2021.0018 Yelm Development Geotechnical ReportEarth Science + Technology
Geotechnical Engineering Services Report
Yelm Development
Yelm, Washington
for
D&B Retail Development
September 14, 2015
Geotechnical Engineering Services Report
Yelm Development
Yelm, Washington
for
D&B Retail Development
September 14, 2015
1101 South Fawcett Avenue, Suite 200
Tacoma, Washington 98402
253.383.4940
Geotechnical Engineering Services Report
Yelm Development
Yelm, Washington
Prepared for:
D&B Retail Development
6402 Tacoma Mall Blvd.
Tacoma, Washington 98409
Attention: Dale Pinney
Prepared by:
GeoEngineers, Inc.
1101 South Fawcett Avenue, Suite 200
Tacoma, Washington 98402
253.383.4940
Basel Kitmit
Geotechnica Engineer
`nnis (D,3� Thompson, PE
nior Geotechnical Engineer
BK:DJT:tt
File No. 22013-001-00
September 14, 2015
Disclaimer: Any electronic form, facsimile or hard copy of the original document (email, text, table, and/or figure), if provided, and any attachments are only a copy
of the original document. The original document is stored by GeoEngineers, Inc. and will serve as the official document of record.
GWENGINEER�
September 14, 2015 | Page i
File No. 22013-001-00
Table of Contents
INTRODUCTION AND PROJECT UNDERSTANDING ................................................................................................. 1
SCOPE OF SERVICES ............................................................................................................................................... 1
SITE CONDITIONS ..................................................................................................................................................... 2
Published Literature ............................................................................................................................................ 2
Surface Conditions............................................................................................................................................... 3
Subsurface Explorations ...................................................................................................................................... 3
Subsurface Conditions ........................................................................................................................................ 3
General .......................................................................................................................................................... 3
Soil Conditions .............................................................................................................................................. 3
Groundwater Condition ................................................................................................................................. 4
CONCLUSIONS AND RECOMMENDATIONS ............................................................................................................ 4
General ................................................................................................................................................................. 4
Stormwater Infiltration ......................................................................................................................................... 4
General .......................................................................................................................................................... 4
Soil Infiltration Rates .................................................................................................................................... 5
Site Development and Earthwork ....................................................................................................................... 6
General .......................................................................................................................................................... 6
Clearing and Stripping .................................................................................................................................. 6
Temporary Excavations, Support and Dewatering ...................................................................................... 6
Permanent Cut and Fill Slopes ..................................................................................................................... 7
Surface Drainage .......................................................................................................................................... 7
Erosion and Sedimentation Control ............................................................................................................. 7
Subgrade Preparation and Evaluation ......................................................................................................... 8
Subgrade Protection and Wet Weather Considerations ............................................................................. 8
Fill Materials ......................................................................................................................................................... 9
General .......................................................................................................................................................... 9
Select Granular Fill ........................................................................................................................................ 9
On-Site Soil .................................................................................................................................................... 9
Fill Placement and Compaction ....................................................................................................................... 10
General ....................................................................................................................................................... 10
Area Fills and Bases ................................................................................................................................... 10
Trench Backfill ............................................................................................................................................ 10
Seismic Design Considerations ........................................................................................................................ 10
General ....................................................................................................................................................... 10
Seismic Design Criteria .............................................................................................................................. 11
Liquefaction Potential ................................................................................................................................ 11
Shallow Foundations ........................................................................................................................................ 11
Foundation Support ................................................................................................................................... 11
Bearing Capacity ........................................................................................................................................ 12
Foundation Drains ...................................................................................................................................... 12
Footing Bearing Surface Preparation ........................................................................................................ 12
Foundation Settlement .............................................................................................................................. 12
September 14, 2015 | Page ii
File No. 22013-001-00
Lateral Resistance ..................................................................................................................................... 13
Conventional Subgrade and Retaining Walls .................................................................................................. 13
Drainage ..................................................................................................................................................... 13
Design Parameters .................................................................................................................................... 13
Building Pads and Floor Slabs ......................................................................................................................... 14
Pavement Recommendations .......................................................................................................................... 14
Asphaltic Concrete Pavement ................................................................................................................... 14
LIMITATIONS .......................................................................................................................................................... 15
LIST OF FIGURES
Figure 1. Vicinity Map
Figure 2. Site Plan
APPENDICES
Appendix A. Field Explorations and Laboratory Testing
Figure A-1. Key to Exploration Logs
Figures A-2 through A-11. Logs of Test Pits
Figures A-12 and A-13. Sieve Analysis Results
Appendix B. Report Limitations and Guidelines for Use
September 14, 2015 | Page 1
File No. 22013-001-00
INTRODUCTION AND PROJECT UNDERSTANDING
GeoEngineers is pleased to present this geotechnical report to support development and construction of
the proposed Yelm Development project located at 1301 Yelm Avenue East in Yelm, Washington as shown
in Figure 1. Our understanding of this project is based on our discussions with you and/or members of your
design team, including Larson and Associates (project civil engineers), and review of conceptual plans
provided.
Based on review of aerial photographs and on-site observations, the parcel is generally flat, removed of
trees and is surfaced with grass vegetation. Abandoned single family homes surround the property in the
south, east and west. The property is irregular in shape; the overall size is on the order of 3.7 acres. The
property is divided into three lots as shown on our Site Plan, Figure 2.
We understand that three retail buildings and a surrounding parking lot area are proposed for and will cover
the majority of the site. The proposed structures will consist of single-story retail shopping and restaurant
type buildings. The exterior walls and interior columns will be supported by conventional spread footings.
Stormwater for each retail building and the parking lot area will be handled by underground infiltration
trenches that will generally be located in the southwest portion of the parcel behind the proposed
developments. We understand that the stormwater infiltration trenches within Lots 1 and 3 will be located
at depths of approximately 5 to 7 feet below ground surface (bgs) and at a depths of approximately 9 to
10 feet bgs within Lot 2. The Washington State Department of Ecology (Ecology) 2012 Stormwater
Management Manual for Western Washington (SWMMWW) Volume III will be used as a guideline for
stormwater design, including stormwater infiltration. Additional improvements include asphalt concrete
parking and installation of underground utilities.
SCOPE OF SERVICES
The purpose of our services was to evaluate soil and groundwater conditions as a basis for developing
recommendations to support the proposed site improvements and to determine infiltration characteristics
of the underlying soil. Our specific scope of services for this study includes:
1. Reviewing existing in-house information on subsurface conditions.
2. Visiting the site, marking out, identifying potential test pit locations and coordinating clearance of
existing utilities.
3. Exploring subsurface conditions at the site by conducting 10 test pit explorations. The test pits were
located around the proposed structures and within proposed infiltration areas (note that the SWMMWW
requires a minimum of two test pits per infiltration facility or trench). Eight test pits were excavated to
depths of approximately 10 to 12-feet and two test pits were excavated to depths of approximately 15
to 16 feet.
4. Performing laboratory tests consisting of eight grain-size analyses on selected soil samples obtained
from the test pits.
5. Providing a discussion of the surface and subsurface conditions encountered.
September 14, 2015 | Page 2
File No. 22013-001-00
6. Providing an estimate of infiltration rate(s) of soil collected in the explorations. Our estimate(s) are
based on the laboratory grain-size analysis and requirements presented in the 2012 SWMMWW.
7. Providing geotechnical seismic design information in accordance with International Building Code (IBC)
criteria and discussing our opinion on the potential for liquefaction.
8. Providing recommendations for design of shallow foundations including recommendations for
foundation design, including bearing surface preparation, removal of uncontrolled fill, soft, organic or
otherwise unsuitable material, backfill compaction and drainage recommendations. We include
recommendations for allowable bearing capacity, estimates of settlement, and lateral resistance.
9. Providing recommendations for conventional below-grade building walls and retaining wall structures,
including allowable soil bearing pressures, settlement (total and differential) estimates, lateral earth
pressures (seismic, active and passive) and coefficient of friction for evaluating sliding resistance. We
also discuss backfill material and compaction requirements and drainage recommendations.
10. Providing recommendations for support of on-grade floor slabs, including modulus of subgrade
reaction, capillary break, vapor retarder and underslab drainage, as appropriate.
11. Providing a recommended asphalt concrete pavement (ACP) section based on our experience and
typical practice in this area.
12. Providing recommendations for site preparation and earthwork. We discuss clearing and stripping,
temporary and permanent cut slopes, suitability of on-site soils for use as structural fill, specifications
for imported soil for use as structural fill, wet weather considerations for earthwork and fill placement
and compaction requirements.
13. Providing recommendations for site drainage and control of groundwater that may be encountered.
14. Preparing a geotechnical report commensurate with the scope described above. Our report presents
our findings and recommendations and including summary logs of the explorations and a plan view
showing the exploration locations.
SITE CONDITIONS
Published Literature
Based on review of geologic maps in our files, Vashon recessional outwash sand and gravel is the dominant,
near-surface, geologic material mapped in the immediate project area. This material is commonly known
as Steilacoom gravel. Vashon recessional outwash was deposited by melt water streams in front of the
most recent glacier during its retreat from the Puget Sound region approximately 10,000 to 15,000 years
ago. These deposits generally consist of permeable sand, or sand and gravel. Cobbles and boulders can
also be encountered in this deposit, depending on the depositional history. Glacial till and/or advance
outwash is commonly encountered at depth below the recessional outwash.
The United States Department of Agriculture (USDA) Soil Conservation Service (SCS) Soil Survey of Pierce
County Area, Washington, maps the project area as Spanaway gravelly sandy loam, 0 to 3 percent slopes
(110). This soil unit is described as being formed in glacial outwash. It is further described as generally
having positive soil characteristics for small commercial buildings. These characteristics include but are
not limited to being somewhat excessively drained, little erosion hazard, and low resistance to compaction.
