09-0239 Pre Stormwater Site Plan 111609•
Prepared For:
LS Construction
20900 Cooley Road
Bend, OR 97701
Prepared By,
Jeremy F. Haug, E.%.T., Project Engineer
Approved By:
Brett M. Allen, P.E., Principal
Project # 09-024
1 hereby state that this Stonn Water Site Plan for Les Schwab Tire Center of 805 Yelm Avenue East has been prepared by me
or under my supervision and meets the standard of care and expertise Malls usual and customary in this communityof professional
engineers. I understand that City of Tacoma does not and will not assume liability for the sufciency, suitability or performance of
drainage facilities prepared by Contour Engineering PLLC This analysis is based on data and records either supplied to, or obtained
by, Contour Engineering, PLLC These documents are referenced within the text of the analysis. The analysis has been prepared
utilizing procedures and practices within the standard accepted practices of the industry.
TABLE OF CONTENTS
PAGE
1.0 PROJECT OVERVIEW.................................................................................................................................2
PURPOSEAND SCOPE................................................................................................................................................. 2
PROiEc'r DIiSCRIPTION.............................................................................................................................................. 2
2.0 EXISTING CONDITIONS SUMMARY..................................................................................................... 3
3.0 DOWNSTREAM ANALYSIS....................................................................................................................... 4
4.0 STORMWATER CONTROLS...................................................................................................................... 5
EXISTINGSi m, HYDROLOGY...................................................................................................................................... 5
DTVELOPE D SI'Z'E HYDROLOGY.................................................................................................................................. 5
P1.-'.R1'ORMANCE STANDARDS...................................................................................................................................... 5
Fi.OW CONTROL SYSTEM........................................................................................................................................... 5
WATLRQUALITY SYSTEMS....................................................................................................................................... 6
S'T'ORM DRAINAGE CONVEYANCE SYSTEMS.............................................................................................................. 6
5.0 DISCUSSION OF MINIMUM REQUIREMENTS................................................................................... 6
Appendix A'
General Exhibits
Appendix '8'
Geotechnical Report
Appendix 'C'
Retention Pond Analysis
Appendix 'D'
Water Quality Systems Sizing and Specifications
Appendix 'E'
Conveyance Calculations
1.0 PROJECT OVERVIEW
Purpose and Scope
This Preliminary Stormwater Site Plan report accompanies the Site Plan Review
application and Short Plat application submittals for the proposed Les Schwab Tire
Center at 805 Yelm Avenue East as submitted to the City of Yelm. This document
provides site information and the preliminary analysis used for the stormwater
conveyance and retention pond designs, as well as the water quality facilities for
both the Les Schwab site and the access roadway.
The 1992 Department of Ecology Stormwater Management Manual for Western
Washington (DOEManuan establishes the methodology and design criteria used for
this project.
Project Description
The proposed project will consist of a short plat subdivision of the existing parcel
into two lots and a tract. The site is currently within parcel 22730121100 which is
approximately 299,457 sq. ft. (6.87 acres) and is zoned Commercial C-1. See
Vicinity Map in Appendix `A'.
Lot 1 will include the proposed Les Schwab Tire Center which will comprise of a
11,751 sq. ft. building with 48 parking stalls, associated drive aisles, loading areas
and landscaping. The existing house and accessory buildings will be demolished and
removed. Lot 1 will contain an underground storm drainage system separate from
either Lot 2 or the Tract.
Lot 2 will encompass the remained of the site (excluding the Retention Pond Tract)
and include the existing church buildings, facilities, and parking areas as well the
access and utility easement for the proposed roadway.
The retention pond tract (Tract A) is located along the southern property line and is
60 -ft in width. This pond is sized for the Les Schwab site, the access roadway, and
the existing church facilities as well as the possible future expansion of the church
facility and its parking area.
Legal Description
Parcel 22730121100
THAT PORTION OF THE NORTHWEST QUARTER OF THE NORTHEAST QUARTER OF
SECTION 30, TOWNSHIP 17 NORTH, RANGE 2 EAST, W.M., DESCRIBED AS
FOLLOWS:
BEGINNING AT A POINT ON THE SOUTH LINE OF SAID SUBDIVISION 310 FEET
WEST OF THE SOUTHEAST QUARTER CORNER THEREOF; THENCE WEST 350 FEET,
MORE OR LESS, TO THE SOUTHWEST CORNER OF THE SOUTHEAST QUARTER OF
THE NORTHWEST QUARTER OF THE NORTHEAST QUARTER; THENCE NORTHERLY
ALONG THE WEST LINE OF SAID SOUTHEAST QUARTER OF THE NORTHWEST
2
QUARTER OF THE NORTHEAST QUARTER AND ALONG THE EAST LINE OF A TRACT
CONVEYED TO JOHN CUBIT BY DEED RECORDED IN VOLUME 100 OF DEEDS, PAGE
201, UNDER RECORDING NO. 98937, 1017.5 FEET, MORE OR LESS TO THE
SOUTHERLY LINE OF SECONDARY STATE HIGHWAY NO. 5-H; THENCE
SOUTHEASTERLY ALONG THE SOUTHERLY LINE OF SAID HIGHWAY TO A POINT
NORTH OF THE POINT OF BEGINNING; THENCE SOUTH 737.12 FEET MORE OR
LESS, TO THE TRUE POINT OF BEGINNING.
EXCEPTING THEREFROM THAT PORTION CONVEYED TO THE CITY OF YELM BY
DEED RECORDED OCTOBER 25, 2001 UNDER AUDITOR'S FILE NO. 3387674 FOR
ROAD.
IN THURSTON COUNTY, WASHINGTON
2.0 EXISTING CONDITIONS SUMMARY
Pre -Developed Site Conditions
Currently, the parcel contains many structures scattered over the northern half of
the parcel. The church facility is comprised of two main buildings and is located
toward the west side of the site. There is a residence toward the northeast portion
of the site, and there are several accessory buildings scattered throughout the site.
Topography and Ground Cover
The topography of the site is relatively flat with an overall slope from north to south
of less than 0.5%. The parcel is primarily grassed in the southern half with not
trees, structures or impervious surfaces. The northern half contains grasses and
scattered trees of mixed varieties, as well as the existing structures, gravel parking
area, basketball court and playground area.
Adjacent Land Uses
The parcel is bordered to the north by Yelm Avenue and to the south by a pond
facility for the housing development to the south. A commercial property, Rite Aid,
is to the northeast with a residential property to the southeast. To the northwest
lies a commercial development, which contains the Country Inn Restaurant, some
mini -storage, and a small strip mall. To the southwest, lies several residential
properties.
Native Soils and Groundwater
The native soils have been mapped as Spanaway gravelly sandy loam (110) and
Spanaway stony sandy loam (112). See Geotechnical Engineering Report as
Appendix 'B'.
3
The site is located outside the Thurston County High Groundwater Hazard Area. No
groundwater was observed at any of the test pits. See the Geotechnical Engineering
Report as Appendix 'B'.
Drainage Patterns
It is assumed, based on the native soils and the relative flatness of the site and
adjacent properties, that all stormwater infiltrates on-site and that there is no off-
site stormwater entering the site.
There are no known drainage or erosion problems on the project site. However, per
representatives of Our Redeemer Lutheran Church, stormwater does pool on
occasion in the existing gravel parking area in front of the church facilities. This
drainage issue does not have an impact on the subject site and will be addressed in
future permits applications.
Critical and Sensitive Areas
There are no known wetlands or any other sensitive area within 300 -ft of the project
site.
Other Existing Site Information
There are currently two wells on the existing parcel. One is located along the
western property line, midway between the church and the northwestern property
corner. This well is to remain for utilization by the church facilities. This well will be
capped and decommissioned as part of this project. To our knowledge, and based
on the DOE Well Logs, there are not other wells within 200 -ft of the project site.
There is an existing septic drainfield for the church located east of the existing
facilities and a septic tank located between the two current buildings. This system
will be decommissioned and removed, and replaced by a sewer STEP system. The
permit application for this sewer STEP system is forthcoming.
Both the well capping and decommissioning, and the septic decommissioning will be
done per current Thurston County Health Department and Department of Ecology
standards.
There are no known underground tanks within the subject parcel.
3.0 DOWNSTREAM ANALYSIS
Since all stormwater will be collected, conveyed and infiltrated on-site, not
downstream analysis is required.
W
4.0 STORMWATER CONTROLS
}
Existing Site Hydrology
It is assumed, based on the native soils, all precipitation currently infiltrates on-site;
Developed Site Hydrology
The post -developed parcel will contain the developed area and some area that will
be left in its native condition. See the Basin Map Exhibit in Appendix 'C'. The
developed area (Retention Pond Basin) will consist of Lot 1 (Les Schwab), the access
roadway, the existing church buildings, facilities and parking area, and a portion of
area south of the existing church for a possible building expansion in the future.
