PL CV Fourre.Mt.View8.27.08 (2)
City of Yelm
Community Development Department
105 Yelm Avenue West
P.O. Box 479
Yelm, WA 98597
Pre-Application Meeting
August 26, 2008
These comments are preliminary in nature and are not intended to represent final comments and or
requirements for the City of Yelm. Until a complete application is made, the Community Development
Department can only attempt to inform the applicant of general requirements as they appear in the form
presented by the applicant at the time of pre-submission.
Proponent: Gary Fourre
Project Proposal: Remove existing mobiles and replace with 2 duplexes.
Project Location: 9107 Mountain View Rd.
Tax parcel number 21713340101
Zoning and Setbacks
The property is zoned Moderate Density Residential (R-6). Any residential use,
including single-family dwellings on individual lots, duplexes, and other multifamily
dwellings, provided they do not exceed six dwelling units per gross acre and are not
less than three units per gross acre. Actual acreage to be determined by a licensed
surveyor.
Setbacks:
Front yard - 15' from R-O-W, with a 20' driveway approach.
Rear Yard - 25'
Side yard - minimum 5', total both sides 12'
Maximum building height is (35) feet.
Site Plan Review Process
A Site Plan Review application as established by Chapter 17.84 YMC is an
administrative review process. The minimum application requirements can be found at
Section 17.84.060 YMC and are listed on the application form. A notice of application is
mailed to all property owners within 300 feet of the site.
The site plan review committee’s decision on a site plan review application may be
appealed to the Hearing Examiner, who would hold an open record hearing on the
Pre-Application Meeting
Page 2 of 9
issue. The Examiner’s decision can be appealed to the City Council, which would hold
a closed record hearing and determine if the decision was supported by substantial
evidence or contrary to law. If a SEPA appeal is filed, the site plan review would be
combined with that appeal and the Hearing Examiner would become the decision maker
with a recommendation from the SPR Committee. An open record hearing would be
held by the examiner on the site plan review application, if combined with a SEPA
appeal.
A conceptual landscaping plan is required at the time of application for site plan review.
The final landscaping and irrigation plan is required as an element of civil plans, with
installation and approval prior to occupancy of the business.
Land use approval typically contains conditions of approval that the applicant must
complete prior to receiving a building permit. Upon satisfactory completion of all
conditions of land use approval, the applicant can submit building plans for approval.
Binding Site Plan Standards
In order to create lease pads for the buildings, a binding site plan is required. A binding
site plan would create building ‘pads’ with common access, parking, and stormwater
facilities. A binding site plan would allow the creation of a condominium at a later date
to sell the buildings located on the approved ‘pads’.
The binding site plan application would show the general area of building pads, parking,
stormwater, utilities, and access. The uses of the buildings would not be reviewed for
site plan review unless the proposed use was known at the time of binding site plan
approval. A binding site plan would also provide an avenue of phased improvements,
based on a phased construction plan.
The binding site plan requires a public hearing before the Yelm Hearing Examiner and
includes Environmental Review. Once preliminary approval is granted, the applicant
has 5 years to install all required infrastructure improvements to serve the pads and
Short Plat Application/Process
Development of the site as a residential short subdivision requires Preliminary and Final
Plat Approval. The preliminary plat review can be completed in 14 to 18 weeks.
Preliminary Plat approval is valid for 5 years.
Preliminary subdivision approval typically contains conditions of approval that the
applicant must complete prior to receiving final subdivision approval or permits for
construction. Following land use approval the applicant is required to submit civil
construction drawings to the Community Development Department for review and
approval, and satisfy all conditions of preliminary subdivision approval.
Pre-Application Meeting
Page 3 of 9
Upon satisfactory completion, the applicant submits the final documentation for final plat
approval. Final Plat approval takes approximately 6-8 weeks from the time the City
receives a completed application packet.
The floor and slopes of any stormwater retention/detention area shall be planted in
vegetation that is suitable and will thrive in hydric soils. The landscaping of the
stormwater facility shall be incorporated with all on-site landscaping.
A conceptual landscaping plan is required at the time of application for Preliminary Plat.
Final landscaping and irrigation plan is required as element of civil construction
drawings, with installation prior to final plat approval.
17.80.090(F) The owner/developer of any project requiring site plan review approval,
subdivision approval, or short subdivision approval shall provide a performance
assurance device in order to provide for maintenance of the required landscaping until
the tenant or homeowners’ association becomes responsible for landscaping
maintenance. The performance assurance device shall be 150 percent of the
anticipated cost to maintain the landscaping for three years.
State Environmental Policy Act Process
A SEPA threshold determination will be required before action is taken on the Site Plan
Review application. An environmental checklist is required when the proposal creates
4,000 square feet or 20 or more parking stalls. Because of the size of the project, an
expanded environmental checklist will be required initially. The expanded checklist
should include the following environmental documents:
• Traffic Impact Analysis
• Preliminary Stormwater Plan.
