R0-01 - Civil Plan Review Checklist3/2/2020 New Submission
https://lf.yelmwa.gov/Forms/CivilPR 1/6
STANDARD ITEMS: WATER, SANITARY SEWER,
STORM SEWER, STREET, LIGHTING, AND SIGNALS
( ) Vicinity Map
( ) Legend (APWA Standard Symbols)
( ) North Arrow
( ) Scale Bar
( ) Datum - Bench Mark Elevation And Location (on all sheets where
elevations are referenced)
( ) Title Block:
( ) Title: APPROVED FOR CONSTRUCTION
( ) Design By:
( ) Drawn By:
( ) Date:
( ) Checked By:
( ) Signature Approval Block
( ) Sheet Number of Total Sheets:
( ) Section, Township and Range (every plan/profile sheet)
( ) Engineers Stamp (signed and dated)
( ) Project Title (cover sheet)
( ) Utility System Map (showing all proposed utilities on one drawing)
( ) Revision Block
PLAN PORTION STANDARD ITEMS
( ) Center line and Stations
( ) Edge of Pavement and Width
( ) Right-of-Way and Width
( ) Proposed Survey Monumentation Locations and Details
( ) Sidewalk and Width
( ) Roadway Sections
( ) Existing Utilities (above and below ground)
( ) Adjacent Property Lines, Ownership, Parcel Number, and Street Address
( ) Identify Street Names, Right-of-Way, Lots
( ) Identify Match Existing Sheet Numbers and Stations
( ) Easements, Width and Type
( ) Define Survey Baselines
( ) Stations for Structures
( ) Flow Direction Arrows
PROFILE PORTION STANDARD ITEMS
3/2/2020 New Submission
https://lf.yelmwa.gov/Forms/CivilPR 2/6
( ) Profile Grades (decimal FT./FT.)
( ) Existing Ground
( ) Scale (horizontal and vertical)
( ) Stationing
( ) Vertical Elevation Increments
( ) Existing Utilities (if available)
Misc.
( ) Detail Sheet
( ) General Notes
SANITARY SEWER
Plan View: (Gravity System)
( ) Manhole
( ) Station Shown at Each Manhole (watch spacing)
( ) Manholes Numbered
( ) Manhole Type Designation
( ) Flow Direction (with arrow on pipe)
( ) Depth at Property Line and Distance from Downhill Manhole for
Side Sewer
( ) Distance from Water Lines
( ) Service to Each Lot
Profile View:
( ) Manholes Numbered
( ) Invert Elevation Showing Direction, In and Out
( ) Gravity
( ) Grades Shown (decimal form FT./FT.) slopes, depths
( ) Type of Pipe
( ) Size of Pipe
( ) Length of Pipe (in L.F.)
( ) Existing Utilities Shown
STEP SYSTEM
( ) Pipe Alignment, grade and offset, type and size
( ) Location of water, utilities crossing
( ) Location of pigging ports
( ) Location of pressure sustaining valves, check valves,
vacuum valves, pressure relief valves, gate valves
( ) Trench and restoration details showing depth,
bedding compaction requirements
( ) Septic (STEP) Tank
3/2/2020 New Submission
https://lf.yelmwa.gov/Forms/CivilPR 3/6
( ) Inverts elevation
( ) Size, type, location
( ) Side sewer location
( ) Electrical hookups
( ) Alarm and controls
( ) Pump operational characteristics
( ) Pump type
Misc.:
( ) Detail Sheet
( ) Sewer General Notes
WATER
Plan View:
( ) System Map (1” = 300’) showing existing and proposed with line size,
valves, and hydrants
( ) Existing Utility Conflicts
( ) Fixtures (need horizontal and vertical control)
( ) Fire Hydrants (at all intersections. See Yelm Fire District #2)
( ) Blow-off (at end of line)
( ) Vacuum and Air Release Valves When Required
( ) Tees, Crosses, Elbows, Adapters and Valves Need Coupling Type,
Meter Locations
( ) Valves (2 each tee, 3 each cross)
( ) Fire Department Connection
( ) Thrust Blocking Required at all Fittings Including In-Line Valves
( ) Distance from Sewer
( ) Service to Each Lot (include open tracts)
Profile View:
( ) Existing Utility Crossings
( ) Show Fixtures (tees, crosses, hydrants)
( ) Show Valves and Couplers
( ) Size of Water-main
( ) Length of Water-main (in L.F.)