The post -developed site hydrology will consist of the following areas:
Total Parcel Area = 299,457 sq. ft. (6.875 acres)
Total Retention Pond Basin = 185,329 sq. ft. (4.255 acres)
Total Tract Area = 21,116 sq. ft. (0.485 acre)
Total Area to Remain in Native Condition = 93,120 sq. ft. (2.138 acres)
The Retention Pond Basin area is used for sizing the retention pond and takes into
consideration the future expansion/improvements of the church (See Basin Map
Exhibit in Appendix `C'). For pond design, 80% of the area was considered
impervious and the remaining 20% was considered pervious. The areas used for
pond design are as follows:
Total Impervious to Pond = 148,177 sq. ft. (3.40 acres)
Total Pervious to Pond = 37,044 sq. ft. (0.85 acres)
The remainder of the area to be left as native, will continue to allow precipitation to
be infiltrated.
Performance Standards
The 1992 Department of Ecology Stormwater Management Manual for Western
Washington establishes the performance standards for all the storm drainage,
infiltration and water quality facilities for the project.
Flow Control System
Flow control for the developed site will be mitigated via a retention pond located
along the southern property of the parcel. (See Appendix `C') The pond is of a linear
design and extends approximately the entire southern property line. An access
ramp for the pond will be located on the western end with the pond inlet and control
structure entering at approximately the middle of the pond. Access gates will be
located for the ramp entrance and for access to the control structure.
Based on infiltration testing for the site, a maximum infiltration rate of 60 in/hr is
recommended by the geotechnical engineer. (See Appendix 'B') The maximum
5
short term infiltration rate per the DOEManual is 20 in/hr. With a safety factor of 2,
the design, long term infiltration rate is 10 in/hr. The pond was designed using an
infiltration rate of 10 in/hr.
The pond was sized to infiltrate the runoff generated from the Tributary Area
discussed above. The pond was designed utilizing the current Dept. of Ecology
Western Washington Hydrology Model (WWHM) version 3 modeling software. With
a design infiltration rate of 10 in/hr and effective depth of 6.5 ft., the minimum
bottom surface area of the pond to achieve 100% infiltration of the Tributary Area is
1,960 sq. ft. The proposed pond has a bottom surface area of 2,756 sq. ft. The
maximum water elevation in the proposed pond is approximately 2.75 ft. above the
bottom elevation. See the Retention Pond Analysis in Appendix `C'.
Water Quality Systems
Water quality treatment will be performed on each of the lots and along the
roadway. As such, there will be several different water quality basins that will treat
the stormwater prior to connection to the storm drainage main that outlets to the
pond.
Lot 1 (Les Schwab) preliminarily has a precast Contech StormwaterSolutions 6'x12'
StormFilter Vault with 10 - 18" cartridges. It will located just inside the southern
most entrance to the site. See pages D1 -D4 in Appendix 'D' for sizing and
specification information.
The roadway is broken into two water quality basins, the northern half (RD1) and
the southern half (RD2). Water quality treatment for RD1 and RD2 will preliminarily
be handled by a Contech Stormwater Solutions 72" StormFilter Manhole and a 48"
Stormfilter Manhole, respectfully. See pages D5 -D11 in Appendix `D' for sizing and
specification information.
Water quality treatment for any future improvements to Lot 2 will be contained
within that specific future permit application. None are proposed at this time.
Storm Drainage Conveyance Systems
Conveyance calculations to ensure minimum cleaning velocity and adequate pipe
sizing are included in Appendix 'E'.
S.O DISCUSSION OF MINIMUM REQUIREMENTS
The Minimum requirements for this project are set forth by 1992 Department of
Ecology Stormwater Management Manual for Western Washington. See Figures 2.2
and 2.3 from the DOEManual in Appendix'A'.
E
Minimum requirements #1 through #10 apply to this project and are discussed
below:
#1 - Preparation of Stormwater Site Plans
This storm water site plan satisfies this requirement.
#2 - Construction Stormwater Pollution Prevention Plan (SWPPP)
A Construction Stormwater Pollution Prevention Plan Short Form will be prepared
and submitted in the civil plan review package.
#3 - Source Control of Pollution
Applicable Source Control BMPs will be employed as needed and will be located in
the SWPPP and the Operations and Maintenance Manual as included in the civil plan
review package.
#4 - Preservation of Natural Drainage Systems and Outfalls
The natural drainage of the site will be maintained by the use of infiltration.
#5 - On-site Stormwater Management
This requirement will be met by the use of infiltration for stormwater mitigation.
#6 — Runoff Treatment
See Section 4.0, Water Quality Systems within this report.
#7 — Flow Control
See Section 4.0, Flow Control System within this report.
#8 — Wetlands Protection
There are no known wetlands in the vicinity of the project site.
#9 — Basin/Watershed Planning
All requirements set forth by the DOEManua/and the City of Yelm Municipal Code
have been adhered too.
#10 — Operations and Maintenance
An Operations and Maintenance Manual will be submitted in the civil plan review
package.
7
APPENDIX A
General Exhibits
Thurston County Map Output Page
Yelr Les Schwab
Disclaimer' Thurston Coolly makes every e0bn to cost Ie that III mop is a it and
acauate mp eserwroo of the \\ Or of County government. I ONyeN or, the County and el l
relined personnel make no warranty, expressed or imp] led, regarding the accuracy.
completeness or convenience ol'ally int ot'mation disclosed on this map. Nei does the Count
accept lisbilip for any damage or iniury caused by the use ofthis map.
In Ore losses( extent per pursuant to applicable law. I limstoo County disclaims all
wamill(im express or implied, including, but not limited to, implied warmm es of merchant
ability, data Gloess for o paNarlar pwpose, and nontinfringentelos of proprietaly rights.
Under To, circumstances, including- hill not limited to, negligence, shall 'I hwstoo Colint} be
liable for any direct, in(irect, incidental, special or consequential kroaLies that result from
Ithe useof, or tile inability to lse 'Ihwstoo County matenalc
Thurs(oit �r Sf 2009 - Thumtoo CounqOeoD Its Censer
G eol)aia;? 2404 Heritage Court SW, 31 d Floor
Cetricr .. Olympia, WA98502-6031
Page 1 of 1
LEGEND
/N/ Major Roads
y Flood Zones
^j Roads
- Suter Bodies
Strearus
`l
{ r zoning
I, -
-J Contours
Wetlands
Cities
Wetland Buffers
Parcels
http://geomapl.geodata.org/servlet/coin.esri.esrimap.Esrimap?ServiceName=cadastralov&... 11/9/2009 n i
Thurston County Map Output Page
elm Les Schwab
10210
Disc Imme.e'fharston Count, males even, elPort to ensure that this map is a true mid
accumte Ieprescntalloft of the cem'k of County eorernment. I-Io6'e,Cl', the COMM -and ell
mlmed pet Fennel make no \,artamn expressed or implied, regarding the accuYocy.
completeness or Coll, enicnce of any infomtation disclosed on this map_ Nor does the Comity
accept habilns f0i any dileltile onnuuy CsL1Scd h) file use ofthis map.
'lo file illicit eUurt ocimismwe pun'uamt to applicable hw- "Ihurstmt Comity disclaims all
osm ilties espies or implied, inJudimg, but not limited to, implied mamm�ics ofinerchmv
ability dam fitness to LL pamckilm purpose, mid non -i ih mgcancnts of propnetan, right'.
Under no circumstances, imcluding, but not limited to, negliglence_ shall Thurston County Ise
liable for any direct, indirect. iocideml, special or consequential damaaes that result from
rhe useof- or the inability to usc. I hurston County materials.
'Yhms4ou 0 2009 - 1 hursfoo County GcoDma Colter
Gei)Datit 2404 Heritage Cour[ SW, 3rd Flow
Gamer Olympia, WA 98502-6031
Page I of I
LEGEND
/N,/ Major Roads Flood Zones
Roads
-,- 1hTdYPS Bodies
streams
Zoning
Contours l
Wetlands n _ Cities
Wetland Buffers Parcels
http://geomapl.goodata.org/servlet/eom.esri.esrimap.Esiimap?ScrviceName=cadastralov&... 11/9/2009 ^-2—
Start Here
Does the site have
Yes
See Redevelopment
35% or more of
All Minimummore
Minimum
existing impervious
or new plus replaced
Requirements and
coverage?
surfaces and converted
Flow Chart
pervious surfaces.
Does the project convert
(Figure 2.3)
No
3/A acres or more of native
vegetation to lawn or
Does the project add
No landscaped areas, or
5,000 square feet or
convert 2.5 acres or more
more of new
10
of native vegetation to
impervious surfaces?
pasture?
Yes
Yes No
Minimum
Does the project have
®
2,000 square feet or
All Minimummore
of new, replaced,
Requirements apply to
or new plus replaced
the new impervious
impervious surfaces?
surfaces and converted
No
pervious surfaces.
Yes No
Minimum
Does the project have
Requirements 41
land -disturbing
through 45 apply toactivities
of 7,000
the new and replaced
Yes square feet or more?
impervious surfaces
and the land disturbed.
No
See Minimum
Requirement S12,
Construction
Stormwater Pollution
Prevention
Figure 2.2 — Flow Chart for Determining Requirements for New Development
February 2005 Volume I — Minimum Technical Requirements
2-9
A�
2-10
Do the new, replaced, or new plus replaced impervious surfaces total 2,000
square feet or more?
OR
Does the land disturbing activity total 7,000 square feet or more?
