PL CV Richard French-MiddleRD.-12.19.07  City of Yelm Community Development Department 105 Yelm Avenue West P.O. Box 479 Yelm, WA 98597   Pre-Application Meeting December 19, 2007 These comments are preliminary in nature and are not intended to represent final comments and or requirements for the City of Yelm. Until a complete application is made, the Community Development Department can only attempt to inform the applicant of general requirements as they appear in the form presented by the applicant at the time of pre-submission. Proponent: Richard French Project Proposal: Short subdivision consisting of 7-9 lots on approximately 1.51 acres and demolition of existing house. Project Location: 16307 Middle Road SE Tax parcel number 64303601000 Zoning and Setbacks Moderate Density Residential (R-6), Chapter 17.15 Density is not to exceed 6 units per acre - Maximum number of dwelling units allowed is 9, minimum is 5, based on the approximate acreage of 1.51. Actual acreage to be determined by a licensed surveyor. Setbacks: Front yard - 15' from R-O-W, with a 20' driveway approach. Rear Yard - 25' Side yard - minimum 5', total both sides 12' Flanking Yard – 15’ Critical Areas All of Yelm is considered a critical aquifer recharge area. The City critical area maps indicate that the property is located outside of wetlands, flood zones, and high ground water area areas. Application/Process Development of the site as a residential short subdivision requires Preliminary and Final Plat Approval. The preliminary plat review can be completed in 14 to 18 weeks. Preliminary Plat approval is valid for 5 years. Preliminary subdivision approval typically contains conditions of approval that the applicant must complete prior to receiving final subdivision approval or permits for construction. Following land use approval the applicant is required to submit civil construction drawings to the Community Development Department for review and approval, and satisfy all conditions of preliminary subdivision approval. Upon satisfactory completion, the applicant submits the final documentation for final plat approval. Final Plat approval takes approximately 6-8 weeks from the time the City receives a completed application packet. State Environmental Policy Act Process A SEPA Environmental checklist is not required for short subdivision. Land Use Fees Short Plat $250.00 + $50.00 per lot Final Plat Application $750.00 Civil Plan Review Billed on a cost recovery basis Traffic Impact Analysis $500.00 scoping fee if it creates more than 20 peak pm trips. Traffic Impact Fee $1,276 per peak PM trip Water Meter Fee Based on meter size Building Plan Review Based on 1997 UBC fee Schedule Building Permit Based on 1997 UBC fee Schedule Sewer Connection Fee $5,885 per ERU or $2,927 if part of LID Sewer Inspection Fee $145.00 per ERU Water Connection Fee $1,500 per ERU Fire Impact Fee $0.216 per 1,000 square feet of gross floor area. Parking Lot Location and Design The requirements for off-street parking and their design shall be regarded as the minimum; however, the owner, developer, or operator of the premises for which the parking facilities are intended shall be responsible for providing adequate amounts and arrangement of space for the particular premises even though such space is in excess of the minimum set forth. Chapter 17.72 YMC requires two off-street parking spaces for every dwelling unit, typically provided by a garage and driveway approach for a single family dwelling. Open Space Chapter 16 YMC. Subdivision and Chapter 14.12 YMC Open Space All residential developments are required to provide 5% of the gross area in open space. For 1.51 acres, approximately 3,267 square feet of qualified open space shall be required. Open space shall be dedicated and have the following attributes and characteristics: Environmental interpretation or other education; Park, recreational land, or athletic fields; Off-road footpaths or bicycle trails; or Any other use found by the City to further the purposes of this chapter. Above ground stormwater treatment areas do not qualify as open space. Landscaping Types and Description The purpose of landscaping requirements is to preserve the aesthetic character of communities; to promote retention and protection of existing vegetation; and to reduce the impacts of development on drainage systems and natural habitats. Type II landscaping is intended to provide visual separation of uses from streets, and visual separation of compatible uses so as to soften the appearance of streets, parking areas and building elevation. It is used around the perimeter of a site with a minimum planting area of eight-feet in width. When used adjacent to a building, a minimum five-foot planting area shall be provided. Type II landscaping will be required around the interior perimeter of the site. Type III landscaping is intended to provide visual relief where clear sight is desired. This type is utilized along pedestrian corridors and walks for separation of pedestrians from streets and parking areas. The minimum width for Type III landscaping shall be six feet. Type III landscaping is required as a part of street frontage improvements. Type V landscaping is to provide visual relief in storm water retention/detention areas with vegetation that is suitable and will thrive in hydric soils. Transportation Ingress and egress at the site must be consistent with the Yelm Development Guidelines, Section 4B.140. Frontage improvements are required for Middle Road and Railway Road. Both Railway and Middle Road are classified as “Neighborhood Collecter” streets. This project will be required to construct half street frontage improvements which include utility installation, asphalt widening, curb and gutter, landscape planter, street trees, sidewalk and lighting. Additional right of way dedication may be required depending on the actual centerline of the road. Residential development requires internal streets to be designed as a local access street, which includes two 11 foot travel lanes, two 7 foot parking strips, two 6 foot planter strips, and a 5 foot sidewalk on one side. The City of Yelm has adopted a Transportation Facility Charge (TFC) of $1,276.00 per PM peak trip generated