However, this soil unit is described as being “very limited” in regards to shallow excavations (i.e., trenches
September 14, 2015 | Page 3
File No. 22013-001-00
or holes excavated to a maximum depth of 5 to 6 feet below ground surface) and will potentially require
“major soil reclamation, special design, or expensive installation procedures”. We interpret part of this
statement to refer to the potential for excessive caving of sidewalls that may occur during excavation below
grade and accompanying shoring, trench boxes, or similar soil support options.
Surface Conditions
The project area is located west of the intersection of East Yelm Avenue, Bald Hill Road SE, and Creek
Street SE in Yelm, Washington. The project area is irregular in shape and is flat or slightly sloping down to
the northwest. A paved road loops around the interior of the site giving access to residences that bordered
the western, southern and eastern perimeter of the site. The residences are abandoned and some of the
structures that are visible from aerial photographs have been removed. A gas line was noted to exist
between the access road and the front of the abandoned residences. Vegetation in the majority of the
property is low growing grasses. Trees of various sizes exist along the perimeter of the property. We did not
observe standing water or indications of wet surface conditions during our time on site.
Subsurface Explorations
Our understanding of subsurface conditions at the project site is based on conditions disclosed in 10 test
pits excavated at the approximate locations shown in Figure 2. Details of the exploratory program,
laboratory testing program and test pit logs completed for this study are presented in Appendix A.
Subsurface Conditions
General
We categorized soil layers encountered in our explorations into the following units in the order in which they
are generally encountered: a weathered outwash, an upper outwash, and a lower outwash. The upper
outwash was present within all test pit locations except in TP-7 where the lower outwash was overlain by
the weathered outwash. Grass or sod and significant organics are typically present within the top 3 to
6 inches of the explorations. The weathered outwash generally is in a loose to medium dense condition and
consists of silty sand with gravel, gravel with silt and sand and occasional organic material. The upper
outwash generally is in a medium dense condition and consists of one or more layers of gravel with sand
and occasional cobbles (up to 1 foot in diameter), silty sand, and sand with silt. The lower outwash generally
is in a medium dense to dense condition and consists of gravel with sand and occasional cobbles up to
and potentially greater than 1 foot in diameter. All the explorations terminated in the lower outwash.
Soil Conditions
We observed approximately 3 inches of sod at the surface in all of the explorations with the exception of
test pits TP-2, TP-3 and TP-4. TP-2 surface soils consisted of a 3-inch layer of gravel base rock that is present
along the shoulder of the existing northwestern access road. Weathered outwash was observed at the
ground surface of test pit locations TP-3 and TP-4.
In TP-1 through TP-4 and TP-8 the weathered outwash is present from the below the ground surface, sod,
or gravel base and extends approximately to depths of 2 to 3.5 feet bgs. The weathered outwash overlies
the upper outwash. The upper outwash extends approximately to depths of 6 to 7 feet bgs. We did not
observe the upper outwash in TP-7, only the lower outwash unit. The lower outwash extends to the full
depths explored in the test pit explorations.
September 14, 2015 | Page 4
File No. 22013-001-00
In TP-5, TP-6, TP-9 and TP-10 the weathered outwash extends approximately to depths of 2 and 3 feet bgs.
The weathered outwash overlies the upper outwash and extends approximately to depths of 7 and 8 feet.
The lower outwash extends to the bottom of the test pit explorations.
Groundwater Condition
No groundwater seepage was observed during our explorations. Ecology’s reports for monitoring wells
completed in the project vicinity were reviewed and indicated static groundwater is encountered at depths
between 26 feet and 59 feet bgs at the well locations. Based on our observations, and review of Ecology’s
reports for monitoring wells combined with the relatively flat topography of the surrounding area, static
groundwater elevation is expected to be well below the depths of the test pit explorations completed for
this project. Groundwater conditions should be expected to vary as a result of season, precipitation and
other factors. Depending on the time of year, it is possible that some groundwater seepage may be
encountered below or within the weathered outwash.
CONCLUSIONS AND RECOMMENDATIONS
General
Based on the results of our study, it is our opinion that the site is generally suitable for the proposed
development with regard to geotechnical considerations. A summary of the primary geotechnical
considerations for the proposed development is provided below, and is followed by our detailed
recommendations.
■ Granular soils were generally encountered; however, we did observe that some of the near-surface site
soil has a higher fines (silt and clay-sized particles passing the U.S. Standard No. 200 sieve) content.
Soil with a higher fines content is more sensitive to small changes in moisture content and may be
difficult, if not impossible, to work and compact during wet weather conditions. This material can also
be susceptible to disturbance from construction traffic when wet, or if earthwork is performed during
wet weather.
■ The proposed structures may be satisfactorily supported on continuous and isolated shallow
foundations supported on the well compacted weathered outwash or the medium dense or dense
native soils or on structural fill that extends to these soils.
■ Floor slabs may be supported on well compacted weathered outwash or the underlying outwash soils.
■ The glacial outwash deposits can contain cobbles and boulders. The contractor should be prepared for
this possibility.
■ On-site stormwater infiltration appears feasible based on the subsurface conditions observed. Greater
infiltration rates will likely be obtained at depth. We provide preliminary infiltration rate
recommendations below.
Stormwater Infiltration
General
Soil consisting of the lower outwash material is typically encountered below Elevation 344.5 feet to 342 feet
in the explorations completed in the project area. In general, it is our opinion that the natural soils
encountered in the lower outwash within our explorations should have adequate permeability to infiltrate
September 14, 2015 | Page 5
File No. 22013-001-00
stormwater from the site. We did not encounter groundwater seepage, staining or other indications of
seasonal shallow groundwater in the explorations.
Soil Infiltration Rates
Stormwater infiltration rates for the site soils were established based on the 2012 Ecology SWMMWW
Volume III in conjunction with the sieve analysis results presented in Appendix A, Figures A-12 and A-13.
TABLE 1. SOIL INFILTRATION RATES1
Test Pit
No.
Soil Sample
No.
Soil Sample
Elevation
(feet)
Percent
Fines2
D10 Size
(mm)3
USCS4 Soil
Classification
Recommended
Long-term Design
Infiltration Rate5
(Inches per Hour)
1 1 345.5 12.5 N/D SM 2(6)
1 2 341 2 0.8 GP 20(7)
2 3 337.5 2 0.52 GW 20(7)
3 2 339.5 1 10.7 GW 20(7)
4 3 336.5 1 0.79 GP 20(7)
5 2 345.5 13.4 N/D SM 2(6)
5 3 342 2 0.87 GP 20(7)
6 2 342 2.3 0.68 GP 20(7)
Notes:
1 For selected soil samples.
2 Fines = Silt and clay-sized particles passing U.S. No. 200 (0.75 mm) sieve.
3 Based on ASTM C 136 Soil Gradation Test.
4 Unified Soil Classification System (USCS).
5 Based on grain-size analysis and the procedures outlined in the 2012 Ecology SWMMWW Volume III Table 3.8.
6 Design infiltration rate determined using USDA soil texture method provided in the 2005 Department of Ecology Stormwater
Management Manual.
7 Calculated infiltration rates were greater than presented and were limited to 20 inches per hour.
We completed explorations within the areas of the infiltration trench locations indicated on the plans
provided by Larson and Associates, Inc. We expect that the relatively clean gravel soils encountered in the
test pits should have adequate permeability and storage capacity to infiltrate stormwater. We recommend
that a long-term design infiltration rate of 20 inches per hour be used for sizing facilities located within the
lower outwash below approximate Elevations 344.5 feet to 342 feet. The value(s) presented above are for
the specific samples tested and are an estimate of subsurface infiltration properties at various depths. We
recommend that the project plans include provisions for GeoEngineers to observe subsurface conditions
during construction to check that the preliminary infiltration rate(s)and soil conditions used for design are
appropriate for the conditions encountered. Site- and location- specific testing may also be required by local
jurisdictions.
Stormwater should be treated in accordance with current regulations prior to infiltration. To help reduce
clogging of infiltration facilities, we recommend they be protected during construction with siltation control
facilities such as temporary settling basins, silt fences and hay bales. Suspended solids can clog the soil
and reduce the infiltration rate. Periodic sweeping of paved areas, during and following construction, will
September 14, 2015 | Page 6
File No. 22013-001-00
help extend the life of the infiltration facilities. Equipment should not be permitted in the infiltration areas
after they are excavated to grade because of the potential for compaction of the subgrade that could reduce
the infiltration rate of the soil.
Site Development and Earthwork
General
We anticipate that site development and earthwork will include clearing and stripping of surface vegetation,
constructing foundations and then placing and compacting fill and backfill materials. We expect that the
majority of site grading can be accomplished with conventional earthmoving equipment. The following
sections provide recommendations for stripping, excavation, erosion control, subgrade development, fill
materials, fill placement and compaction.
Clearing and Stripping
Based on our observations at the site, we estimate that the depth of stripping could be on the order of
3 inches to 1 foot. For estimating purposes we suggest a depth of stripping of 6 inches. Greater stripping
depths may be required to remove localized zones of loose or organic-rich soil. In addition, demolition
around existing structures may cause localized disturbance and require greater stripping depths. The
primary root systems of shrubs should be completely removed. Stripped material should be transported off
site for disposal or processed and used as fill in landscaping areas.
We did encounter cobbles/boulders during our subsurface investigation, confirming our experience that
cobbles/boulders can be present in the glacial deposits in the area. Accordingly, the contractor should be
prepared to remove cobbles/boulders, if encountered during grading or utility excavations. Boulders may
be removed from the site or buried in landscape areas. Voids caused by boulder removal should be
backfilled with structural fill.