( ) Cover Over Pipe
( ) Grades (Engineered Design Grade to F.L.)
Misc.
( ) Detail Sheet
( ) Water General Notes
STORM SEWER
( ) Drainage and Erosion Control Plan Report
( ) Cover sheet
( ) Table of Contents
( ) Section 1 - Proposed Project Description
( ) Section 2 - Existing Conditions
( ) Section 3 - Infiltration Rates/Soils Report
( ) Section 4 - Wells
( ) Section 5 - Fuel Tanks
( ) Section 6 - Sub-Basin Description
( ) Section 7 - Analysis of the 100-Year Flood
( ) Section 8 - Aesthetic Considerations for Facilities
( ) Section 9 - Downstream Analysis
( ) Section 10 - Covenants, Dedications, Easements
( ) Section 11 - Homeowners - Articles of Incorporation
( ) Project Engineers Certificate
( ) Facility Summary Form
( ) Engineer ’s Estimate
( ) Erosion Control Plan Report
( ) Section 1 - Construction Sequence and Procedure
( ) Section 2 - Trapping Sediment
3/2/2020 New Submission
https://lf.yelmwa.gov/Forms/CivilPR 4/6
( ) Section 3 - Permanent Erosion Control and Site Restoration
( ) Section 4 - Geotechnical Analysis and Report
( ) Section 5 - Inspection Sequence
( ) Drawings and Specification
( ) Vicinity map
( ) Project Boundaries
( ) Sub-Basin Boundaries
( ) Off-Site Area Tributary to Project
( ) Contours
( ) Major Drainage Features
( ) Flow Path
( ) Site Map
( ) Existing Topography at Least 50 Feet Beyond Site Boundaries
( ) Finished Grades
( ) Existing Structures within 100 Feet of Project Boundary
( ) Utilities
( ) Easements, Both Existing and Proposed
( ) Environmentally Sensitive Area
( ) 100-Year Flood Plain Boundary
( ) Existing and Proposed Wells within 1,200 feet of Proposed
Retention Facility
( ) Existing and Proposed Fuel Tanks
( ) Existing and Proposed On-Site Sanitary Systems within 100 Feet
of Detention/Retention Facilities
( ) Proposed Structures Including Roads and Parking Surfaces
( ) Lot Dimensions and Areas
( ) Proposed Drainage Facilities and Sufficient Cross-Section and
Details to Build
( ) Plan View - Conveyance System
( ) Station and Number at each Manhole/Catch Basin
( ) Manhole/Catch Basin Type and Size
( ) Manhole/Catch Basin Rim Elevation
( ) Flow Direction with Arrow on Pipe/Channel
( ) Type and Size of Pipe
( ) Length of Pipe in Lineal Feet
( ) Profile View - Conveyance System
( ) Station and Number at each Manhole/Catch Basin
( ) Rim Elevation
( ) Invert In and Out
( ) Length of Pipe (in L.F.)
( ) Grades (FT./FT.)