Yes i No
Mininmm Requirements #1 through #5
apply to the new and replaced impervious
surfaces and the land disturbed.
Next Question
Apply Minimum Requirement #2,
Construction Stormwater Pollution
Prevention -
Does the project add 5,000 square feet or more of new impervious surfaces?
OR
Convert 1/4 acres or more of native vegetation to lawn or landscaped areas?
OR
Convert 2.5 acres or more of native vegetation to pasture?
Yes No
Next
Mininumt Requirements #1 through #10 Question Is this a road -
apply to the new, impervious surfaces and related project?
the converted pervious surfaces. Yes
No
Does the project add 5,000 square feet or more of new impervious surfaces?
Yes
Do new impervious surfaces add 50% or
mare to the existing impervious surfaces
within the project limits?
No Yes
No additional
No
7s the total of the new plus replaced
impervious surfaces 5,000 square feet or
more, AND does the value of the
proposed improvements — including
interior improvements— exceed 50% of
the assessed value (or replacement value)
of the existing site improvements?
Yes No
No additional
Minimum Requirements #1 through 1/10
apply to the new and replaced impervious
surfaces.
Figure 2.3 — Flow Chart for Determining Requirements for Redevelopment i
Volume / — Minimum Technical Requirements February 2005
A9
Geotechnical Report
Ph.253-896-1011
Fx.253-638-8992
Les Schwab Tire Centers
c/o Contour Engineering
330956 1h Street NW
Gig Harbor, WA 98359
Attn: Mr, Brett Allen, PE
GeoResources, LLC
5113 Pacific Hwy. E, Ste. 1-1
Fife, Washington 98424-2649
August 12, 2009
Geotechnical Engineering Report
Les Schwab Facility
805 East Yelm Avenue
Yelm, Washington
No: LesSchwab.YelmAve.RG
INTRODUCTION
This report presents the results of our geotechnical services for the proposed Les
Schwab Tire Center commercial development at 805 East Yelm Avenue in Yelm,
Washington. The location of the site is illustrated on the Vicinity Map, Figure 1.
This report provides geotechnical recommendations and design criteria for the
proposed site development. We further understand that stormwater infiltration systems
are proposed for the development. The proposed site layout is illustrated on the Site
Plan, Figure 2.
Our services are provided at your request. Our understanding of the project is
based on our discussions with you, our previous work in the area and our site
observations and explorations. The purpose of our services is to evaluate the subsurface
conditions at the site to determine geotechnical recommendations and design criteria,
including stormwater infiltration rates. Specifically, our scope of services includes the
following:
1. Review the available geologic, soil and ground water data relevant to the
site.
2. Conduct a geologic reconnaissance of the site area. Monitor the excavation
of trackhoe test pits across the site, and specifically in the area of the
proposed infiltration systems.Collecting select soil samples for laboratory
testing, as appropriate.
3. Providing geotechnical recommendations for site grading including site
preparation, subgrade preparation, fill placement criteria, suitability of on-
site soils for use as structural fill, temporary and permanent cut and fill
slopes, drainage and erosion control measures.
4. Providing recommendations and design criteria for foundation elements
and floor/driveway slab support, including allowable bearing capacity,
subgrade modulus, lateral resistance valuesand estimates of settlement.
5. Providing recommendations and design criteria for conventional
subgrade/retaining (basement) walls, including backfill and drainage
requirements, lateral design loads, and lateral resistance values. Providing
pavement subgrade recommendation for the plat roadway.
'bl
Les Schwab — Yelm Avenue
August 12, 2009
Page 2
6. Providing stormwater infiltration rates for the native soils at the proposed
locations of the stormwater infiltration systems based on the City of Yelm
regulations per Table 1, Soil Classification Table.
SITE CONDITIONS
Surface Conditions
The project site is located in the central portion of the Yelm glacial outwash plain.
The site is bounded by existing commercial development on the southeast and west, and
Yelm Avenue on the north. We understand that the site is currently owned by the
adjacent church (west), but will be subdivided for the proposed commercial development.
The east portion of the site was previously developed as a residential site. The residence
remains at the site but will be removed. In addition, the garage slab, fence, well house
and timber storage building in the central portion of the site will be removed. There are
also several concrete slabs utilized as play areas in the south portion of the site that will
likely be removed.
The ground surface at the site is generally flat. No surface water flow was
observed at the site at the time of our reconnaissance. The site is currently vegetated
with scattered shrubs, several large trees and ornamental grass.
Site Geologic Conditions
The site is situated in the central portion of the Yelm glacial outwash plain. The
existing topography, as well as the surficial and shallow subsurface soils in the area are
the result of the most recent Vashon stade of the Fraser glaciation that occurred between
about 12,000 and 15,000 years ago, and the subsequent weathering and erosion. A
description of the surficial soils is included in the "Site Soils" section of this report.
In general the site is underlain by Vashon glacial outwash. The recessional
outwash material consists of gravelly sand with cobbles and occasional boulders, and
minor silt. The outwash material is in a medium dense condition near the surface to a
depth of approximately 2 feet. The soils become dense below that depth. Based on our
experience in the area, we expect that the site area is underlain by glacial till at depth,
likely several 10s of feet.
Site Soils
The NCRS - SCS (Thurston County Soil Conservation Survey) has mapped the
soils in the site area as Spanaway gravelly sandy loam (110) and Spanaway stony sandy
loam (112). Both these soils are described as having a rapid permeability with a "slight'
erosion hazard. We observed no active erosion in the site area during our
reconnaissance. Based on our observations, the site soils appear to have little or no
susceptibility to erosion, particularly where vegetation is established.
Subsurface Conditions
The subsurface conditions in the site area were evaluated by reviewing the
geologic maps and previous geotechnical reports in the site area, and monitoring test pits
excavated across the site and in the proposed infiltration areas. in general, recessional
outwash sandy gravel was encountered to the full depth explored in the test pit
explorations, up to 14.0 feet. The outwash material consisted of sandy gravel with
cobbles and occasional boulders. The soil classification method used is included as
Figure 4. Copies of the test pit logs area are included Figure S. Based on our site
observations and experience, the soils at the site are generally consistent. Therefore, no
additional subsurface explorations or borings are required.
S2—
Les Schwab —Yelm Avenue
August12,2009
Page 3
Grain size tests were performed on soil samples collected below the bottom of the
proposed infiltration system. The grain size tests indicate the soils are poorly graded
gravel with sand (GP). Copies of the grain size tests are included in Appendix A.
CONCLUSIONS AND RECOMMENDATIONS
GENERAL
Based on our site observations, explorations and analyses, we conclude that the
site is suitable for the proposed commercial site development. It is also our opinion that the
native site soils are suitable for the infiltration of stormwater, provided the
recommendations and design criteria provided herein area followed. The site-specific soils
at the proposed depth of the infiltration system and below a minimum of three feet consist
of sandy gravel with cobbles and boulders and minor silt. These Type A soils will allow
infiltration of stormwater from both the paved areas and the roof areas of the structures.
Based on the soils encountered in the subsurface explorations at the site and our
understanding of the proposed site development, conventional earthwork and foundation
support is feasible for the project.
Pertinent conclusions and geotechnical recommendations regarding the design and
construction of the proposed development are presented below.
Landslide Hazards
No slopes over 15 percent occur at the site. No evidence of soil movement was
observed at the site.
Erosion Hazards
Erosion hazard areas are defined by the City of Yelm as those areas defined by the
USDA Soil Conservation Service (SCS) soil survey maps as having a "moderate to
severe", "severe", or "very severe" rill and inter -rill erosion hazard.
The subject property is located in an area mapped by the SCS as Spanaway stoney
and gravelly sandy loam (112 and 116). It is our opinion that any potential erosion hazard
of the site soils during site development is not a limiting factor for the proposed
development. Temporary and permanent erosion control measures should be installed
and maintained during construction or as soon as practical thereafter to limit the influx of
additional water to exposed or disturbed areas.
Erosion control measures may include, but should not be limited to, berms and
swales with check dams to direct surface water runoff, ground cover/protection in
exposed areas and silt fences where appropriate. Graded areas should be shaped to
avoid concentrations of runoff onto cut or fill slopes, natural slopes or other erosion -
sensitive areas. Temporary ground cover/protection such as jute matting, excelsior
matting, wood chips or clear plastic sheeting may be used until the permanent erosion
protection is established.
Seismic Hazards
According to the Seismic Zone Map of the United States contained in Figure 16-2 of
the 1997 UBC (Uniform Building Code) and IBC (International Building Code), the project
site is located within Seismic Risk Zone 3. Based on the subsurface conditions observed
at the site, we interpret the structural site conditions to corresponds with a seismic Soil
Profile type Se, (Site Class "C") as defined by Table 16-J 7JBC) and Table 1615.1.1 in
the 2003 IBC documents, respectively. This is based on the likely range of equivalent
SPT (Standard Penetration Test) blow counts for the soil types observed in the site area.
These conditions were assumed to be representative for the conditions beyond the
Les Schwab — Yelm Avenue
August12,2009
Page 4
depths explored. Structures located at the site that are constructed in accordance with the
appropriate seismic criteria will have the same risk as other designed structures in the
Puget Sound area.