Temporary Excavations, Support and Dewatering
Excavations deeper than 4 feet should be shored or laid back at a stable slope if workers are required to
enter. Shoring and temporary slope inclinations must conform to the provisions of Title 296 Washington
Administrative Code (WAC), Part N, “Excavation, Trenching and Shoring.” Regardless of the soil type
encountered in the excavation, shoring, trench boxes or sloped sidewalls will be required under Washington
Industrial Safety and Health Act (WISHA). The contract documents should specify that the contractor is
responsible for selecting excavation and dewatering methods, monitoring the excavations for safety and
providing shoring, as required, to protect personnel and structures. We provide additional
recommendations in regard to temporary and permanent shoring below.
In general, temporary cut slopes should be inclined no steeper than about 1-1/2H:1V (horizontal:vertical).
This guideline assumes that all surface loads are kept at a minimum distance of at least one-half the depth
of the cut away from the top of the slope and that seepage is not present on the slope face. Flatter cut
slopes will be necessary where seepage occurs or if surcharge loads are anticipated. We observed caving
in our explorations; therefore, some sloughing and raveling of cut slopes should be expected. Temporary
covering with heavy plastic sheeting should be used to protect these slopes during periods of wet weather.
Based on our explorations, we do not expect groundwater to be a major factor during shallow excavations
and earthwork. However, some perched groundwater could occur in the near-surface soil depending on the
September 14, 2015 | Page 7
File No. 22013-001-00
time of year of construction. We anticipate that groundwater handling needs will typically be lower during
the late summer and early fall months. We anticipate that shallow perched groundwater can typically be
handled adequately with sumps, pumps, and/or diversion ditches, as necessary. Ultimately, we recommend
that the contractor performing the work be made responsible for controlling and collecting groundwater
encountered.
Permanent Cut and Fill Slopes
Based on site grades and the proposed construction, we anticipate that only minor cutting and filling will
be required for this project. However, if permanent slopes are necessary, we recommend they be
constructed at a maximum inclination of 2H:1V. Where 2H:1V permanent slopes are not feasible, protective
facings and/or retaining structures should be considered.
To achieve uniform compaction, we recommend that fill slopes be overbuilt slightly and subsequently cut
back to expose well-compacted fill. Fill placement on slopes steeper than 5H:1V should be benched into
the slope face and include keyways. The configuration of the bench and keyway depends on the equipment
being used. Bench excavations should be level and extend into the slope face. We recommend that a
vertical cut of about 3 feet be maintained for benched excavations. Keyways should be about 1-1/2 times
the width of the equipment used for grading or compaction.
Exposed areas should be re-vegetated as soon as practical to reduce the surface erosion and sloughing.
Temporary protection should be used until permanent protection is established.
Surface Drainage
Surface water from roofs, driveways and landscape areas should be collected and controlled. Curbs or
other appropriate measures such as sloping pavements, sidewalks and landscape areas should be used
to direct surface flow away from the buildings, erosion sensitive areas and from behind retaining structures.
Roof and catchment drains should not be connected to wall or foundation drains.
Erosion and Sedimentation Control
Potential sources or causes of erosion and sedimentation can be influenced by construction methods, slope
length and gradient, amount of soil exposed and/or disturbed, soil type, construction sequencing and
weather. Implementing an erosion and sedimentation control plan will reduce the project impact on erosion-
prone areas. The plan should be designed in accordance with applicable city, county and/or state
standards. The plan should incorporate basic planning principles, including:
■ Scheduling grading and construction to reduce soil exposure.
■ Re-vegetating or mulching denuded areas.
■ Directing runoff away from denuded areas.
■ Reducing the length and steepness of slopes with exposed soils.
■ Decreasing runoff velocities.
■ Preparing drainage ways and outlets to handle concentrated or increased runoff.
■ Confining sediment to the project site.
September 14, 2015 | Page 8
File No. 22013-001-00
■ Inspecting and maintaining control measures frequently.
Some sloughing and raveling of exposed or disturbed soil on slopes should be expected. We recommend
that disturbed soil be restored promptly so that surface runoff does not become channeled.
Temporary erosion protection should be used and maintained in areas with exposed or disturbed soils to
help reduce erosion and reduce transport of sediment to adjacent areas and receiving waters. Permanent
erosion protection should be provided by paving, structure construction or landscape planting.
Until the permanent erosion protection is established and the site is stabilized, site monitoring may be
required by qualified personnel to evaluate the effectiveness of the erosion control measures and to repair
and/or modify them as appropriate. Provision for modifications to the erosion control system based on
monitoring observations should be included in the erosion and sedimentation control plan.
Subgrade Preparation and Evaluation
Subgrade areas should be thoroughly compacted with heavy, smooth-drum vibratory equipment to a
uniformly dense and unyielding condition prior to placement of structural fill or structural elements. We
recommend that prepared subgrades be observed by a member of our firm, who will evaluate the suitability
of the subgrade and identify any areas of yielding, which are indicative of soft or loose soil. The exposed
subgrade soil should be proof-rolled with heavy rubber-tired equipment or probed with a 1/2-inch-diameter
steel rod, as appropriate depending on prevailing conditions. If soft or otherwise unsuitable areas revealed
during probing or proof-rolling cannot be compacted to a stable and uniformly firm condition, we
recommend that: 1) the subgrade soils be scarified (e.g., with a ripper or a farmer’s disc), aerated and
recompacted; or 2) the unsuitable soils be removed and replaced with structural fill, as needed.
Subgrade Protection and Wet Weather Considerations
The wet weather season generally begins in October and continues through May in western Washington;
however, periods of wet weather can occur during any month of the year. In our opinion, site grading and
fill placement could be considered during wet weather, but it should be noted that some of the soils
encountered in our explorations contain a significant amount of fines and will be susceptible to disturbance
during extended periods of wet weather. Soil with high fines content is very sensitive to small changes in
moisture and is susceptible to disturbance from construction traffic when wet or if earthwork is performed
during wet weather. If wet weather earthwork is unavoidable, we recommend that the following steps be
taken.
■ The ground surface in and around the work area should be sloped so that surface water is directed
away from the work area. The ground surface should be graded so that areas of ponded water do not
develop. Measures should be taken by the contractor to prevent surface water from collecting in
excavations and trenches. Measures should be implemented to remove surface water from the work
area.
■ Earthwork activities should not take place during periods of heavy precipitation.
■ Slopes with exposed soils should be covered with plastic sheeting.
■ The contractor should take necessary measures to prevent on-site soils and other soils to be used as
fill from becoming wet or unstable. These measures may include the use of plastic sheeting, sumps
with pumps and grading. The site soils should not be left uncompacted and exposed to moisture.
September 14, 2015 | Page 9
File No. 22013-001-00
Sealing the surficial soils by rolling with a smooth-drum roller prior to periods of precipitation will help
reduce the extent to which these soils become wet or unstable.
■ Construction traffic should be restricted to specific areas of the site, preferably areas that are surfaced
with working pad materials not susceptible to wet weather disturbance.
■ Construction activities should be scheduled so that the length of time that soils are left exposed to
moisture is reduced to the extent practical.
■ Protective surfacing such as placing asphalt-treated base (ATB) or haul roads made of quarry spalls or
a layer of free-draining material such as well graded pit-run sand and gravel may be necessary to protect
completed areas. Typically, minimum gravel thicknesses on the order of 24 inches are necessary to
provide adequate subgrade protection.
■ During periods of wet weather, concrete should be placed as soon as practical after preparation of the
footing excavations. Foundation bearing surfaces should not be exposed to standing water. Should
water infiltrate and pool in the excavation, it should be removed before placing structural fill or
reinforcing steel. Subgrade protection for foundations consisting of a lean concrete mat should be
considered if footing excavations are exposed to extended wet weather conditions.
Fill Materials
General
Material used for structural fill should be free of debris, organic contaminants and rock fragments larger
than 6 inches. The workability of material for use as structural fill will depend on the gradation and moisture
content of the soil. As the amount of fines increases, soil becomes increasingly more sensitive to small
changes in moisture content. We recommend that structural fill and trench backfill material consist of
material similar to “Select Borrow” or “Gravel Borrow” as described in Section 9-03.14 of the Washington
State Department of Transportation (WSDOT) Standard Specifications. If construction is performed during
wet weather, we recommend using select granular fill as described below. If prolonged dry weather prevails
during the earthwork phase of construction, a somewhat higher fines content may be acceptable.
Select Granular Fill
We recommend select granular fill for construction during wet weather conditions, consist of well-graded
sand and gravel or crushed rock with a maximum particle size of 6 inches and less than 5 percent fines by
weight based on the minus 3/4-inch fraction. Organic matter, debris or other deleterious material should
not be present. In our opinion, material conforming to WSDOT Specification 9-03.9 (Aggregates for Ballast
and Crushed Surfacing), 9-03.10 (Aggregate for Gravel Base), or 9-03.14 (Borrow) is suitable for use as
import fill material during wet weather with the exception that the fines content should be less than 5
percent based on the minus 3/4-inch fraction. In addition, some larger particle sizes are acceptable, as
described above.
On-Site Soil
During dry weather and periods of light rain fall any non-organic on-site soil may be considered for use as
fill provided it meets the criteria described above and can be compacted as recommended. When the fines
content in the soil exceeds about 5 percent, the soil becomes more sensitive to moisture. Portions of the
on-site soil contain enough fines to be moisture sensitive and may not be suitable for use as fill during
extended periods of wet weather and/or if exposed to wet conditions. Even when properly compacted, this
September 14, 2015 | Page 10
File No. 22013-001-00
material can be easily disturbed and will soften when exposed to moisture. Based on our subsurface
explorations, on-site material in the top approximate 6 feet will typically not be suitable for use as drainage
material, for use behind retaining walls, or as a capillary break material. Use of on-site soils for drainage
material should be evaluated on a case-by-case basis, and approved by the engineer.