( ) Design Velocity
( ) Work Map
( ) Unit Areas (including Off-Site Contributing Areas)
( ) Percentage Impervious
( ) Average Slope
( ) Estimated Ultimate Infiltration Rate
( ) Conveyance Date, Identifier (for Reference to Model Output),
Length, Slope, Inverts
( ) Overland Flow Paths and Distances
( ) Soil Types
( ) Spot Water Surface Elevations, Discharges and Velocities for the
Design Event
( ) Erosion Control Drawing
( ) Soil Types
( ) Locations of Soil Pits and Infiltration Tests
( ) Construction Entrance Detail
( ) Silt Fences and Traps
( ) Mulching and Vegetation Plan
( ) Clearing and Grubbing Limits
( ) Existing and Finished Grade
3/2/2020 New Submission
https://lf.yelmwa.gov/Forms/CivilPR 5/6
( ) Details and Locations of all BMPs Recommended
( ) Location and Details of Temporary Sediment Ponds
( ) Maintenance Report
( ) Required Type and Frequency of Long-Term Maintenance
( ) Identification of Responsible Maintenance Organization
( ) Frequency of Sediment Removal
( ) Cleaning of Catch Basins
( ) Vegetation Control
( ) Annual Cost Estimate of Maintenance
( ) Construction Inspection Report
Misc.
( ) Detail Sheet
( ) Storm General Notes
STREET
Plan View:
( ) Flow Direction Arrows at Curb Returns Showing Grade
( ) Spot Elevations on Curb Returns
( ) Station PC, PT, PI, and Intersections
( ) Curve Information Delta, Radius, Length and Tangent
( ) BCR and ECR (Begin Curb Radius, End Curb Radius)
( ) Identify All Field Design Situations
( ) Typical Sections
( ) Pavement Marking Details With Station and Offset
( ) Sidewalks
( ) Driveway Entrances
( ) Station
( ) Width, Material ( AC, PCC)
( ) Driveway Type
( ) Curb Ramps - Detail and Type
( ) Public Transit Facilities and Bus Stops
Profile View:
( ) Vertical Information VPI, BVC, EVC, AP, Low Point, High Point
( ) Show Grades in Decimal Form with (+ or -) Slope
( ) Super Elevated Roadways
( ) Detail - Show Transitions
( ) Special Detail Showing Gutter Flowing Adequately
Misc.
( ) Detail Sheet
( ) Street General Notes
( ) AASHTO Street Design Worksheet, With Soils Report, if Applicable
ILLUMINATION AND SIGNALS
( ) Lighting
( ) Station and Offset to Fixtures
( ) Pole Type, including Manufacturer
( ) Mounting Height, Arm Length, Anchor Bolt Size and Pattern
( ) Power Source
( ) Wire size, Type, Conduit
( ) Line Loss Calculations
( ) Luminaire Type, Lamp Wattage
( ) Location of Service Disconnects (5% Max. Voltage Drop from
Source to Farthest Luminaire)
( ) J-Box Location (include station and offset)
( ) Signals (Follow WSDOT Specs Unless Otherwise Required by the
City)
( ) Station and Offset to Signal Base, Cabinets, Ped. Lead, Loops, etc.
( ) Wiring Schedule
( ) Signal Heads and Mounting Assembly
( ) Detection Loops
( ) Opticom
( ) Control Cabinet, Size and Layout
( ) Power Source
3/2/2020 New Submission
https://lf.yelmwa.gov/Forms/CivilPR 6/6
( ) Conduit
( ) Wire Size and Type
( ) Construction Notes
( ) J-Box Schedule
( ) Pedestrian Signal Type with Push Button
( ) Controller Type, Configuration, and Wiring Schematic
Misc.
( ) Detail Sheet
( ) Lighting General Notes
( ) Line Loss Calculations
MISCELLANEOUS
( ) Easements and/or Dedication Deeds
( ) Contract Documents/Specifications
Additional Items:
( ) Sheet Index (on title sheet if required)
( ) Field Verify Note on DWG - Expose Connection Points And Verify Fittings
48 Hours Prior To Distributing shut-Down Notices
( ) Call Before You Dig Note
( ) Signing - Temporary And Permanent
( ) Channelization
( ) Location of Cluster Mailboxes
Applicant
Agreement:*
I have read the above Application Requirements and understand that there is a $250.00 deposit fee
required before review of my application.
I Agree