High Groundwater Hazards
The subject site is located outside of the Thurston County High Groundwater
Hazard area. A copy of the Thurston County Data Center High Groundwater Map for the
area is included as Figure 6.
EARTHWORK RECOMMENDATIONS
The following section of this report addresses our general conclusions and
recommendations regarding site preparation, structural fill, and the re -use of onsite soils.
Site Preparation
Areas at the site to be graded should be cleared of deleterious matter including
any existing structures, foundations, abandoned utility lines, debris and vegetation. The
portions of the site still covered with vegetation should be stripped of any organic -laden
soils. We anticipate that the average stripping depths will be on the order of 6 to 12
inches, although we expect that areas of deeper organics and topsoil will be encountered
in the east portion of the site, up to 2 feet locally. The stripped topsoil may be stockpiled
and later used for erosion control and landscaping/revegetation. Materials that cannot be
used for landscaping or erosion control should be removed from the project site.
Below the organic material and topsoil, there will be a layer of black sand and
gravel with variable silt content. This material is commonly referred to as the Steilacoom
Gravel. Although it is suitable for use as structural fill with the appropriate moisture
content, it is moisture sensitive and difficult to work with during wet weather conditions.
Where placement of fill material is required, the stripped/exposed subgrade areas
should be compacted to a firm and unyielding surface prior to placement of any fill. We
recommend that trees be removed by overturning in fill areas so that a majority of the
roots are removed. Excavations for tree stump removal should be backfilled with
structural fill compacted to the densities described in the Structural Fill section of this
report.
We recommend that a member of our staff evaluate the exposed subgrade
conditions after removal of vegetation and topsoil stripping is completed and prior to
placement of structural fill. The exposed subgrade soil should be proofrolled with heavy
rubber -tired equipment during dry weather or probed with a 1/2 -inch -diameter steel rod
during wet weather conditions.
Any soft, loose or otherwise unsuitable areas delineated during proof rolling or
probing should be recompacted, if practical, or over -excavated and replaced with
structural fill, based on the recommendations of our site representative.
Structural Fill
All material placed as fill associated with mass grading or as utility trench backfill
should be placed as structural fill. The structural fill should be placed in horizontal lifts of
appropriate thickness to allow adequate and uniform comi'action of each lift. Fill should
be compacted to at least 95 percent of MDD (maximum dry density as determined in
accordance with ASTM D-1557).
�3y
Les Schwab — Yeim Avenue
August12,2009
Page 5
The appropriate lift thickness will depend on the fill characteristics and
compaction equipment used. We recommend that the appropriate lift thickness be
evaluated by our field representative during construction. We recommend that our
representative be present during site grading activities to observe the work and perform
field density tests.
The suitability of material for use as structural fill will depend on the gradation and
moisture content of the soil. As the amount of fines (material passing US No. 200 sieve)
increases, soil becomes increasingly sensitive to small changes in moisture content and
adequate compaction becomes more difficult to achieve. During wet weather, we
recommend use of well -graded sand and gravel with less than 5 percent (by weight)
passing the US No. 200 sieve based on that fraction passing the 3/4 -inch sieve. If
prolonged dry weather prevails during the earthwork and foundation installation phase of
construction, higher fines content (up to 10 to 12 percent) will be acceptable.
Material placed for structural fill should be free of debris, organic matter, trash and
cobbles greater than 6 -inches in diameter. The moisture content of the fill material should
be adjusted as necessary for proper compaction.
Suitability of On -Site Materials as Fill
During dry weather construction, any nonorganic on-site soil may be considered
for use as structural fill; provided it meets the criteria described above in the structural fill
section and can be compacted as recommended. If the material is over -optimum
moisture content when excavated, it will be necessary to aerate or dry the soil prior to
placement as structural fill. We generally did not observe the site soils to be excessively
moist at the time of our subsurface exploration program.
As discussed above, the near surface Steilacoom gravel materials have a high
fines content and are moisture sensitive. During wet weather conditions, special
consideration will be required to utilized these soils as structural fill.
The underlying soils at the site generally consist of a fine to coarse sand with
gravel, cobbles and boulders. These soils are generally comparable to "common borrow"
material and will be suitable for use as structural fill provided the moisture content is
maintained within 4 percent of the optimum moisture content. However, the outwash
does appear to have a significant amount of cobbles and boulders, which may require
removal in the upper two feet of fill. Care should be taken when placing and compacting
granular material that has individual particales over 3 inches near utility lines and
immediately below pavement surfaces.
All fill material in building and driveway areas should be placed as described in
the "Structural Fill" section of this report and compacted to at least 95 percent of the
MDD. If fill material is imported to the site for wet weather construction, we recommend
that it be clean sand and gravel mixture, such as high quality pit run with less than
5 percent fines, or crushed rock.
Cut and Fill Slopes
All job site safety issues and precautions are the responsibility of the contractor
providing services/work. The following cut/fill slope guidelines are provided for planning
purposes only.
Temporary cut slopes will likely be necessary during grading operations or utility
installation. As a general guide, temporary slopes of 1.51-n V (Horizontal:Vertical) or
flatter may be used for temporary cuts in the upper 3 to 4 feet of the soils that are
weathered to a loose/medium dense condition. Where ground water seepage is
encountered, flatter temporary slopes may be required. These guidelines assume that all
BT
Les Schwab —Yelm Avenue
August12,2009
Page 6
surface loads are kept at a minimum distance of at least one half the depth of the cut
away from the top of the slope and that significant seepage is not present on the slope
face. Flatter cut slopes will be necessary where significant raveling or seepage occurs.
We recommend a maximum slope of 2H:1 V for permanent cut and fill slopes in
areas of medium dense sand and gravel. Where 2H:1 V slopes are not feasible in these
soils, retaining structures should be considered. Where retaining structures are greater
than 4 -feet in height (bottom of footing to top of structure) or have slopes of greater than
15 percent above them, they should be engineered. It should be recognized that slopes
of this nature do ravel and require occasional maintenance. Where raveling or
maintenance is unacceptable, we recommend that flatter slopes or retaining systems be
considered.
GEOTECHNICAL DESIGN CRITERIA
Foundation Support
Based on the encountered subsurface soil conditions encountered across the site,
we recommend that spread footings for the new residences be founded on medium
dense native outwash soils or on structural fill that extends to suitable native soils.
The soil at the base of the excavations should be disturbed as little as possible.
All loose, soft or unsuitable material should be removed or recompacted, as appropriate.
A representative from our firm should observe the foundation excavations to determine if
suitable bearing surfaces have been prepared, particularly in the areas where the
foundation will be situated in fill material.
We recommend a minimum width of 2 feet for isolated footings and at least 16
inches for continuous wall footings. All footing elements should be embedded at least 18
inches below grade for frost protection. Footings founded on the shallow black silty sand
and gravel as described above can be designed using an allowable soil bearing capacity
of 2,000 psf (pounds per square foot) for combined dead and long-term live loads.
Where footings extend to and are founded on the underlying gravelly sand, they can be
designed using an allowable soil bearing capacity of 3,000 psf for the combined dead and
long-term live loads. The weight of the footing and any overlying backfill may be
neglected. The allowable bearing value may be increased by one-third for transient loads
such as those induced by seismic events or wind loads.
Lateral loads may be resisted by friction on the base of footings and floor slabs
and as passive pressure on the sides of footings. We recommend that an allowable
coefficient of friction of 0.40 be used to calculate friction between the concrete and the
underlying soil. Passive pressure may be determined using an allowable equivalent fluid
density of 350 pcf (pounds per cubic foot). Factors of safety have been applied to these
values.
We estimate that settlements of footings designed and constructed as
recommended will be less than 1 inch, for the anticipated load conditions, with differential'
settlements between comparably loaded footings of 1/2 inch or less. Most of the
settlements should occur essentially as loads are being applied. However, disturbance of
the foundation subgrade during construction could result in larger settlements than
predicted.
Floor Slab Support
Slabs -on -grade, if constructed, should be supportel on the medium dense native
outwash soils or on structural fill prepared as described above. We recommend that floor
slabs be directly underlain by a capillary break material with minimum 6 -inch thickness of
30
Les Schwab — Yelm Avenue
August 12, 2009
Page 7
coarse sand, pea gravel, or gravel containing less than 3 percent fines. The drainage
material should be placed in one lift and compacted to an unyielding condition.
A synthetic vapor barrier is recommended to control moisture migration through
the slabs. This is of particular importance where the foundation elements are underlain
by the silty till or lake sediments, or where moisture migration through the slab is an
issue, such as where adhesives are used to anchor carpet or tile to the slab. A thin layer
of sand may be placed over the vapor barrier and immediately below the slab to protect
the liner during steel and/or concrete placement.
A subgrade modulus of 400 kcf (kips per cubic foot) may be used for floor slab
design. We estimate that settlement of the floor slabs designed and constructed as
recommended, will be 1/2 inch or less over a span of 50 feet.