Fill Placement and Compaction
General
To obtain proper compaction, fill soil should be compacted near optimum moisture content and in uniform
horizontal lifts. Lift thickness and compaction procedures will depend on the moisture content and
gradation characteristics of the soil and the type of equipment used. The maximum allowable moisture
content varies with the soil gradation and should be evaluated during construction. Silty soil and other fine
granular soil may be difficult or impossible to compact during persistent wet conditions. Generally, 12-inch
loose lifts are appropriate for steel-drum vibratory roller compaction equipment. Compaction should be
achieved by mechanical means. During fill and backfill placement, sufficient testing of in-place density
should be conducted to check that adequate compaction is being achieved.
Area Fills and Bases
Fill placed to raise site grades and materials under pavements should be placed on subgrades prepared
as previously recommended. In general, area fills and bases should be compacted to at least 95 percent
of the maximum dry density (MDD) determined by ASTM International (ASTM) Test Method D 1557
(modified Proctor).
Trench Backfill
For utility excavations, we recommend that the initial lift of fill over the pipe be thick enough to reduce the
potential for damage during compaction but generally should not be greater than about 18 inches. In
addition, rock fragments greater than about 1 inch in maximum dimension should be excluded from this
lift.
In paved and structural areas, trench backfill should be uniformly compacted in horizontal lifts to at least
95 percent of the MDD in the upper 2 feet below subgrade. Fill placed below a depth of 2 feet from subgrade
in paved areas must be compacted to at least 90 percent of the MDD. In nonstructural areas, trench backfill
should be compacted to a firm condition that will support construction equipment, as necessary.
Seismic Design Considerations
General
The site is located within the Puget Sound region, which is seismically active. Seismicity in this region is
attributed primarily to the interaction between the Pacific, Juan de Fuca, and North American plates. The
Juan de Fuca plate is subducting beneath the North American plate. It is thought that the resulting
deformation and breakup of the Juan de Fuca plate might account for the deep focus earthquakes in the
region. Hundreds of earthquakes have been recorded in the Puget Sound area. In recent history, four of
these earthquakes were large events: 1) in 1946, a Richter magnitude 7.2 earthquake occurred in the
Vancouver Island, British Columbia area; 2) in 1949, a Richter magnitude 7.1 earthquake occurred in the
Olympia area; 3) in 1965, a Richter magnitude 6.5 earthquake occurred between Seattle and Tacoma; and
4) on February 28, 2001, a magnitude 6.8 earthquake occurred at Nisqually near Olympia.
September 14, 2015 | Page 11
File No. 22013-001-00
Research is currently underway regarding historical large magnitude subduction-related earthquake activity
along the Washington and Oregon coasts. Geologists are reporting evidence that suggests several large
magnitude earthquakes (Richter magnitude 8 to 9) have occurred in the last 1,500 years, the most recent
of which occurred about 300 years ago. No earthquakes of this magnitude have been documented during
the recorded history of the Pacific Northwest. Local design practice in Puget Sound assumes that the
magnitude felt from such an earthquake is about the same as from the existing design earthquake because
of the distance.
Seismic Design Criteria
Seismic design may be performed using the equivalent static force procedure outlined in the 2012 IBC
using the design parameters provided below.
TABLE 2. SEISMIC DESIGN PARAMETERS
2012 IBC
Spectral Response Accel. at Short Periods (SS) = 1.244
Spectral Response Accel. at 1 Second Periods (S1) = 0.495
Site Class = C
Site Coefficient (FA) = 1.0
Site Coefficient (FV) = 1.51
Liquefaction Potential
Liquefaction refers to a condition where vibration or shaking of the ground, usually from earthquake forces,
results in development of excess pore pressures in loose, saturated soils and subsequent loss of strength
in the deposit of soil so affected. In general, soils that are susceptible to liquefaction include loose to
medium dense “clean” to silty sands that are below the water table. In our opinion, the potential for
liquefaction at this site is low.
Shallow Foundations
Foundation Support
Proposed structures can be satisfactorily founded on continuous wall or isolated column footings supported
on densely compacted weathered outwash or undisturbed native soils below the weathered outwash, or on
structural fill placed over these materials. If the bearing surface is loose or disturbed it must be compacted
to a dense, unyielding condition or the loose soil removed and replaced with compacted structural fill. As
noted above, the weathered outwash material contains fine-grained material and will be susceptible to
disturbance if wet or compacted during periods of rain. This should be considered during site development
and depending on the time of year. The weathered outwash material must be thoroughly compacted to a
uniformly dense and unyielding condition prior to construction of foundations.
The exterior footings should be established at least 18 inches below the lowest adjacent grade. The
recommended minimum footing depth is greater than the anticipated frost depth. Interior footings can be
founded a minimum of 12 inches below the top of the floor slab. Isolated column and continuous wall
footings should have minimum widths of 24 and 18 inches, respectively.
September 14, 2015 | Page 12
File No. 22013-001-00
Bearing Capacity
We recommend that footings founded as recommended be proportioned using an allowable soil bearing
pressure of 4,000 pounds per square foot (psf). The allowable soil bearing pressure may be increased to
6,000 psf for footings greater than 4 feet in width. The bearing pressures apply to the total of dead and
long-term live loads and may be increased by one-third when considering total loads, including earthquake
or wind loads. These are net bearing pressures. The weight of the footing and overlying backfill can be
ignored in calculating footing sizes.
Foundation Drains
In general, it is our opinion that foundation drains are not necessary for this project as we have considered
some water near the base of the footing in the foundation design recommendations presented. However,
due to the fine-grained nature of the weathered outwash, some foundation excavations may experience
seepage, depending on the time of year of excavation. In addition, some areas may exhibit wet conditions
near the surface depending on how foundations are backfilled, the design of the final grade surrounding
the building and other improvements such as irrigation. The use of foundation drains should be determined
on a case-by-case basis and consider items such as soil conditions exposed during construction, the
presence of seepage or evidence of seepage during excavation, surrounding irrigation lines, direction of
the surface water flow surrounding the structure(s), and maintenance programs in place. In some
instances, the backfill area around foundations is converted to landscape areas and it is common for
surface water to accumulate in these areas, which may require maintenance.
Footing Bearing Surface Preparation
Footing excavations should be performed using a smooth-edged bucket to limit bearing surface
disturbance. The foundation bearing surface should be recompacted as necessary to a dense, non-yielding
condition. Loose or disturbed materials present at the base of footing excavations should be removed or
compacted. Foundation bearing surfaces should not be exposed to standing water. Should water infiltrate
and pool in the excavation, it should be removed before placing structural fill or reinforcing steel.
If foundation bearing surfaces will be exposed to wet weather and/or construction traffic, we recommend
that they be protected using a crushed rock or lean-mix concrete. Typically, 8 to 12 inches of crushed rock
or 4 inches of lean-mix concrete is adequate for protection.
We recommend that a member from our firm observe foundation excavations before placing reinforcing
steel in order to confirm that adequate bearing surfaces have been prepared or provide recommendations
for removal of unsuitable soil. Unsuitable bearing materials should be recompacted or removed and
replaced with compacted structural fill as recommended by the geotechnical engineer.
Foundation Settlement
We estimate that settlement of footings designed and constructed as recommended will be less than
1 inch, for an assumed loading condition of up to 200 kips per column and 6 kips per lineal foot for
continuous footings. Differential settlements between comparably loaded isolated column footings or along
50 feet of continuous footing should be less than 1/2 inch. Settlement is expected to occur rapidly as loads
are applied. Settlements could be larger than estimated if footings are placed on loose or disturbed soil.
We should be contacted if foundation loads are anticipated to be greater than described above.
September 14, 2015 | Page 13
File No. 22013-001-00
Lateral Resistance
The ability of the soil to resist lateral loads is a function of frictional resistance, which can develop on the
base of footings and slabs and the passive resistance, which can develop on the face of below-grade
elements of the structure as these elements tend to move into the soil. For footings and floor slabs founded
in accordance with the recommendations presented above, the allowable frictional resistance may be
computed using a coefficient of friction of 0.40 applied to vertical dead-load forces. The allowable passive
resistance on the face of footings, grade beams or other embedded foundation elements may be computed
using an equivalent fluid density of 300 pounds per cubic foot (pcf) for undisturbed on-site soils or structural
fill extending out from the face of the foundation element a distance at least equal to two and one-half
times the depth of the element.
The passive earth pressure and friction components may be combined provided that the passive
component does not exceed two-thirds of the total. The passive earth pressure value is based on the
assumptions that the adjacent grade is level and that groundwater remains below the base of the footing
throughout the year. The top foot of soil should be neglected when calculating passive lateral earth
pressures unless the foundation area is covered with pavement or slab-on-grade. The lateral resistance
values include a safety factor of approximately 1.5.
Conventional Subgrade and Retaining Walls
Drainage
Positive drainage is imperative behind any retaining structure. This can be accomplished by providing a
zone of free-draining material behind the wall with perforated pipes to collect seepage water. The drainage
material should consist of coarse sand and gravel containing less than 5 percent fines based on the fraction
of material passing the 3/4-inch sieve. The wall drainage zone should extend horizontally at least 18 inches
from the back of the wall.
Perforated smooth-walled rigid PVC pipe having a minimum diameter of 4 inches should be placed at the
bottom of the drainage zone along the entire length of the wall, with the pipe invert at or below the elevation
of the base of the wall footing. The drainpipes should discharge to a tightline leading to an appropriate
collection and disposal system. An adequate number of cleanouts should be incorporated into the design
of the drains in order to provide access for regular maintenance. In general, roof downspouts, perimeter
drains or other types of drainage systems should not be connected to retaining wall drain systems.
