20190034 Sewer Site Plan APPROVED
Sewer service needsto be tapped into the4" main coming offNP RD. Sewer tapmust be done byprofessional tappingservice
Water and Reclaimed Water mainsin this area run along property linemust have 10' minimum separationfrom STEP tank. Sewer service linesin traffic areas must be sleeved withpressure pipe
and or when with in 10'of water or reclaimed water.
Must have a 6" diameter sidesewer and 6" inlet baffle witha 2 way clean out installed2.5' from foundation. Propertyowner is responsible for theside sewer to the tank. Sidesewer pictured
is in a trafficarea that supports heavytrucks.
Tank needs 5' setback fromfence and must be protected bybollards or be an H20 trafficrated tank with traffic bearing lids
control panel for review.
system by the City of Yelm.
place for a commercial STEP
guidelines and specifications in
This is considered a commercial
Need proposed location of pump
STEP System and must follow the