The SEPA threshold determination is appealable to the Hearings Examiner, who would
hold an open record hearing on the issue. The Examiner’s decision may be appealed to
City Council, which would conduct a closed record hearing and determine if the
Examiner’s decision was contrary to law and sup ported by substantial evidence.
A SEPA Environmental checklist is not required for short subdivision.
Critical Areas
All of Yelm is considered a critical aquifer recharge area. The City critical area maps
indicate that the property is located outside of wetlands, flood zones, and high ground
water areas.
Pre-Application Meeting
Page 4 of 9
Land Use Fees
Short Plat Application $250.00 + $50.00 per lot.
Site Plan Review $350.00 + $50 per 1,000 sq ft per gross floor area.
SEPA $150.00
Civil Plan Review Billed on a cost recovery basis
Traffic Impact Analysis $500.00 scoping fee, and actual cost for review
Traffic Impact Fee $1,321.00 per peak PM trip
Water Meter Fee Based on meter size
Building Plan Review Based on 1997 UBC fee Schedule
Building Permit Based on 1997 UBC fee Schedule
Sewer Connection Fee $5,885 per ERU or $3,009 if part of LID
Sewer Inspection Fee $145.00 per ERU
Water Connection Fee $1,500 per ERU
Fire Impact Fee $0.32 per 1,000 square feet of gross floor area.
Landscaping Types and Description
The purpose of landscaping requirements is to preserve the aesthetic character of
communities; to promote retention and protection of existing vegetation; and to reduce
the impacts of development on drainage systems and natural habitats.
Type II landscaping is intended to provide visual separation of uses from streets, and
visual separation of compatible uses so as to soften the appearance of streets, parking
areas and building elevation. It is used around the perimeter of a site with a minimum
planting area of eight-feet in width. When used adjacent to a building, a minimum five-
foot planting area shall be provided. Type II landscaping will be required around the
perimeter of the site.
Type III landscaping is intended to provide visual relief where clear sight is desired.
This type is utilized along pedestrian corridors and walks for separation of pedestrians
from streets and parking areas. The minimum width for Type III landscaping shall be six
feet. Type III landscaping is required as a part of street frontage improvements.
Type IV landscaping is intended to provide visual relief and shade in parking areas.
Parking shall have at least 24 square feet of landscape development for each parking
stall proposed. Each area of landscaping must contain at least 100 square feet of area
and must be at least six feet in any direction.
Pre-Application Meeting
Page 5 of 9
Type V landscaping is to provide visual relief in storm water retention/detention areas
with vegetation that is suitable and will thrive in hydric soils.
Open Space
Chapter 16 YMC. Subdivision and Chapter 14.12 YMC Open Space
All residential developments are required to provide 5% of the gross area in open
space. All multi-family residential developments are required to provide 10% of the
gross area in open space.
• Open space shall be dedicated and have the following attributes and
characteristics:
• Environmental interpretation or other education;
• Park, recreational land, or athletic fields;
• Off-road footpaths or bicycle trails; or
• Any other use found by the City to further the purposes of this chapter.
Above ground stormwater treatment areas do not qualify as open space.
Water
Parking Lot Location and Design
The requirements for off-street parking and their design shall be regarded as the
minimum; however, the owner, developer, or operator of the premises for which the
parking facilities are intended shall be responsible for providing adequate amounts and
arrangement of space for the particular premises even though such space is in excess
of the minimum set forth.
Chapter 17.72 YMC requires duplexes and multifamily units to provide two parking
spaces for each unit.
A standard stall is 9 feet by 20 feet while a compact stall is 8 by 16.
All parking areas must be surfaced with asphalt or concrete, and shall be striped and
landscaped to the standards of the development guidelines.
The design details for parking lot construction can be found in the Yelm Development
Guidelines.
Refuse
The refuse area must be large enough to accommodate a dumpster and recycle bin.
Refuse areas must be screened with an enclosure of a material and design compatible
Pre-Application Meeting
Page 6 of 9
with the overall architectural theme. A six foot wall or fence shall enclose any outdoor
refuse collection point. The fence shall be a solid material such as wood or masonry.
Transportation
Ingress and egress at the site shall be consistent with the Yelm Development
Guidelines, Section 4B.140. Existing access vehicular access into the site will need to
be reviewed.
The Traffic Impact Analysis, if required as part of the environmental review will indicate
the impacts that the development will have on the transportation system and suggest
mitigation measures that may be required.
Frontage improvements are required for all new development within the city. Frontage
requirements include improvements to the roadway from the centerline of right-of-way
back towards your property. This project will be required to complete frontage
improvements on Mt. View Road SE. This will include street trees, curb, gutter,
sidewalk, lighting etc.
