURE LOCATIONS4. SCREW PLYWOOD (MAXSPACING 12" OC)PAINT DUST WALLS TO MATCH ADJACENT IF DUST WALLS TO BE IN PLACE MORE THAN TWO WEEKS. COORDINATE WITH WALMART CONSTRUCTION MANAGERDEMO AREASALES2x4 TREATED WOODSILL PLATECONTINUOUS SEALANT BOTH SIDES OF SILL PLATE2x4 STUDS @ 24"OC (TYPICAL)EXISTING WALL TOREMAIN1/2" C/D EXT. PLYWOOD SCREWED TO STUDS OVER 6 MIL CLEAR POLY SHEETS2x WOOD PLATECONTINUOUS SEALANTNOTE:THE GENERAL CONTRACTOR SHALL REPAIR/REPLACE ANY DAMAGED FLOOR TILE DUE TO INSTALLATION OR REMOVAL OF TEMPORARY SECURITY ENCLOSURE.MAX2'-0"EXISTING OPENING3'-0"MINPAINT DUST WALLS TO MATCH ADJACENT IF DUST WALLS TO BE IN PLACE MORE THAN TWO WEEKS. COORDINATE WITH WALMART CONSTRUCTION MANAGERDUST DRAPEROOF DECKDUST DRAPEDEMO AREACONTINUOUS 2"x4"DUST DRAPE HOLD DOWN2x4 TOP PLATE2x4 STUD AT 96" OC2x4 BRACE AT 96" OCCONTRACTORS OPTIONON ATTACHMENT2x4 BOTTOMPLATEANCHORS AT 96" OC1/2" CD PLYWOODATTACHED TO STUD AT12" OC MAXCONTINUOUS SEALANTBEAD AGAINSTPLYWOOD AND FLOORFLOORDUST DRAPE TO BE 6 MIL. CLEAR POLYSHEETING OVERLAPPED AT JOINTS A MINIMUMOF 2'-0" AND CONTINUOUSLY TAPED JOINTS.ATTACH SHEETING FROM CEILING TO TOP OFBARRIER AS SHOWN FOR A DUSTPROOFCONDITION. IF ATTACHMENT TO CEILING ISIMPOSSIBLE, LIGHT FRAMING SHALL BEINSTALLED WITH SHEETING ATTACHED AROUNDIT TO PROHIBIT DUST PENETRATION4'-0"CONTINUOUS SEALANTBETWEEN BOTTOM EDGE OFFRP AND FINISH FLOORFRP ON 1/2" C/D PLYWOODOVER 6 MIL. POLY CLEARSHEETING FROM FLOOR TOBOTTOM OF FINISH CEILING.INSTALL FULL SHEETS, LONGDIMENSION HORIZONTALEXISTING ROOF DECKWALL TO BE REMOVEDSTUD TRACK. ANCHORAT 48" O.C.EXISTING FINISH CEILINGREMOVE CEILING PANELSAND LIGHTS AT WALLLOCATION. GRID TO REMAIN.SEAL CLEAR SHEETINGAROUND GRIDALL PLYWOOD ON SALESFLOOR SIDE OF PARTITION TO BE PAINTED2 ROWS OF 2X BLOCKINGBETWEEN STUDS. LAP 6 MIL.POLY CLEAR SHEETINGBETWEEN ROWS AND ATTACH@ 24" O.C.METAL STUDS @ 24" O.C.:WALLS UP TO 14':3-5/8" X 22GAWALLS HIGHER THAN 14':6" X 18GADEMO AREA3-5/8" x 22GAMETAL STUDBRACE @ 96"O.C.CONTRACTOR'SOPTION FORATTACHMENTSTUD TRACKATTACHED TO BOTTOMOF DECK AT 48" O.C.CONTINUOUS SEALANT AGAINST TRACKFINISH FLOORNOTE: TYPICAL AT FOOD AREAS WITH CEILINGS / NOT ON AN EXTERIOR WALL2x BLOCKING BETWEENSTUDS, PROVIDE 2XBLOCKING BEHIND EACHHORIZONTAL JOINT IN THEPLYWOOD WALL COVERINGAND ATTACH PLYWOOD TOSTUDS AND BLOCKING AT12"OC MAX, TYPP1314'-0" ALL OTHER LOCATIONS6'-0" @ LOAD BEARINGINSTALL CONTINUOUS LAYER 6 MIL POLY CLEAR SHEETING