Pavement and Driveway Areas
We understand that asphalt pavements will be used for the new driveways and
parking areas. All structural fill should be compacted according to our recommendations
given in the "Structural Fill" section. Specifically, the upper 2 feet of soils underlying
pavement section should be compacted to at least 95 percent of ASTM: D-1557, and all
soils below 2 feet should be compacted to at least 90 percent. The subgrade areas
should be proof -rolled with a loaded dump truck or heavy compactor to verify that a firm
and unyielding surface has been achieved. Any areas where this proof -rolling operation
reveals soft, organic, or pumping soils at or closely beneath the pavement subgrade
should be overexcavated to a maximum depth of 8 inches and replaced with a suitable
structural fill material.
DRAINAGE CONSIDERATIONS
Stormwater Infiltration Rates
Based on the soils encountered in our explorations and the results of the grain size
tests, we conclude that the infiltration of storm water is feasible at the site. The thick
underlying deposits of recessional outwash soils have adequate permeability and storage
capacity to infiltrate storm water from the site, provided adequate design, construction and
maintenance practices are used.
Storm water infiltration rates for the site soils were determined in accordance with
the Yelm/Thurston County Stormwater Manual guidelines, Table 1. Grain size distribution
tests were performed on select soil samples collected from the depth of the proposed
infiltration trench. The results of the grain size test are included in Appendix A.
Based on the soils observed in the test pits excavated at the site's stormwater
infiltration locations, we recommend a maximum infiltration rate of 60 inches per hour be
used for the infiltration system to be located in the area of Test Pits 3 through 6. For the
soils encountered in Test Pits 7 and 8 we recommend an infiltration rate of 40 inches per
hour. We recommend an appropriate factor of safety be applied to these values. Typically,
surface systems (ponds) utilize a factor of safety of 2, while a higher factor of safety should
be utilized for a below grade system (gallery).
Suspended solids could eventually clog the soil and reduce the infiltration rate for
retention ponds or trenches. Because of the potential for clogging, we recommend that an
appropriate factor of safety be utilized in the design. To reduce potential clogging of the
infiltration systems, the infiltration ponds or galleries shouldaot be connected to the
stormwater runoff system until after construction is complete and the site areas are
landscaped and paved. Temporary systems may be utilized through construction, or the
pond/trench bottom left a minimum of 1.5 -feet high during construction and later excavated
to the design grade. Periodic sweeping of the paved areas will help extend the life of the
S1
Les Schwab — Yelm Avenue
August 12, 2009
Page 8
infiltration system.
LIMITATIONS
We have prepared this report for Les Schwab and project consultants for use in
design and construction of the various components of this project. The data and report can
be utilized for bidding or estimating purposes, but our report, conclusions and
recommendations should not be construed as a warranty of the subsurface conditions, as
they may vary both vertically and laterally.
If there are changes in the locations or assumptions stated for this project, the
conclusions and recommendations presented may not be fully applicable. If design
changes are made, we should review the proposed changes to verify the applicability of our
conclusions and recommendations.
Variations in subsurface conditions are possible between the explorations and
may also occur with time. Sufficient monitoring, testing and consultation should be
provided by our firm during construction to confirm that the conditions encountered are
consistent with those indicated by the explorations, to provide recommendations for
design changes should the conditions revealed during the work differ from those antici-
pated, and to evaluate whether earthwork and foundation installation activities comply
with contract plans and specifications.
Within the limitations of scope, schedule and budget, our services have been
executed in accordance with generally accepted practices in this area at the time this
report was prepared. No other conditions, expressed or implied, should be understood.
♦ ♦ O
We appreciate the opportunity to be of service to you on this project. Please call if
you have any questions regarding this submittal, or if we can provide additional services.
Yours very truly,
GeoResources, LLC
Glen Coad, PE
BPS:GGbpb
DoclD:LesSch W ab.YelmAVe.RG
ii
Adad,l r ls: Figure site vwdy Map
Figure 2 - Site Pan
Figure $ • NRCS SCS Map
Figure 4 - Soil Classification System
Figure 5 - Test Prt Logs
Figure 6— Thurston Cmnty High Groundwater Hazard Map
AppondiK A— Grein Size Mali
Brad P. Biggerstaff, LHG
Principal
IL LEY P. PacGERSTAw:1
s
.RIS
f.
Av
!A
I H U R S T 0 N
q.
A,
Pv oCcarars
I
12
I Ito Ave
SE
ax
i Ae L
i
A,
Pv oCcarars
I
12
I Ito Ave
SE
ax
A,
Cook RASE
4".1IM"4Y$E
IMAwSE
ax
j -"I
R
GeoResources, LLC
5007 Pacific Highway East, Suite 20
Fife, Washington 98424
Phone: 253-896-1011
Fax: 253-896-2633
Approximate Site Location
Not to Scale
Site Vicinity Map
Proposed Commercial Development
805 Yelm avenue SE
Yelm, VVeshington
-
DocID: LesSchwab.Yelm�August 2009 Figure 1v,.SW
rr �"r:i anew
,
f, I I t"si
,�
i 9�
TP -2m
a
rto
ij cwuacr+
P -6i■ TP -3■ �y
a
r
°- !
TP -5 ,1 C.\ TP -4 ■tM
fn I t I Nrvrvou Anl4 \� plyy i .' J
L _..
9T2 PLAN � w _I '-------------- .._._`.___
SCALE 1" = 100'
APPROXIMATE LOCATION AND NUMBER OF TEST PIT TP -1 ■
Site Plan Provided by Contour Engineering & prepared LS Construction Co. dated 8.01.2009 _
GeoResources, LLC Site Pian & Exploration Map
5007 Pacific Highway East, Suite 20 Proposed Commmcial Development
Fife, Washington 98424 805 Yelm Avenue SE
Phone: 253-896-1011 Ye m, Washin ton _
Fax: 253-896-2633 DocID: LesSchwab.YelmAve.SP August 2009 Figure 2
�I�
Approximate Site Location
SCS
Soil Type
SCS Soil Name
Parent Material
Slopes
in ercent
74
_ _
Nisqually loamy fine sand
Sandy Glacial Outwash
3 to 15
110
Spanaway gravelly sandy loam
Volcanic ash over gravelly outwash
0 to 3
GeoResources, LLC
5007 Pacific Highway East, Suite 20
Fife, Washington 98424
Phone: 253-896-1011
Fax: 253-896-2633
NRCS Soils Map
Proposed Commercial Development
805 Yelm Avenue SE
Yelm,Washington
DocID: LesSchwab.YelmAve.SCS I August 2009
Not to Scale
Figure 3
U
SOIL CLASSIFICATION SYSTEM
MAJOR DIVISIONS
GROUP
GROUP NAME
SYMBOL
GRAVEL
CLEAN
GW
WELL -GRADED GRAVEL, FINE TO COARSE
..
GRAVEL
GRAVEL .-
_
COARSE
GP
POORLY -GRADED GRAVEL
GRAINED
More than 50%
-
—
SOILS
Of Coarse Fraction
GRAVEL
GM
SILTY GRAVEL
Retained on
WITH FINES
---
No. 4 Sieve
-
GC
CLAYEY GRAVEL
More than 50%
SAND
CLEAN SAND
SW
WELL -GRADED SAND, FINE TO COARSE SAND
Retained on
No. 200 Sieve
SP
POORLY -GRADED SAND
More than 50%
'Of Coarse Fraction
SAND
SM
SILTY SAND
Passes
WITH FINES
----
_.
No.4 Sieve
SC
CLAYEY SAND
....
SILT AND CLAY
INORGANIC
ML
SILT
CL -..._
CLAY
FINE_:: �
GRAINED
-
_...
.. SOILS
Liquid Limit
Less than 50
ORGANIC
OL
ORGANIC SILT, ORGANIC CLAY
SILT AND CLAY
INORGANIC
MH
SILT OF HIGH PLASTICITY, ELASTIC SILT
- . More than 50%
Passes
CH
CLAY OF HIGH PLASTICITY, FAT CLAY
No. 200 Sieve
Liquid Limit
50 or more
pRGANIC
OH
ORGANIC CLAY, ORGANIC SILT
HIGHLY ORGANIC SOILS
PT
PEAT
NOTES:
1... Field classification is based on visual examination of soil
in general accordance with ASTM D2488-90.
j 2. „ . Soil classification using laboratory tests Is based on
ASTM Q24$7-90.
3. Description of soil density or consistency are based on
interpretation of blow count data, visual appearance of
soils, and or test data.
SOIL MOISTURE MODIFIERS:
Dry- Absence of moisture, dry to the touch
Moist- Damp, but no visible water
Wet- Visible free water or saturated, usually soil Is
obtained from below water table
GeoResources, LLC Soil Classification System
5007 Pacific Highway East, Suite 20 Proposed Commercial Development
Fife, Washington.98424 805 Yelm Avenue SE
Phone: 253-898.1011 Yeim, Washington
-Fax' 253-896-2633
JOB LesSchwab.YelmAva August 2009 Figure 4
BIZ
IW
Test Pit TP-1
Location: NE portion of the site, by old house
Depth (ft.)