Design Parameters
The pressures presented assume that backfill placed within 2 feet of the wall is compacted by hand-
operated equipment to a density of 90 percent of the MDD and that wall drainage measures are included
as previously recommended. For walls constructed as described above, we recommend using an active
lateral earth pressure corresponding to an equivalent fluid density of 35 pcf for the level backfill condition.
For walls with backfill sloping upward behind the wall at 2H:1V, an equivalent fluid density of 55 pcf should
be used. This assumes that the tops of the walls are not structurally restrained and are free to rotate. For
the at-rest condition (walls restrained from movement at the top) an equivalent fluid density of 50 pcf
should be used for design. For seismic conditions, we recommend a uniform lateral pressure of 8H (where
H is the height of the wall) psf be added to these lateral pressures. Note that if the retaining system is
designed as a braced system but is expected to yield a small amount during a seismic event, an active
earth pressure condition may be assumed and combined with the uniform seismic surcharge pressure.
September 14, 2015 | Page 14
File No. 22013-001-00
The recommended pressures do not include the effects of surcharges from surface loads. If vehicles will
be operated within one-half the height of the wall, a traffic surcharge should be added to the wall pressure.
The traffic surcharge can be approximated by the equivalent weight of an additional 2 feet of backfill behind
the wall. Additional surcharge loading conditions should also be considered on a case-by-case basis.
Retaining wall foundations may be designed using the allowable soil bearing values and lateral resistance
values presented above in the “Shallow Foundations” section of this report provided that bearing surfaces
are prepared as recommended. We estimate settlement of retaining structures will be similar to the values
previously presented for building foundations.
Building Pads and Floor Slabs
A modulus of subgrade reaction of 350 pounds per cubic inch (pci) can be used for designing the building
floor slab provided that the subgrade consists of dense native soil or structural fill and has been prepared
in accordance with the “Site Development and Earthwork” section of this report. Settlement for floor slabs
designed and constructed as recommended are estimated to be less than 3/4 inch for a floor load of
250 psf. We estimate that differential settlement of floor slabs will be 1/2 inch or less over a span of 50 feet
providing that the fill below the slab is compacted as specified. The subgrade soils are non-expansive, so
heave is not anticipated beneath the floor slab.
We recommend that on-grade slabs be underlain by a minimum 6-inch-thick capillary break layer to reduce
the potential for moisture migration into the slab. The capillary break material should consist of a well-
graded sand and gravel or crushed rock with a maximum particle size of 3/4 inch and less than 5 percent
fines. The material should be placed as recommended in the “Fill Placement and Compaction” section of
this report. If dry slabs are required (e.g., where adhesives are used to anchor carpet or tile to the slab), a
waterproof liner may be placed as a vapor barrier below the slab.
Pavement Recommendations
Asphaltic Concrete Pavement
Pavement subgrades and fill should be prepared and placed as previously described. The crushed rock
base course should be moisture conditioned near the optimum moisture content and compacted to at least
95 percent of the MDD determined in accordance with ASTM D 1557 test procedures. An appropriate
number of in-place density tests should be conducted on the compacted base course to check that
adequate compaction has been obtained. Crushed rock base course should conform to applicable sections
of 4-04 and 9-03.9(3) of the WSDOT Standards.
For this project, we based the recommended pavement sections described below on an assumed in-situ
California Bearing Ratio (CBR) between 20 and 25. The heavy-duty pavement section thickness is based
on a traffic loading of about 1,000,000, 18-kip equivalent single-axle loads (ESALs); we used a design life
of 10 years. The standard-duty section is appropriate for areas that will not be exposed to heavy truck loads.
Hot mix asphalt (HMA) should conform to applicable sections of 5-04, 9-02 and 9-03 of the WSDOT
Standards. The recommended pavement sections assume that final improvements surrounding the
pavement will be designed and constructed such that stormwater or excess irrigation water from landscape
areas does not infiltrate below the pavement section into the crushed base.
September 14, 2015 | Page 15
File No. 22013-001-00
STANDARD-DUTY ASPHALTIC CONCRETE PAVEMENT
■ 2 inches of hot mix asphalt.
■ 4 inches of crushed surfacing base course and/or top course compacted as recommended.
■ 12 inches compacted depth of granular native subgrades and/or imported structural fill compacted to
95 percent MDD (ASTM D 1557) and in a firm and unyielding condition.
HEAVY-DUTY ASPHALTIC CONCRETE PAVEMENT
■ 3 inches of hot mix asphalt.
■ 6 inches of crushed surfacing base course and/or top course compacted as recommended.
■ 12 inches compacted depth of granular native subgrades and/or imported structural fill compacted to
95 percent MDD (ASTM D 1557) and in a firm and unyielding condition.
LIMITATIONS
We have prepared this report for the exclusive use by D&B Retail Development and their authorized agents
for the Yelm Development project located at 1301 Yelm Avenue East in Yelm, Washington, Washington.
Within the limitations of scope, schedule and budget, our services have been executed in accordance with
generally accepted practices in the field of geotechnical engineering in this area at the time this report was
prepared. No warranty or other conditions, express or implied, should be understood.
Please refer to Appendix B titled “Report Limitations and Guidelines for Use” for additional information
pertaining to use of this report.
µ
SITE
Vicinity Map
Figure 1
Yelm DevelopmentYelm, Washington
2,000 2,0000
Feet
Data Source: Mapbox Open Street Map, 2015
Notes:1. The locations of all features shown are approximate.2. This drawing is for information purposes. It is intended to assist in showing features discussed in an attached document. GeoEngineers, Inc. cannot guarantee the accuracy and content of electronic files. The master file is stored by GeoEngineers, Inc. and will serve as the official record of this communication.
Projection: NAD 1983 UTM Zone 10N
\\tac\projects\22\22013001\GIS\2201300100_Task100_F01_VM.mxd Date Exported: 09/14/15 by cchelf
TP-1
TP-8
TP-2
TP-9
TP-10
TP-3 TP-4
TP-7
TP-5
TP-6
YELM AVE.E.(S.R.507)
LOT 1 LOT 2
LOT 3
Feet
060 60
Notes:
1. The locations of all features shown are approximate.
2. This drawing is for information purposes. It is intended to assist in showing
features discussed in an attached document. GeoEngineers, Inc. cannot
guarantee the accuracy and content of electronic files. The master file is stored
by GeoEngineers, Inc. and will serve as the official record of this communication.
Data Source: Base survey drawing provided by Larson and Associates. Proposed features provided by architect firm.
Projection: NAD83 Washington State Planes, South Zone, US Foot.\\TAC\Projects\22\22013001\00\CAD\Sheetfiles\2201300100_F2.dwgTAB:F2DateExported:09/14/15-11:14bycvanslykeYelm DevelopmentYelm, Washington
Site Plan
Figure 2Vertical Datum: Thurston County Datum (NGVD 29).
TP-1 Test pit number and approximate location
Legend
APPENDIX A
Field Explorations and Laboratory Testing
September 14, 2015 | Page A-1
File No. 22013-001-00
APPENDIX A
FIELD EXPLORATIONS AND LABORATORY TESTING
Subsurface Explorations
Soil and groundwater conditions at the proposed development site were explored by excavating 10 test pits
on August 14, 2015. Subsurface exploratory services were subcontracted to GeoEngineers, Inc. Eight of
the test pit explorations extended to depths between 10 and 12 feet below surrounding site grades. The
remaining test pit explorations extended to depths between 15 and 16 feet below surrounding site grades.
The locations of the test pits were determined by pacing and visual triangulation from existing site features
such as roadways and property corners. The elevations presented on the test pit logs are based on a site
plan obtained from Larson and Associates Land Surveyors and Engineers Inc. The locations and elevations
of the explorations should be considered approximate. Locations of the explorations are provided on the
Site Plan, Figure 2.
Our field representative obtained samples, classified the soils, maintained a detailed log of each
exploration and observed groundwater conditions where applicable. The samples were retained in sealed
plastic bags to prevent moisture loss. The soils were classified visually in general accordance with the
system described in Figure A-1, which includes a key to the exploration logs. Summary logs of the
explorations are included as Figures A-2 through A-11. The densities noted on the test pit exploration logs
are based on the difficulty of excavation, observations of caving and our experience and judgment.
Laboratory Testing
Soil samples obtained from the test pits were transported to our laboratory and examined to confirm or
modify field classifications, as well as to evaluate engineering properties of the soil. Representative
samples were selected for laboratory testing. Laboratory testing included moisture content determination
conducted in general accordance with ASTM International (ASTM) D 2216 and grain-size analyses
conducted in general accordance with ASTM C 136. The sample test depths and moisture content test
results are shown on the exploration logs. Sieve analysis results are presented in Figures A-12 and A-13.
AC
Cement Concrete
%F
AL
CA
CP
CS
DS
HA
MC
MD
OC
PM
PI
PP
PPM
SA
TX
UC
VS
CC
Asphalt Concrete
No Visible Sheen
Slight Sheen
Moderate Sheen
Heavy Sheen
Not Tested
NS
SS
MS
HS
NT
ADDITIONAL MATERIAL SYMBOLS
Measured groundwater level in
exploration, well, or piezometer
Measured free product in well or
piezometer
Distinct contact between soil strata or
geologic units
Approximate location of soil strata
change within a geologic soil unit
Distinct contact between soil strata or
geologic units
Approximate location of soil strata
change within a geologic soil unit
Graphic Log Contact
Groundwater Contact
Material Description Contact
Laboratory / Field Tests
Sheen Classification
Percent fines
Atterberg limits
Chemical analysis
Laboratory compaction test
Consolidation test
Direct shear
Hydrometer analysis
Moisture content
Moisture content and dry density
Organic content
Permeability or hydraulic conductivity
Plasticity index
Pocket penetrometer
Parts per million
Sieve analysis
Triaxial compression
Unconfined compression
Vane shear
Sampler Symbol Descriptions
NOTE: The reader must refer to the discussion in the report text and the logs of explorations for a proper understanding of subsurface conditions.