by new development. The code provides a default table that the applicant can use to determine the number of new PM trips generated by a proposal. Traffic Facilities Charges may be applied to off-site improvements required to mitigate potential significant impacts attributed to the proposed development if the required improvements are capacity related. Water The proposed site is currently connected to the City of Yelm water system. There is an existing 10 inch existing water main located on Railway Road and Middle Road which is to be extended into the development to service the new lots or units. Water connections are based on a consumption rate of 900 cubic feet a month and are charged at a rate of $1,500 per connection (fee subject to change) inside the city limits. An engineers estimate for water usage will be required as part of the civil plan submission. Water connection fees are payable at building permit issuance. An irrigation meter shall be installed, provided an approved backflow prevention device is provided. As sewer use fees are calculated based on water usage, an irrigation meter will lower monthly sewer bills. The existing well(s) will need to be abandoned per Department of Ecology standards and any water rights will need to be dedicated to the city. Sewer The proposed site is currently not connected to the City of Yelm’s S.T.E.P. sewer system. There is an existing 6” sewer line located on Railway and Middle Road. The project will be required to connect to the existing sewer main and extend the line into the site as needed to serve the development. Any on-site septic systems will need to be abandoned prior to site plan review approval. This project will be required to install a City of Yelm STEP sewer tank(s) assembly. The size of both the STEP tank will be based on peak flows as calculated by the developer’s engineer and approved by City, which must be submitted as part of the civil plan review. There is a sewer latecomers fee associated with the site in the amount of $2,925.31. This fee is due prior to final plat approval. Sewer connections are based on a consumption rate of 900 cubic feet a month and are charged at a rate of $5,885.00 per a connection (fee subject to change) inside city limits. An inspection fee of $145.00 per a connection will also be required. Fire Protection All projects need to have fire protection for the buildings. It is likely that fire flow may be an issue at this location, which will be addressed through building official review of the proposed building uses and construction material used for the buildings. The International Building Code (IBC) provides occupancy ratings for different types of uses. The fire coverage and sprinkler system for the proposed use must meet IBC requirements. Fire Impact Fee pursuant to Section 15.40.020 (B)(6) YMC is established at a rate of $0.216 per square foot of development for all new development I the City of Yelm. Stormwater Developments with additional impervious surface are required to provide stormwater facilities pursuant to the 1992 DOE Stormwater Manual. Stormwater treatment for all impervious surfaces, such as internal and frontage streets is to be treated on site. The size and design would be reviewed as part of the site plan review and further review at civil plan submittal. An operations and maintenance agreement will be required. ADA Requirements The American Disabilities Act required that facilities are ADA accessible. Facility improvements will have to meet current code. Review of these improvements will be determined upon further review of the civil and architectural plans. Civil Plan Review Process Civil Plan review generally takes place after a land use approval. The Yelm Development Guidelines contain standard details for all infrastructure requirements, including parking lot layout, sewer and water lines, STEP tank design, and stormwater control. Building Permit Process Building Plan review, permitting and inspections will be based on Title 15 Yelm Municipal Code, adopting the 2003 IBC, IMC, UPC, IFC and the 2001 Washington State Energy Code. By resolution, the City of Yelm re-adopted the 1997 UBC, UMC and UPC Fee schedules. Building Plans may be submitted after Site Plan Review approval. Five(5) sets of plans, one of which may be half scale, two (2) sets of engineering calculations, energy calculations and specifications will be required. Due to the size of the occupancy, an integrated sprinkler and fire alarm system will be required. These plans may be submitted at a later date along with any required kitchen suppression systems. All fire related items 5’ outside the building will be subject to civil review along with domestic water, waste, and storm water. Concurrently with Site Plan Review two sets of building and accessory building elevations must be submitted for review of the building for consistency with the Design Guidelines. Allow at least 8 to 12 weeks for Building Plan Review and 2 weeks for design guideline review. Other Thurston County Health Department Review may be required if any wells and/or septic systems are located on or within 100' of property. All wells and septic systems within 200' of the property must be shown on preliminary plat drawings. Any existing wells and septic must be abandoned, and any water rights deeded to the City. ORCAA: Buildings containing asbestos and/or lead paint are potential environmental and health hazards. State and federal laws regulate the demolition of buildings containing asbestos and/or lead paint. State law (Chapter 173-425 WAC) defines land clearing burning as outdoor burning of trees, stumps, shrubbery, or other natural vegetation from land clearing projects. Olympic Region Clean Air Authority (ORCCA) issues land clearing permits for burning. The applicant shall contact the ORCAA, 2940-B Limited Lane NW, Olympia, WA 98502, (360) 586-1044 to secure any necessary permit(s) for the removal of materials containing asbestos and/or lead paint, and for land clearing burn permits. Prior to issuance of a city building permit the applicant shall demonstrate compliance with any ORCAA requirements, and prior to any demolition, proof of compliance with ORCAA and a City demolition permit is required.