Soil Type Description
0.0- 1.0
Sod/Topsoil w/ sand and gravel
1.0-2.5
GM Brown silty GRAVEL with occ. cobbles (loose, moist)
2.5-5.0
SP Org/Brn SAND w/ gvl, cobbles, occ. boulders (med. dense to dense, moist)
6.0- 11.0
SP Brn gravelly SAND w/ cobbles, boulders (dense, moist)
Terminated at 11.0 feet below ground surface.
Minor caving observed.
No groundwater seepage observed.
Test Pit TP-2
Location: Behind old house, between shed
Depth (ft)
Soil Type Description
0.0-2.0
Sod/Topsoil.
2.0-2.5
GM Blk si GRAVEL w/ occ. cobbles (loose, moist)
2.5-9.5
SP Brn gravelly SAND w/ cobbles & boulders (med. dense to dense, moist)
Terminated at 6.0 feet below the ground surface.
Moderate caving observed at 6.0 feet below ground surface.
No groundwater seepage observed.
Test Pit TP-3
Location: NE corner of Playfield
Depth (ft)
Soil Type Description
0.0-1.5
Sod/Topsoil.
1.5-2.5
GM Blk si GRAVEL w/ occ. cobbles (loose, moist)
2.5-8.0
SP Brn gravelly SAND w/ cobbles & boulders (med. dense to dense, moist)
8.0- 14.0
GP Brn sdy/cobbly GRAVEL w/ occ. boulders (dense, moist)
Terminated at 14.0 feet below the ground surface.
Minor caving observed
No groundwater seepage observed.
GeoResources, LLC
Test Pit Logs
5007 Pacific
Highway East, Suite 20
Les Schwab Tires - Yeirn Avenue
Fife, Washington 98424
Yeim1 Washington
Phone: 253-896-1011
Fax: 253-896-2633
JOB: LesSohwab.YelmAve.TP
Aug 2009
Figure 5
IW
31 lq
Test Pit TP -4
Location: SE corner of Playground
Depth (ft)
Soil Type Description
_
0.0- 1.0
SodlTopsoil.
1.0- 1.5
SM Blk si SAND w/ gravel, occ. cobbles (loose, moist)
1.5 - 12.5
SP Brn gravelly SAND w/ cobbles & boulders (med. dense to dense)
Terminated at 12.5 feet below the ground surface.
Minor caving observed
No groundwater seepage observed.
Test Pit TP -5
Location: SW corner of Playground
Depth (ft)
Soil Type Description
0.0-0.5
Sod/Topsoil.
0.5- 1.0
GM Blk si GRAVEL w/ occ. cobbles (loose, moist)
1.0-15.0
SP Brn gravelly SAND w! cobbles & boulders (med. dense to dense)
Terminated at 6.0 feet below the ground surface.
Moderate caving observed at 6.0 feet below ground surface.
No groundwater seepage observed.
Test Pit TP -6
Location: NW corner of Playground
Depth (ft)
Soil Type Description
0.0-1.0
Sod(Topsoil.
1.0-2.0
SM Blk si SAND w/ gravel occ. cobbles (loose, moist)
2.0-6.0
SP Brn gravelly SAND w/ cobbles & occ. boulders (med. dense to dense)
6.0- 13.0
GP Brn sdy GRAVEL w/ cobbles, boulders (dense, moist)
Terminated at 6.0 feet below the ground surface.
Moderate caving observed at 6.0 feet below ground surface.
No groundwater seepage observed.
GeoResources,
LLC
Test Pit Logs
5007 Pacific Highway
East, Suite 16
NW Corner Yelm Avenue SE & Creek Street
Fife, Washington 98424
Yelm, Washington
Phone: 253.896-1011
Fax: 253-896.2633
JOB: DevelopmentatYeim.YeimSCornersRetaii.TP
May 2007
Figure 5 '..
31 lq
Test Pit TP -7
Location: Behind garage slab, next to tree
Depth (ft)
Soil Type
Description
0.0-1.5
Sod/Topsoil.
1.5-2.6
SM
Silk si SAND w/ occ. cobbles, organics (loose, moist)
2.5-5.0
SP
Org/Brn gravelly SAND w/ cobbles & boulders (med. dense to dense)
5.0- 12.5
GP
Brn sdy GRAVEL w/ cobbles & boulders (dense, moist)
Terminated at 12.5 feet below the ground surface.
Moderate caving observed
No groundwater seepage observed.
Test Pit TP -8
Location: East of church driveway, west part of site
Depth (ft) Soil Type Description
0.0-0.5 Sod/Topsoil.
0.5.1.8 GM Blk si GRAVEL w/ occ. cobbles (loose, moist)
1.8-4.0 SP Brn SAND w/ gravel, cobbles & occ. boulders (med. dense to dense)
4.0-9.5 SP Gry SAND w/ gravel, cob & occ. boulders (dense, moist)
9.5-16.0 GP Gry/Brn gravelly SAND w/ cobbles & boulders (dense, moist)
Terminated at 16.0 feet below the ground surface.
Moderate caving observed
No groundwater seepage observed.
Test Pit TP -9
Location: NW corner of site, next to tree
Depth (ft) Soil Type Description
0.0-1.0 Sod/Topsoil.
1.0-2,0 SM Blk si SAND w/ occ. cobbles, organics (loose, moist)
2.0 - 12.15 GP Brn sdy GRAVEL w/ cobbles & boulders (dense, moist)
Terminated at 12.5 feet below the ground surface.
Moderate caving observed
No groundwater seepage observed.
Logged by: BPB
Date: Aug 2009
GeoResources, LLC Test Pit Logs
5007 Pacific Highway East, Suite 16 NW Corner Yelm Avenue SE & Creek Street
Fife, Washington 98424 Yelm, Washington
Phone: 253-896.1011 _
Fax: 253-896-2633 --- —
J08: Les Schwab.YelmAve.TP Aug 2009 Figure 5
8)5
APPENDIX "A"
SIEVE
SIZE
PERCENT
" FINER
SPEC.'
PERCENT
PASS?
(X=NO)
2.5
100.0
2.0
_Particle Size Distributions
Report
1.5
64.4
8 S
'x
-.1.2.5-
63.0
1
56.0
Z u$
Z i v
46.6
100
39.1
.3125
36.4
#4
32.5
#10
30.4
#20
25.5
#40
9.6
-#60
3.2
#100
1.7
#200
1.0
80
70
so
Z
l
LL
j
z
so
V
LU
-
v
I
I
I I
I
I
I
I
V
I I
I
w
40
-
1
+
I
-
.....
_
30
V
I
_
-
2a
1I(
_
I
IItill"
Ii
l I
I
I
I
I
I I
I
N
100
10 1
0.1
0.01
c
GRAIN SIZE - mm.
c
%Gravel
%Sentl
V. Fines
p
° °'
Coarse Fine
Coarse
Medium Fine
Silt "
.., 4) _
0.0
1
53.4 1 14.1
1 2.1
1 20.8 1 8.6 1
1.0
SIEVE
SIZE
PERCENT
" FINER
SPEC.'
PERCENT
PASS?
(X=NO)
2.5
100.0
2.0
80.7
1.5
64.4
-.1.2.5-
63.0
1
56.0
.75
46.6
.5
39.1
.3125
36.4
#4
32.5
#10
30.4
#20
25.5
#40
9.6
-#60
3.2
#100
1.7
#200
1.0
0
-.. 10
20
--- 30
40
-- 50
so
70
80 -
90
100
Material Description
Sandy GRAVEL
Sampled by BPB on 8/6/09
Tested by RMH on 8/7/09
Atterberg Limits
PL= LL= P1=
Coefficients
D85= 53.5063 D60= 28.2286 D50= 21.4036
D80= 1.3754 D15= 0.5394 DiO= 0.4342
Cu= 65.02 Cc= 0.15 '
Classification
USCS= GP AASHTO=
Remarks
F.M.=6.36
F -- specification provided) _
2 p Sample Number: 090160 Depth: 12-15 feet depth
m " Location. TP -8 Date: 8/10/09
° Geollesources, LLQ Client: Les Schwab Store
- Project: Proposed Commercial Developement
1 h - F1fe,_WA. " - Project No: LesSchwab.Yeltitffty Figure
Tested By: RMH - _ Checked By: BPB__..,_ _
I - Gas
APPENDIX C
Retention Pond Analysis
Western Washington Hydrology Mode].
PROJECT REPORT
Project Name: 09-024.Lin Ret Pond Required
Site Address:
City
Report Date :1./9/2009
Gage Olympia
Data Start 1955/10/01
Data End 1.999/09/30
Precip Scale: 0.80
WWH43 Version:
DEVELOPED LAND USE
Name Pond
Bypass: No
Groundwater: No
Pervious Land Use
Acres
C, Lawn, Flat
.65
Impervious Land Use
Acres
PARKING FLAT
3.4
Element Flows To:
Surface
Interflow
Groundwater
Trapezoidal Pond 1,
Trapezoidal Pond 1.,
Name Trapezoidal Pond 1
_
6
Bottom Length: 196ft.
R tioi�°✓vl
F
Bottom Width: i0ft.
Depth : 6.5f.t.
Volume at riser head
: 0.5638f.t.
Infiltration On
Infiltration rate
20 \�
Infiltration saftey factor 0.5.x_
Side slope 1: 2 To 1
Side slope 2: 2 To 1
Side slope 3: 2 To 1
Side slope 4: 2 To 1.