Descriptions on the logs apply only at the specific exploration locations and at the time the explorations were made; they are not warranted to be
representative of subsurface conditions at other locations or times.
GRAPH
Topsoil/
Forest Duff/Sod
Crushed Rock/
Quarry Spalls
Blowcount is recorded for driven samplers as the number
of blows required to advance sampler 12 inches (or
distance noted). See exploration log for hammer weight
and drop.
A "P" indicates sampler pushed using the weight of the
drill rig.
FIGURE A-1
2.4-inch I.D. split barrel
SYMBOLS TYPICAL
KEY TO EXPLORATION LOGS
CR
DESCRIPTIONSLETTER
TS
GC
PT
OH
CH
MH
OL
GM
GP
GW
DESCRIPTIONS
TYPICAL
LETTER
(APPRECIABLE AMOUNT
OF FINES)
MAJOR DIVISIONS
POORLY-GRADED SANDS,GRAVELLY SAND
PEAT, HUMUS, SWAMP SOILSWITH HIGH ORGANIC CONTENTS
CLEAN SANDS
GRAVELS WITH
FINES
CLEAN
GRAVELS
HIGHLY ORGANIC SOILS
SILTS
AND
CLAYS
SILTS
AND
CLAYS
SAND
AND
SANDY
SOILS
GRAVEL
AND
GRAVELLY
SOILS
(LITTLE OR NO FINES)
FINE
GRAINED
SOILS
COARSE
GRAINED
SOILS
SW
MORE THAN 50% OF
COARSE FRACTION
RETAINED ON NO. 4
SIEVE
CL
WELL-GRADED SANDS,GRAVELLY SANDS
SILTY GRAVELS, GRAVEL - SAND- SILT MIXTURES
LIQUID LIMIT
GREATER THAN 50
SILTY SANDS, SAND - SILTMIXTURES
(APPRECIABLE AMOUNT
OF FINES)
SOIL CLASSIFICATION CHART
LIQUID LIMIT
LESS THAN 50
SANDS WITH
FINES
SP
(LITTLE OR NO FINES)
ML
SC
SM
NOTE: Multiple symbols are used to indicate borderline or dual soil classifications
MORE THAN 50% OF
COARSE FRACTION
PASSING NO. 4
SIEVE
CLAYEY GRAVELS, GRAVEL -SAND - CLAY MIXTURES
CLAYEY SANDS, SAND - CLAYMIXTURES
INORGANIC SILTS, ROCK FLOUR,CLAYEY SILTS WITH SLIGHT
PLASTICITY
ORGANIC SILTS AND ORGANICSILTY CLAYS OF LOW
PLASTICITY
INORGANIC SILTS, MICACEOUSOR DIATOMACEOUS SILTY SOILS
ORGANIC CLAYS AND SILTS OFMEDIUM TO HIGH PLASTICITY
INORGANIC CLAYS OF HIGHPLASTICITY
MORE THAN 50%
PASSING NO. 200
SIEVE
MORE THAN 50%
RETAINED ON NO.
200 SIEVE
WELL-GRADED GRAVELS,GRAVEL - SAND MIXTURES
POORLY-GRADED GRAVELS,GRAVEL - SAND MIXTURES
INORGANIC CLAYS OF LOW TOMEDIUM PLASTICITY, GRAVELLY
CLAYS, SANDY CLAYS, SILTYCLAYS, LEAN CLAYS
GRAPH
SYMBOLS
Standard Penetration Test (SPT)
Shelby tube
Piston
Direct-Push
Bulk or grab
Continuous Coring
1
SA
2
SA
3
Grass and topsoil
Brown silty sand with gravel (loose to medium dense, dry to moist)
Yellowish-brown silty fine to medium sand with occasional gravel
(medium dense, moist)
Gray fine to coarse gravel with sand occasional cobbles and trace silt
(dense, moist)
Increased sand content
Test pit completed at 12 feet
No groundwater seepage observed
Moderate caving observed at 3.5 to 6 feet
TS
SM
SM
GP
9
4
%F=13
%F=2
Cobble/boulders; up to 1 foot in diameter
observed
Notes: See Figure A-1 for explanation of symbols.
The depths on the test pit logs are based on an average of measurements across the test pit and should be considered accurate to 0.5 foot.Tacoma: Date:9/15/15 Path:P:\22\22013001\GINT\2201300100.GPJ DBTemplate/LibTemplate:GEOENGINEERS8.GDT/GEI8_TESTPIT_1P_GEOTECDate Excavated:
Equipment:
Logged By:8/14/2015
Komatsu PC120 Total Depth (ft)
BK
12.0
Testing SampleDepth (feet)1
2
3
4
5
6
7
8
9
10
11
12
SAMPLE
Graphic LogElevation (feet)348347346345344343342341340339338337Sample NameTestingMATERIAL
DESCRIPTION
GroupClassificationEncountered WaterMoistureContent, %REMARKS
Log of Test Pit TP-1
Yelm Development
Yelm, Washington
22013-001-00
Project:
Project Location:
Project Number:Figure A-2
Sheet 1 of 1
1
2
3
SA
Gravel, base rock
Brown silty fine sand with gravel (medium dense, moist)
Yellow-brown fine to medium sand with silt, occasional gravel (medium
dense, moist)
Yellow-gray fine to coarse gravel with occasional cobbles and sand and
trace silt (medium dense, moist)
Grades to with sand and medium dense to dense
Test pit completed at 12 feet
No groundwater seepage observed
Moderate caving observed at 0 to 7 feet
GW
SM
SP-SM
GW
4
Cobble/boulders; up to 1 foot in diameter
observed
%F=2
Notes: See Figure A-1 for explanation of symbols.
The depths on the test pit logs are based on an average of measurements across the test pit and should be considered accurate to 0.5 foot.Tacoma: Date:9/15/15 Path:P:\22\22013001\GINT\2201300100.GPJ DBTemplate/LibTemplate:GEOENGINEERS8.GDT/GEI8_TESTPIT_1P_GEOTECDate Excavated:
Equipment:
Logged By:8/14/2015
Komatsu PC120 Total Depth (ft)
BK
12.0
Testing SampleDepth (feet)1
2
3
4
5
6
7
8
9
10
11
12
SAMPLE
Graphic LogElevation (feet)348347346345344343342341340339338337Sample NameTestingMATERIAL
DESCRIPTION
GroupClassificationEncountered WaterMoistureContent, %REMARKS
Log of Test Pit TP-2
Yelm Development
Yelm, Washington
22013-001-00
Project:
Project Location:
Project Number:Figure A-3
Sheet 1 of 1
1
2
SA
3
Brown silty fine sand with gravel (loose, dry to moist)
Yellow-brown fine to medium sand with silt, occasional gravel (medium
dense, moist)
Gray medium to coarse gravel with sand and occasional cobbles and
trace silt (medium dense, moist)
Test pit completed at 16 feet
No groundwater seepage observed
Moderate caving observed at 0 to 6 feet
SM
SP-SM
GW
2
Cobble/boulders; up to 1 foot in diameter
observed
%F=1
Notes: See Figure A-1 for explanation of symbols.
The depths on the test pit logs are based on an average of measurements across the test pit and should be considered accurate to 0.5 foot.Tacoma: Date:9/15/15 Path:P:\22\22013001\GINT\2201300100.GPJ DBTemplate/LibTemplate:GEOENGINEERS8.GDT/GEI8_TESTPIT_1P_GEOTECDate Excavated:
Equipment:
Logged By:8/14/2015
Komatsu PC120 Total Depth (ft)
BK
16.0
Testing SampleDepth (feet)1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
SAMPLE
Graphic LogElevation (feet)349348347346345344343342341340339338337336335334Sample NameTestingMATERIAL
DESCRIPTION
GroupClassificationEncountered WaterMoistureContent, %REMARKS
Log of Test Pit TP-3
Yelm Development
Yelm, Washington
22013-001-00
Project:
Project Location:
Project Number:Figure A-4
Sheet 1 of 1
1
2
3
SA
Brown silty fine sand with gravel (loose, dry)
Yellow-brown fine to medium sand with silt and occasional gravel
(medium dense, moist)
Gray fine to coarse gravel with sand and occasional cobbles and silt
(medium dense, moist)
Grades to with sand and dense
Test pit completed at 15.5 feet
No groundwater seepage observed
Moderate caving observed at 0 to 6 feet
SM
SP-SM
GP
3
Cobble/boulders; up to 1 foot in diameter
observed
%F=1
Notes: See Figure A-1 for explanation of symbols.
The depths on the test pit logs are based on an average of measurements across the test pit and should be considered accurate to 0.5 foot.Tacoma: Date:9/15/15 Path:P:\22\22013001\GINT\2201300100.GPJ DBTemplate/LibTemplate:GEOENGINEERS8.GDT/GEI8_TESTPIT_1P_GEOTECDate Excavated:
Equipment:
Logged By:8/14/2015
Komatsu PC120 Total Depth (ft)
BK
15.5
Testing SampleDepth (feet)1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
SAMPLE
Graphic LogElevation (feet)349348347346345344343342341340339338337336335334Sample NameTestingMATERIAL
DESCRIPTION
GroupClassificationEncountered WaterMoistureContent, %REMARKS
Log of Test Pit TP-4
Yelm Development
Yelm, Washington
22013-001-00
Project:
Project Location:
Project Number:Figure A-5
Sheet 1 of 1
1
2
SA
3
SA
4
Grass and topsoil
Brown fine to coarse gravel with sand and silt and occasional cobbles
and organic matter (roots) (loose to medium dense, dry)
Yellow-brown fine to coarse gravel with sand, occasional cobbles, trace
silt (medium dense to dense, moist)
Yellow silty fine sand (medium dense, moist)
Brown-gray fine to coarse gravel with sand and occasional cobbles and
trace silt (medium dense to dense, dry to moist)
Grades to moist
Test pit completed at 12 feet
No groundwater seepage observed
Moderate caving observed at 2.5 to 12 feet bgs
TS
GP-GM
GP
SM
GP
6
3
%F=13
Cobble/boulders; up to 1 foot in diameter
observed
%F=2
Notes: See Figure A-1 for explanation of symbols.