FROM FLOOR TO ROOF DECK, OVERLAPPED AT JOINTS A MINIMUM OF 2'-0" AND CONTINUOUSLY TAPED AT ALL JOINTS. SEAL VOIDS AT DECKCONTINUOUS SEALANTBETWEEN BOTTOM EDGE OFFRP AND FINISH FLOORFRP ON 1/2" C/D PLYWOODOVER 6 MIL. POLY CLEARSHEETING FROM FLOOR TO8'-0" AFF. INSTALL FULLSHEETS, LONG DIMENSIONHORIZONTALEXISTING ROOF DECKSTUD TRACK. ANCHORAT 48" O.C.DEMO AREA3-5/8" x 22GA METAL STUD BRACE @ 96" O.C. CONTRACTOR'S OPTION FOR ATTACHMENTALL PLYWOOD ON SALESFLOOR SIDE OF PARTITION TO BE PAINTED2 ROWS OF 2X BLOCKINGBETWEEN STUDS. LAP 6 MIL.POLY CLEAR SHEETINGBETWEEN ROWS AND ATTACH@ 24" O.C.STUD TRACKATTACHED TO BOTTOMOF DECK AT 48" O.C.CONTINUOUS SEALANT AGAINST TRACKFINISH FLOORNOTE: TYPICAL WHERE UTILITY TRENCHES ARE CUT IN FLOORS OF FOOD AREASWITHOUT CEILINGS / NOT ON AN EXTERIOR WALLMETAL STUDS @ 24" O.C.:WALLS UP TO 14':3-5/8" x 22GAWALLS HIGHER THAN 14':6" x 18GA2x BLOCKING BETWEENSTUDS, PROVIDE 2XBLOCKING BEHIND EACHHORIZONTAL JOINT IN THEPLYWOOD WALL COVERINGAND ATTACH PLYWOOD TOSTUDS AND BLOCKING AT12"OC MAX, TYPP131108'-0" AFFTOP OF PLYWOODINSTALL CONTINUOUS LAYER 6 MIL POLY CLEAR SHEETING FROM FLOOR TO ROOF DECK, OVERLAPPED AT JOINTS A MINIMUM OF 2'-0" AND CONTINUOUSLY TAPED AT ALL JOINTS. SEAL VOIDS AT DECKarchitecture2809 Ajax Avenue Suite 100Rogers Arkansas 72758Phone: 479.636.3545Fax: 479.636.1209+engineeringArchitect of RecordWilliam Douglas HurleyWashington License No. 8855Unified Business ID No. 602 491 668STIPULATION FOR REUSETHIS DRAWING WAS PREPARED FOR USE ON A SPECIFIC SITE AT:CONTEMPORANEOUSLY WITH ITS ISSUE DATE ON AND IT IS NOT SUITABLE FOR USE ON A DIFFERENT PROJECT SITE OR AT A LATER TIME. USE OF THIS DRAWING FOR REFERENCE OR EXAMPLE ON ANOTHER PROJECT REQUIRES THE SERVICES OF PROPERLY LICENSED ARCHITECTS AND ENGINEERS. REPRODUCTION OF THIS DRAWING FOR REUSE ON ANOTHER PROJECT IS NOT AUTHORIZED AND MAY BE CONTRARY TO THE LAW.DRAWN BY:CHECKED BY:DOCUMENT DATE:PROTO:SUPER BUNDLEPROTO CYCLE:DOCUMENTS THAT DO NOT HAVE THE ARCHITECT OR ENGINEER OF RECORD SEAL AND SIGNATURE SHALL BE CONSIDERED NOT FOR CONSTRUCTIONSHEET:ISSUE BLOCKYELM, WASHINGTON03/11/2020YELM, WASHINGTONSTORE NO.3705-232JOB NUMBER: 2019.0835ECJT17601/31/202003/11/2020DEMOLITIONDETAILSD1.1 3/4" = 1'-0"1DUST WALL SECTION 3/4" = 1'-0"2SECURITY ENCLOSURE 3/4" = 1'-0"5TEMPORARY BARRIER/DUST DRAPE 3/4" = 1'-0"4TEMPORARY FRP CLAD BARRIER/DUST DRAPE 3/4" = 1'-0"3TEMPORARY FRP CLAD TRENCHBARRIER/DUST DRAPE