Discharge Structure
Riser Height: 5.5 ft.
Riser Diameter: 1.8 in.
Element Flows To:
Outlet 1
Outlet 2
GZ-
Pond Hydraulic Table
Stage(ft) Area(acr) Volume(acr-ft) Dschrg(cfs) Infilt(cfs)
0.000
0.045
0.000
0.000
0.000
0.072
0.046
0.003
0.000
0.454
0.144
0.048
0.00'7
0.000
0.454
0.21.7
0.049
0.01.0
0.000
0.454
0.289
0.050
0.01.4
0.000
0.454
0.361
0.052_
0.017
0.000
0.454
0.433
0.053
0.021.
0.000
0.454
0.506
0.055
0.025
0.000
0.454
0.578
0.056
0.029
0.000
0.454
0.650
0.057
0.033
0.000
0.454
0.722
0.059
0.037
0.000
0.454
0.794
0.060
0.042
0.000
0.454
0.867
0.062
0.046
0.000
0.454
0.939
0.063
0.051.
0.000
0.454
1.011
0.064
0.055
0.000
0.454
1.083
0.066
0.060
0.000
0.454
1..156
0.067
0.065
0.000
0.454
1.228
0.069
0.070
0.000
0.454
1.300
0.070
0.075
0.000
0.454
1.372
0.072
0.080
0.000
0.454
1.444
0.073
0.085
0.000
0.454
1.517
0.075
0.090
0.000
0.454
1.589
0.076
0.096
0.000
0.454
1.661
0.077
0.1.01
0.000
0.454
1.733
0.079
0.107
0.000
0.454
1.806
0.080
0.113
0.000
0.454
1.878
0.082
0.119
0.000
0.454
1.950
0.083
0.125
0.000
0.454
2.022.
0.085
0.131
0.000
0.454
2.094
0.086
0.137
0.000
0.454
2.167
0.088
0.143
0.000
0.454
2.239
0.089
0.150
0.000
0.454
2.311
0.091
0.156
0.000
0.454
2.383
0.092
0.163
0.000
0.454
2.456
0.094
0.169
0.000
0.454
2.528
0.095
0.176
0.000
0.454
2.600
0.097
0.183
0.000
0.454
2.672
0.098
0.190
0.000
0.454
2.744
0.100
0.1.97
0.000
0.454
2.817
0.1.01
0.205
0.000
0.454
2.889
0.103
0.212
0.000
0.454
2.961
0.1.04
0.219
0.000
0.454
3.033
0.106
0.227
0.000
0.454
3.106
0.107
0.2.35
0.000
0.454
3.178
0.1.09
0.242
0.000
0.454
3.250
0.110
0.250
0.000
0.454
3.322
0.112
0.258
0.000
0.454
3.394
0.113
0.267
0.000
0.454
3.467
0.
115
0.275
0.000
0.454
3.539
0.
117
0.283
0.000
0.454
3.611.
0.1.18
0.292
0.000
0.454
3.683
0.1.20
0.300
0.000
0.454
3.756
0.1.21
0.309
0.000
0.454
3.828
0.123
0.318
0.000
0.454
3.900
0.124
0.327
0.000
0.454
3.972
0.126
0.336
0.000
0.454
4.044
0.128
0.345
0.000
0.454
4.117
0.129
0.354
0.000
0.454
G3
4.189
0.131
0.
363
0.000
5 year
0.454
4.261
0.132
0.3'73
1..3428
0.000
50 year
0.454
4.333
0.134
0.383
0.000
0.4:14
4.406
0.435
0.392
0.000
0.4514
4.478
0.;.37
0.402
0.000
0.454
4.550
0.
1.39
0.41.2
0.000
0.454
4.622
0.140
0.422
0.000
0.454
4.694
0.1.42
0.432
0.000
0.454
4.167
0.144
0.443
0.000
0.454
4.839
0.145
0.453
0.000
0.454
4.911
0.147
0.464
0.000
0.454
4.983
0.148
0.474
0.000
0.454
5.056
0.1.50
0"485
0.000
0.454
5.128
0.1.57.
0.496
0.000
0.454
5.200
0.153
0.50"1
0.000
0.454
5.272
0.155
0.51.8
0.000
0"454
5.344
0.151
0.529
0.000
0.454
5.417
0.158
0.541
0.000
0.454
5.489
0.160
0.552
0.000
0.454
5.561
0.1.62
0.564
0.221
0.454
5.633
0.1.63
0.576
0.71.1
0.454
5.706
0.165
0.587
1.361
0.454
5.778
0.1.67
0.599
2.139
0.454
5.850
0.168
0.611,
3.025
0.454
5.922
0.170
0.624
4.008
0.454
5.994
0.172
0.636
5.079
0.454
6.067
0.173
0.648
6.232
0.454
6.139
0.175
0.661
7.460
0.454
6.211
0.177
0.674
8.160
0.454
6.283
0.178
0.687
10.13
0.454
6.356
0.1.80
0.699
11.56
0.454
6.428
0.182
0.71.3
13.05
0.454
6.500
0.183
0.726
14.61
0.454
6.572
0.185
0.739
1.6.22
0.454
ANALYSIS RESULTS
Flow Frequency Return Periods for Developed. POC #1
Return Period
Flow(cfs)
2 year
0.8829
5 year
1.0769
10 year
1.1.9'73
25 year
1..3428
50 year
1..4475
100 year
1.5495
This program and accompanying documentation is provided 'as -is' without warranty of
any kind. The entire risk regarding the performance and results of this program is
assumed by the user. Clear Creek Solutions and the Washington State Department of
Ecology disclaims all warranties, either expressed or implied, including but not
limited to implied warranties of program and accompanying documentation. In no event
shall Clear Creek Solutions and/or the Washington State Department of Ecology be
liable for any damages whatsoever (including without limitation to damages for loss of
business profits, Loss of business .i.nformation, business interruption, and the like)
arising out of the use of, or .inability to use this program even if Clear Creek
Solutions or the Washington State Department of Ecology has been advised of the
possibility of such damages.
(, 114
APPENDIX D
Water Quality Systems Sizing and Specifications
1 el v- i %.MAS /'5- - f(ov (cin ` 0,154 7 6
7, 7
.� .i
yrs SSG
sdt_ -
7�
�-
lode.(
5���
�r✓ — /S 5�/
i
e
/ o?u i
�l.f� ..S- -
�7 4' `>-I.�`7� '
- /,� 7� l 5F' _ �Y `t7' I I � (�� :J�i` Gi:✓e)
117,5 /5F' �iSG
5(= of 13SS (C'Z3QG:e5�
1 el v- i %.MAS /'5- - f(ov (cin ` 0,154 7 6
7, 7
Western Washington Hydrology Model
PROJECT REPORT
Project Name:
Site Address:
City
Report Date
Gage
Data Start
Data End
Precip Scale:
WWH43 Version:
09-024.WQ BASIN SCHWAB
1.0/28/2009
Olympia
1955/10/01
1.999/09/30
0.80
Name SCHWAB
Bypass: No
GroundWater: NO
Pervious Land Use Acres
C, Lawn, Flat .23
Impervious Land Use Acres
PARKING FLAT 1.03
Element Flows To
Surface Interflow Groundwater
Water Quality SMP Flow and Volume for POC 1.
On-line facility volume: 0.1421 acre-feet
On-line facility target flow: 0.01 cfs. /
Adjusted for 15 min: 0.1587 cfs. t (Avp f --Ir
Off-line facility target flow: 0.0806 cfs
Adjusted for 15 min: 0.0892 cfs.
This program and accompanying documentation is provided 'as -is' without warranty of any
kind. The entire risk regarding the performance and results of this program is assumed
by the user. Clear Creek Solutions and the Washington State Department of Ecology
disclaims a1.1warranties, either expressed or implied, including but not l.i.mi.ted to
implied warranties of program and accompanying documentation. In no event shall Clear
Creek Solutions and/or the Washington State Department of Ecology be liable for any
damages whatsoever (including without limitation to damages for loss of business profits,
loss of business information, business interruption, and the like) arising out of the use
of, or. inability to use this program even if Clear Creek Solutions or the Washington
State Department of Ecology has been advised of the possibility of such damages.
g2_
bAIAJIST
.O -AI ION
PIPE (`iEE NOT[ 15)
LocnTION (TYP)
(SEE NOI E 6)
OUILF1
RAY
INLE1 PIPE _� + OUTLET PIPE
(5EE NOTES 546) (5EE NOTE5 5£G
6'x 12' STORMFILTER - PLAN VIEW rl
30'0 PRAMS AND
COVER (TYP)
(5EE NOTE 4)
GRADE. RING
((Yr)
FLOW SPREADER 1
(TYP) P.AFPLF Y✓Alt.