The depths on the test pit logs are based on an average of measurements across the test pit and should be considered accurate to 0.5 foot.Tacoma: Date:9/15/15 Path:P:\22\22013001\GINT\2201300100.GPJ DBTemplate/LibTemplate:GEOENGINEERS8.GDT/GEI8_TESTPIT_1P_GEOTECDate Excavated:
Equipment:
Logged By:8/14/2015
Komatsu PC120 Total Depth (ft)
BK
12.0
Testing SampleDepth (feet)1
2
3
4
5
6
7
8
9
10
11
12
SAMPLE
Graphic LogElevation (feet)351350349348347346345344343342341340Sample NameTestingMATERIAL
DESCRIPTION
GroupClassificationEncountered WaterMoistureContent, %REMARKS
Log of Test Pit TP-5
Yelm Development
Yelm, Washington
22013-001-00
Project:
Project Location:
Project Number:Figure A-6
Sheet 1 of 1
1
2
SA
Grass and topsoil
Brown fine to coarse gravel with silt and sand and occasional cobbles
and organic matter (roots) (medium dense, dry)
Yellow-brown fine to coarse gravel with sand, occasional cobbles and
trace silt (medium dense, dry)
Yellow-brown silty fine sand (medium dense, dry)
Gray-brown fine to coarse gravel with sand and occasional cobbles and
trace silt (medium dense to dense, dry to moist)
Test pit completed at 11 feet
No groundwater seepage observed
Minor caving observed at 1 to 11 feet
TS
GP-GM
GP
SM
GP
3
Cobble/boulders; up to 1 foot in diameter
observed
%F=2
Notes: See Figure A-1 for explanation of symbols.
The depths on the test pit logs are based on an average of measurements across the test pit and should be considered accurate to 0.5 foot.Tacoma: Date:9/15/15 Path:P:\22\22013001\GINT\2201300100.GPJ DBTemplate/LibTemplate:GEOENGINEERS8.GDT/GEI8_TESTPIT_1P_GEOTECDate Excavated:
Equipment:
Logged By:8/14/2015
Komatsu PC120 Total Depth (ft)
BK
11.0
Testing SampleDepth (feet)1
2
3
4
5
6
7
8
9
10
11
SAMPLE
Graphic LogElevation (feet)351350349348347346345344343342341Sample NameTestingMATERIAL
DESCRIPTION
GroupClassificationEncountered WaterMoistureContent, %REMARKS
Log of Test Pit TP-6
Yelm Development
Yelm, Washington
22013-001-00
Project:
Project Location:
Project Number:Figure A-7
Sheet 1 of 1
1
2
Grass and topsoil
Brown fine to coarse gravel with silt, sand and occasional organic
matter (roots) (medium dense, dry)
Brown-gray fine to coarse gravel with sand and occasional cobbles and
trace silt (medium dense to dense, moist)
Sand becomes medium to coarse
Test pit completed at 10 feet
No groundwater seepage observed
Minor caving observed at 3 to 10 feet
TS
GP-GM
GP
Cobble/boulders; up to 1 foot in diameter
observed
Notes: See Figure A-1 for explanation of symbols.
The depths on the test pit logs are based on an average of measurements across the test pit and should be considered accurate to 0.5 foot.Tacoma: Date:9/15/15 Path:P:\22\22013001\GINT\2201300100.GPJ DBTemplate/LibTemplate:GEOENGINEERS8.GDT/GEI8_TESTPIT_1P_GEOTECDate Excavated:
Equipment:
Logged By:8/14/2015
Komatsu PC120 Total Depth (ft)
BK
10.0
Testing SampleDepth (feet)1
2
3
4
5
6
7
8
9
10
SAMPLE
Graphic LogElevation (feet)351350349348347346345344343342Sample NameTestingMATERIAL
DESCRIPTION
GroupClassificationEncountered WaterMoistureContent, %REMARKS
Log of Test Pit TP-7
Yelm Development
Yelm, Washington
22013-001-00
Project:
Project Location:
Project Number:Figure A-8
Sheet 1 of 1
1
2
Topsoil and grass
Brown silty fine to medium gravel with sand and occasional organic
matter (roots) (medium dense, dry)
Yellow-brown fine to medium sand with silt and occasional gravel and
trace cobbles (medium dense, moist)
Yellow-brown fine to coarse gravel with sand and trace silt (medium
dense to dense, moist)
Test pit completed at 11.5 feet
No groundwater seepage observed
Moderate caving observed at 3.5 to 11.5 feet
TS
GM
SP-SM
GP
Cobble/boulders; up to 1 foot in diameter
observed
Notes: See Figure A-1 for explanation of symbols.
The depths on the test pit logs are based on an average of measurements across the test pit and should be considered accurate to 0.5 foot.Tacoma: Date:9/15/15 Path:P:\22\22013001\GINT\2201300100.GPJ DBTemplate/LibTemplate:GEOENGINEERS8.GDT/GEI8_TESTPIT_1P_GEOTECDate Excavated:
Equipment:
Logged By:8/14/2015
Komatsu PC120 Total Depth (ft)
BK
11.5
Testing SampleDepth (feet)1
2
3
4
5
6
7
8
9
10
11
SAMPLE
Graphic LogElevation (feet)348347346345344343342341340339338Sample NameTestingMATERIAL
DESCRIPTION
GroupClassificationEncountered WaterMoistureContent, %REMARKS
Log of Test Pit TP-8
Yelm Development
Yelm, Washington
22013-001-00
Project:
Project Location:
Project Number:Figure A-9
Sheet 1 of 1
1
2
3
Topsoil and grass
Brown silty fine to coarse gravel with sand and occasional organic
matter (roots) (medium dense, dry)
Yellow-brown fine to coarse gravel with sand (medium dense to dense,
moist)
Yellow-gray fine to medium sand with silt and occasional gravel
(medium dense, dry to moist)
Gray fine to coarse gravel with sand and occasional cobbles and trace
silt (medium dense to dense, moist)
Test pit completed at 12 feet
No groundwater seepage observed
Minor to moderate caving observed at 4 to 12 feet
TS
GM
GP
SP-SM
GP Cobble/boulders; up to 1 foot in diameter
observed
Notes: See Figure A-1 for explanation of symbols.
The depths on the test pit logs are based on an average of measurements across the test pit and should be considered accurate to 0.5 foot.Tacoma: Date:9/15/15 Path:P:\22\22013001\GINT\2201300100.GPJ DBTemplate/LibTemplate:GEOENGINEERS8.GDT/GEI8_TESTPIT_1P_GEOTECDate Excavated:
Equipment:
Logged By:8/14/2015
Komatsu PC120 Total Depth (ft)
BK
12.0
Testing SampleDepth (feet)1
2
3
4
5
6
7
8
9
10
11
12
SAMPLE
Graphic LogElevation (feet)349348347346345344343342341340339338Sample NameTestingMATERIAL
DESCRIPTION
GroupClassificationEncountered WaterMoistureContent, %REMARKS
Log of Test Pit TP-9
Yelm Development
Yelm, Washington
22013-001-00
Project:
Project Location:
Project Number:Figure A-10
Sheet 1 of 1
1
2
3
Grass and topsoil
Brown silty fine to coarse gravel with sand and occasional organic
matter (roots) (medium dense, dry)
Gray-brown fine to coarse gravel with sand and occasional cobbles
(medium dense, dry to moist)
Yellow-brown fine sand with silt (medium dense, moist)
Gray fine to coarse gravel with sand and occasional cobbles and trace
silt (dense, moist)
Test pit completed at 11 feet
No groundwater seepage observed
Minor to moderate caving observed at 4.5 to 11 feet
TS
GM
GP
SP-SM
GP
Cobble/boulders; up to 1 foot in diameter
observed
Notes: See Figure A-1 for explanation of symbols.