A Traffic Impact Analysis may be required. This analysis may trigger additional off-site
improvements to mitigate traffic impacts associated with the proposal.
Chapter 15.40 YMC, Concurrency Management
The City has adopted a Transportation Facility Charge (TFC) of $1,321.00 per pm peak
trip. The Ordinance provides a default table that the applicant can use to determine
new pm trips generated by the proposed use. A single family home generates 1.01 pm
peak trips per unit, which is equivalent to a $1,335.00 TFC. The TFC is payable at time
of building permit issuance.
Traffic Facilities Charges may be applied to off-site improvements required to mitigate
potential significant impacts attributed to the proposed development if the required
improvements are capacity related.
Water
The proposed project is located in the City of Yelm’s water service area, and is not
currently connected to City water service. The site will be required to connect to the
water line located on Mt. View Road and extend services as necessary to serve the
intended use.
Water connections are based on a consumption rate of 900 cubic feet a month and are
charged at a rate of $1,500 per a connection (fee subject to change) inside city limits.
Pre-Application Meeting
Page 7 of 9
The fees will be calculated utilizing the water consumption calculations provided by your
civil engineer. These fees are payable at building permit issuance.
There is a water latecomers’ fee associated with this parcel which is in the amount of
$2,232.95 and is required to be paid prior to civil plan approval.
An irrigation meter shall be installed and an approved backflow prevention device
provided. As sewer use fees are calculated based on water usage, an irrigation meter
will lower monthly sewer bills.
Any existing well(s) will need to be abandoned per Department of Ecology standards
and the water rights will need to be dedicated to the city.
All commercial buildings and irrigation systems are required to provide for cross-
connection control through the provisions of a back flow prevention device installed on
the water services. A list of approved devices can be found at Chapter 246-290-490
WAC.
Sewer
The proposed site is currently located in the City of Yelm’s STEP sewer system service
area, and the proposed site is not currently connected to the City of Yelm’s STEP sewer
system. The site will be required to connect to the City’s sewer line located on Mt. View
Road and extend services as necessary to serve the intended use.
Any on-site septic systems will need to be abandoned prior to site plan review approval.
There is a sewer latecomers’ fee associated with this parcel which is in the amount of
$1,682.00 and is required to be paid prior to civil plan approval.
If additional connections are required, sewer connections are based on a consumption
rate of 900 cubic feet a month and are charged at a rate of $5,885.00 per a connection
(fee subject to change) inside city limits. An inspection fee of $145.00 per a connection
will also be required.
Fire Protection
All projects need to have fire protection for the buildings. It is likely that fire flow may be
an issue at this location, which will be addressed through building official review of the
proposed building uses and construction material used for the buildings.
The International Building Code (IBC) provides occupancy ratings for different types of
uses. The fire coverage and sprinkler system for the proposed use must meet IBC
requirements.
Pre-Application Meeting
Page 8 of 9
Fire Impact Fee pursuant to Section 15.40.020 (B)(6) YMC is established at a rate of
$0.32 per square foot of development for all new development I the City of Yelm.
Stormwater
Developments with additional impervious surface are required to provide stormwater
facilities pursuant to the 1992 DOE Stormwater Manual. Stormwater treatment for all
impervious surfaces, such as internal and frontage streets is to be treated on site.
The size and design would be reviewed as part of the site plan review and further
review at civil plan submittal. An operations and maintenance agreement will be
required.
ADA Requirements
The American Disabilities Act required that facilities are ADA accessible. Facility
improvements will have to meet current code. Review of these improvements will be
determined upon further review of the civil and architectural plans.
Civil Plan Review Process
Civil Plan review generally takes place after a land use approval. The Yelm
Development Guidelines contain standard details for all infrastructure requirements,
including parking lot layout, sewer and water lines, STEP tank design, and stormwater
control.
Building Permit Process
Building Plan review, permitting and inspections will be based on Title 15 Yelm
Municipal Code, adopting the 2006 IBC, IMC, UPC, IFC and the 2001 Washington State
Energy Code. By resolution, the City of Yelm re-adopted the 1997 UBC, UMC and UPC
Fee schedules.
Building Plans may be submitted after Site Plan Review approval. Five(5) sets of plans,
one of which may be half scale, two (2) sets of engineering calculations, energy
calculations and specifications will be required. Due to the size of the occupancy, an
integrated sprinkler and fire alarm system will be required. These plans may be
submitted at a later date along with any required kitchen suppression systems. All fire
related items 5’ outside the building will be subject to civil review along with domestic
water, waste, and storm water.
Concurrently with Site Plan Review two sets of building and accessory building
elevations must be submitted for review of the building for consistency with the Design
Guidelines.
Pre-Application Meeting
Page 9 of 9
Allow at least 8 to 12 weeks for Building Plan Review and 2 weeks for design guideline
review.