The depths on the test pit logs are based on an average of measurements across the test pit and should be considered accurate to 0.5 foot.Tacoma: Date:9/15/15 Path:P:\22\22013001\GINT\2201300100.GPJ DBTemplate/LibTemplate:GEOENGINEERS8.GDT/GEI8_TESTPIT_1P_GEOTECDate Excavated:
Equipment:
Logged By:8/14/2015
Komatsu PC120 Total Depth (ft)
BK
11.0
Testing SampleDepth (feet)1
2
3
4
5
6
7
8
9
10
11
SAMPLE
Graphic LogElevation (feet)350349348347346345344343342341340Sample NameTestingMATERIAL
DESCRIPTION
GroupClassificationEncountered WaterMoistureContent, %REMARKS
Log of Test Pit TP-10
Yelm Development
Yelm, Washington
22013-001-00
Project:
Project Location:
Project Number:Figure A-11
Sheet 1 of 1
Note: This report may not be reproduced, except in full, without written approval of GeoEngineers, Inc. Test results are applicable only to the specific sample on which they wereperformed, and should not be interpreted as representative of any other samples obtained at other times, depths or locations, or generated by separate operations or processes.The grain size analysis results were obtained in general accordance with ASTM D 6913..Figure A-12
Sieve Analysis Results
Yelm Development
Yelm, Washington
22013-001-00 Date Exported: 08/21/15EXPLORATION NUMBERDEPTH(ft)LABORATORY SOIL CLASSIFICATIONTP-1TP-1TP-2TP-33.5 811.510Silty sand (SM)Poorly graded gravel with sand (GP)Well-graded gravel with sand (GW)Well-graded gravel (GW)SYMBOLSANDSILT OR CLAYCOBBLESGRAVELCOARSE MEDIUM FINECOARSE FINEBOULDERS3/8”3” #20 #200#40 #60#1001.5” #10#43/4”01020304050607080901000.0010.010.11101001000PERCENT PASSING BY WEIGHT GRAIN SIZE IN MILLIMETERSU.S. STANDARD SIEVE SIZE
Note: This report may not be reproduced, except in full, without written approval of GeoEngineers, Inc. Test results are applicable only to the specific sample on which they wereperformed, and should not be interpreted as representative of any other samples obtained at other times, depths or locations, or generated by separate operations or processes.The grain size analysis results were obtained in general accordance with ASTM D 6913..Figure A-13
Sieve Analysis Results
Yelm Development
Yelm, Washington
22013-001-00 Date Exported: 08/21/15EXPLORATION NUMBERDEPTH(ft)SOIL CLASSIFICATIONTP-4TP-5TP-5TP-61369.59.5Poorly graded gravel with sand (GP)Silty sand (SM)Poorly graded gravel with sand (GP)Poorly graded gravel with sand (GP)SYMBOLSANDSILT OR CLAYCOBBLESGRAVELCOARSE MEDIUM FINECOARSE FINEBOULDERS3/8”3” #20 #200#40 #60#1001.5” #10#43/4”01020304050607080901000.0010.010.11101001000PERCENT PASSING BY WEIGHT GRAIN SIZE IN MILLIMETERSU.S. STANDARD SIEVE SIZE
APPENDIX B
Report Limitations and Guidelines for Use
September 14, 2015 | Page B-1
File No. 22013-001-00
APPENDIX B
REPORT LIMITATIONS AND GUIDELINES FOR USE1
This appendix provides information to help you manage your risks with respect to the use of this report.
Geotechnical Services are Performed for Specific Purposes, Persons and Projects
This report has been prepared for the exclusive use by D&B Retail Development and their authorized
agents. This report is not intended for use by others, and the information contained herein is not applicable
to other sites.
GeoEngineers structures our services to meet the specific needs of our clients. For example, a geotechnical
or geologic study conducted for a civil engineer or architect may not fulfill the needs of a construction
contractor or even another civil engineer or architect that are involved in the same project. Because each
geotechnical or geologic study is unique, each geotechnical engineering or geologic report is unique,
prepared solely for the specific client and project site. Our report is prepared for the exclusive use of our
Client. No other party may rely on the product of our services unless we agree in advance to such reliance
in writing. This is to provide our firm with reasonable protection against open-ended liability claims by third
parties with whom there would otherwise be no contractual limits to their actions. Within the limitations of
scope, schedule and budget, our services have been executed in accordance with our Agreement with the
Client and generally accepted geotechnical practices in this area at the time this report was prepared. This
report should not be applied for any purpose or project except the one originally contemplated.
A Geotechnical Engineering or Geologic Report is Based on a Unique Set of Project-Specific
Factors
This report has been prepared for the Yelm Development project located at 1301 Yelm Avenue East in
Yelm, Washington. GeoEngineers considered a number of unique, project-specific factors when
establishing the scope of services for this project and report. Unless GeoEngineers specifically indicates
otherwise, do not rely on this report if it was:
■ not prepared for you,
■ not prepared for your project,
■ not prepared for the specific site explored, or
■ completed before important project changes were made.
For example, changes that can affect the applicability of this report include those that affect:
■ the function of the proposed structure;
■ elevation, configuration, location, orientation or weight of the proposed structure;
■ composition of the design team; or
1 Developed based on material provided by ASFE, Professional Firms Practicing in the Geosciences; www.asfe.org.
September 14, 2015 | Page B-2
File No. 22013-001-00
■ project ownership.
If important changes are made after the date of this report, GeoEngineers should be given the opportunity
to review our interpretations and recommendations and provide written modifications or confirmation, as
appropriate.
Subsurface Conditions Can Change
This geotechnical or geologic report is based on conditions that existed at the time the study was performed.
The findings and conclusions of this report may be affected by the passage of time, by manmade events
such as construction on or adjacent to the site, or by natural events such as floods, earthquakes, slope
instability or groundwater fluctuations. Always contact GeoEngineers before applying a report to determine
if it remains applicable.
Topsoil
For the purposes of this report, we consider topsoil to consist of generally fine-grained soil with an
appreciable amount of organic matter based on visual examination, and to be unsuitable for direct support
of the proposed improvements. However, the organic content and other mineralogical and gradational
characteristics used to evaluate the suitability of soil for use in landscaping and agricultural purposes was
not determined, nor considered in our analyses. Therefore, the information and recommendations in this
report, and our logs and descriptions should not be used as a basis for estimating the volume of topsoil
available for such purposes.
Most Geotechnical and Geologic Findings Are Professional Opinions
Our interpretations of subsurface conditions are based on field observations from widely spaced sampling
locations at the site. Site exploration identifies subsurface conditions only at those points where subsurface
tests are conducted or samples are taken. GeoEngineers reviewed field and laboratory data and then
applied our professional judgment to render an opinion about subsurface conditions throughout the site.
Actual subsurface conditions may differ, sometimes significantly, from those indicated in this report. Our
report, conclusions and interpretations should not be construed as a warranty of the subsurface conditions.
Geotechnical Engineering Report Recommendations Are Not Final
Do not over-rely on the preliminary construction recommendations included in this report. These
recommendations are not final, because they were developed principally from GeoEngineers’ professional
judgment and opinion. GeoEngineers’ recommendations can be finalized only by observing actual
subsurface conditions revealed during construction. GeoEngineers cannot assume responsibility or liability
for this report's recommendations if we do not perform construction observation.
Sufficient monitoring, testing and consultation by GeoEngineers should be provided during construction to
confirm that the conditions encountered are consistent with those indicated by the explorations, to provide
recommendations for design changes should the conditions revealed during the work differ from those
anticipated, and to evaluate whether or not earthwork activities are completed in accordance with our
recommendations. Retaining GeoEngineers for construction observation for this project is the most
effective method of managing the risks associated with unanticipated conditions.
September 14, 2015 | Page B-3
File No. 22013-001-00
A Geotechnical Engineering or Geologic Report Could be Subject to Misinterpretation
Misinterpretation of this report by other design team members can result in costly problems. You could
lower that risk by having GeoEngineers confer with appropriate members of the design team after
submitting the report. Also retain GeoEngineers to review pertinent elements of the design team's plans
and specifications. Contractors can also misinterpret a geotechnical engineering or geologic report. Reduce
that risk by having GeoEngineers participate in pre-bid and preconstruction conferences, and by providing
construction observation.
Do Not Redraw the Exploration Logs
Geotechnical engineers and geologists prepare final boring and testing logs based upon their interpretation
of field logs and laboratory data. To prevent errors or omissions, the logs included in a geotechnical
engineering or geologic report should never be redrawn for inclusion in architectural or other design
drawings. Only photographic or electronic reproduction is acceptable, but recognize that separating logs
from the report can elevate risk.
Give Contractors a Complete Report and Guidance
Some owners and design professionals believe they can make contractors liable for unanticipated
subsurface conditions by limiting what they provide for bid preparation. To help prevent costly problems,
give contractors the complete geotechnical engineering or geologic report, but preface it with a clearly
written letter of transmittal. In that letter, advise contractors that the report was not prepared for purposes
of bid development and that the report's accuracy is limited; encourage them to confer with GeoEngineers
and/or to conduct additional study to obtain the specific types of information they need or prefer. A pre-bid
conference can also be valuable. Be sure contractors have sufficient time to perform additional study. Only
then might an owner be in a position to give contractors the best information available, while requiring them
to at least share the financial responsibilities stemming from unanticipated conditions. Further, a
contingency for unanticipated conditions should be included in your project budget and schedule.
Contractors are Responsible for Site Safety on their Own Construction Projects
Our geotechnical recommendations are not intended to direct the contractor’s procedures, methods,
schedule or management of the work site. The contractor is solely responsible for job site safety and for
managing construction operations to minimize risks to on-site personnel and to adjacent properties.
Read These Provisions Closely
Some clients, design professionals and contractors may not recognize that the geoscience practices
(geotechnical engineering or geology) are far less exact than other engineering and natural science
disciplines. This lack of understanding can create unrealistic expectations that could lead to
disappointments, claims and disputes. GeoEngineers includes these explanatory “limitations” provisions in
our reports to help reduce such risks. Please confer with GeoEngineers if you are unclear how these “Report
Limitations and Guidelines for Use” apply to your project or site.
Geotechnical, Geologic and Environmental Reports Should not be Interchanged
The equipment, techniques and personnel used to perform an environmental study differ significantly from
those used to perform a geotechnical or geologic study and vice versa. For that reason, a geotechnical
engineering or geologic report does not usually relate any environmental findings, conclusions or
September 14, 2015 | Page B-4
File No. 22013-001-00
recommendations; e.g., about the likelihood of encountering underground storage tanks or regulated
contaminants. Similarly, environmental reports are not used to address geotechnical or geologic concerns
regarding a specific project.
Biological Pollutants
GeoEngineers’ Scope of Work specifically excludes the investigation, detection, prevention, or assessment
of the presence of Biological Pollutants in or around any structure. Accordingly, this report includes no
interpretations, recommendations, findings, or conclusions for the purpose of detecting, preventing,
assessing, or abating Biological Pollutants. The term “Biological Pollutants” includes, but is not limited to,
molds, fungi, spores, bacteria, and viruses, and/or any of their byproducts.