(TYP)
FF I LADDER 4'-G' MIN
(SEE NOTE 7)
3'-4
PERMANENT
POOL
11 it lilt i t
ENERGY 5TORMFILTFR
D1551PA1 OR CARTRIDGE. (TYP) UNDERDRAIN
(HE NOTE 2) MANIPOI.D
6' x 12' STORMFILTER-SECTION VIEW Dif 51ORMWAUR MANAGZWNT
5[onN
1 LlS.PAIFN2Plo.o. 53 5.322.629.
Nc..707.529, N, 6A27,639
NAND 649,OAb. No. 5.FOUIG6,
/JJD OTNF.R U.S. ANG FOREIGN
(92006 CONTECH Stonwater Solutions PATfNT5 Penowc
6' x 12' PRECAST STORMFILTER DR WING
STORMWATER PLAN AND SECTION VIEWS �
SOLUTIONS STANDARD DETAIL 112
Wntehatomwaler.wm DATE: 09129105 1 SCAT H: NONE I FILE NAME: 5F61bPC4XL OfNWN:MAV CHECRL):PRC
V J
GENERAL NOTE5
I) 5TORMPILTER BY CONTECH STOPMWATEP. 501UTIONS; PORTLAND, OR (800) 548-4667; 5CA.PROR000t', M(_ (877) 907 8G7G;
E.LKPJDGE, MD (8GG) 740.3 18.
2) FILTER CARTRIDGE(-,) TO DE SIPHON -ACTUATED AMC) 511L1 -CLEANING. 51ANDAR,D DETAIL DPAWING 5HOW5 MAXIMUM NUMI3LR
OF CARTRIDGEr, ACTUAL NUMBER REQUIRED TO RE SPECIFIED ON 51T'E PLANS OR IN DATA TABLE BELOW.
3) PRECAST VAULT TO HE CONSTRUCTED IN ACCORDANCE tNlTfi ASTM C857 AND 0858. DETAIL DRAWING REFLECTS DESIGN
IIJTENT ONLY. ACTLJAI. DMENSIOWS ANO CONFIGURATIOIJ OF .STRUCTURE WILT. RE SHOWN ON PRODUCTION SHOE DRP.WING.
4) STRUCTURE. ANC ACCESS COVERS TO MEET AASrrO tf20 LOAD RATING.
5) 5TORMEII.TCR REQUIRE-, 2.3 FEET OP DROP FROM INLET TO OUTI.ET. IF LESS DROP IS AVP.IIAI3LC-, CONTACT CONTECY,
5TORMWATER 50(UTION5,
G) INLET ANC OUFF1 FIRING i0 BF 5PFCIPIED BY ENGINEER AND PROVIIJED by CONTWP.CTOR. PRECAST 5TORMFILTFR VAUIT
FQUIPPED WITH EITHER CORED OPENINGS OR ICNOCICOU15 AT [NJ FI AND OUTLT LOCANON5.
7) PROVIDE MINIMUM CI EARANCE POR MA.INTENlWCE ACCESS. If A 51-11,I.I.OWER 5Y5TE M: IS REQUIRED, CONTACT CONTECH
5TORMWATEP 5OLUTIONS POR OTYER OPTIONS.
5) ANTI -FLOTATION 3AIIA5T TO BE 51'EQFIED BY ENGINEER AND PPOVIDED BY CONTRACTOR, IF REQUIRED, RAJ I AiT TO EC 5117
ALONG ENTIRE LENGTH OF BOTH 51DE5 Of THE 5TRUCTUPE.
9) AL15TORMFILTER5 REQUIRE REGU[AR MAINTENANCE, REFER TO OPERATION AND MAINTENA.NCE GUIDELINE5 FOR MORE
RAF BE
fl/A11
30'0 FRAME AND COVER
(TYP) (SEE 140TE 4)
FLOW
SPREADER
BALLAST
(SIFE NOTE 8)
HEIGHT
e +
UNDERORAIN
MANIFOLD WIDTH��--)
6'x 12' STORMFILTER - SECTION VIEW rBS-�
2
W'3
6' x 12' STORMFILTER -TOP VIEW
2
RfP STOR�n1VA'fFl2 MANAG[MCNT
$R:crxJ
0.5. PATENTNT 11nlo. 5,322.629,
No. D.707.e27, No. e.027o39
AND OTfiPB U.S. AND FOREIGN
PhiZNt$ WUNDING
�/=��i�SITCAIJ� 6'x 12' PRECAST STORMFILTER
V����� i TOP VIEW, SECTION VIEW AND NOTES 2
STORMWATER�----� STANDARD DETAIL
�---�SOLUTIONS v2
wntechstormvmter,wm DATE.09I26I05 I SCALE:NONE I I ILE NAML:SF612.PC-DTL DHAV✓N: MJW I CHE:CKED;ARG
V�y
r w /.ti =�� �J i� oil -02-y
2 SF 0;LICJS—
Iffier✓'. ;; ,;c .�-rte.. = f:Xv35i= x"L = 2. 73'�
,5�..�per✓:jos rr_ = 1710 Z-7 iLiU2- 5F �U(, '3``iZ Gc✓c)
�%✓ (,JG✓{�/�� iS-rn�h �%e.✓ R �- = C�,��SzB c -ice
AID
rAre
pe ✓;a✓y f�v c-
_ l�lv� f -
a'tiS = l"zh YJo
�11 � WC/i I-I/✓i
/S r��
-F/e.✓ &w c
= 0.0>1'13 ci's
7
C�Oly3
K `l49 =
Z.�"3 '—'
3c�r 5ey ��S�MIf'
Western Washington Hydrology Model
PROJECT REPORT
Project Name:
Site Address:
city
Report Date
Gage
Data Start
Data End
Precip Scale:
WWHIf3 Version:
09-024.WQ BASIN ;pRDl
11/4/2009
Olympia
1955/10/01
1999/09/30
0.80
Name RD1
Bypass: No
GroundWater: NO
Pervious Land Use Acres
C, Lawn, Flat .063
Impervious Land Use Acres
ROADS FLAT 0.342
Element Flows To:
Surface Interflow Groundwater
Water Quality BMP Flow and Volume for POC 1.
On-line facility volume: 0.0469 acre-feet e
On-line facility target flow: 0.01 efs. U eck For slZ,In
Adjusted for 15 min: 0.0528 cfs. <_- J
Off-line facility target flow: 0.0267 efs.
Adjusted for 15 min: 0.0296 cfs.
This program and accompanying documentation is provided 'as -is' without warranty of any
Kind. The entire risk regarding the performance and results of this program is assumed
by the user. Clear Creek Solutions and the IJashington State Department of Ecology
disclaims all warranties, either expressed or implied, including but not limited to
implied warranties of program and accompanying documentation. in no event shall Clear
Creek Solutions and/or the Washington State Department of Ecology be liable for any
damages whatsoever (including without limitation to damages for loss of business profits,
loss of business information, business interruption, and the Like) arising out of the use
of, or inability to use this program even if Clear Creek Solutions or the Washington
State Department of Ecology has been advised of the possibility of such damages.
D(o
Western Washington Hydrology Model
PROJECT REPORT
Project Name:
Site Address:
City
Report Date
Gage
Data Start
Data End
Precip Scale:
WWHM3 Version:
09-024.4gQ BASIN IIRD2
7.1/4/2009
Olympia
1955/10/01
1999/09/30
0.80
Name RD2
Bypass: No
GroundWater: No
Pervious Land Use Acres
C, Lawn, Flat .044
Impervious Land Use Acres
ROADS FLAT 0.287
Element Flows To:
Surface Interflow
Groundwater
Water Quality li+ Flow and Volume for POC 1.
On-line facility volume: 0.039 acre-feet
On-line facility target flow: 0.01 cfs.
Adjusted for 15 min: 0.0443 cfs. _< (Ac, S� 2'n�
Off-line facility target flow: 0.0224 cfs.
Adjusted for 15 min: 0.0249 cfs.
This program and accompanying documentation is provided 'as -is' without warranty of any
kind. The entire risk regarding the performance and results of this program is assumed
by the user. Clear Creek Solutions and the Washington State Department of Ecology
disclaims all warranties, either expressed or implied, including but not limited to
implied warranties of program and accompanying documentation. In no event shall Clear
Creek Solutions and/or the Washington State Department of Ecology be liable for any
damages whatsoever (including without limitation to damages for loss of business profits,
loss of business information, business interruption, and the like) arising out of the use
of, or inability to use this program even .if Clear. Creek Solutions or the Washington
State Department of Ecology ties been advised of the possibility of such damages.
D-7
64.1.1:.51
° (5EE NOTE 8)
7Z''O
°
A
1
INLET PIPE 5'71 2'0 I1DPE OUTLET
(5EE NOTE5 5 E G) 5TUD (5EE NOTE5 5 G)
n
MANHOLE STORMFILTER - PLAN VIEW �1�
1
30'6 PRME AND
COVER (5TD)
CONCRETE (5EE NOTE A)
GRADE RING
51 EP (TYP)
INLET PIPE -'.DPE OUTLET
(SEE NOTES 5 E G) R15ER WM
SCUM DAM E
r� 4' G" MIN
(5EE NOTE 7)
5ALLA51
(5EE NOTE 5)
YIEIGII7 dO `\\
WIDTH I �-�— `— SEE DETAIL 2/2
UNDFRCRA.IN 51ORMPILTE1? CARTRIDGE
MANIFOLD (iYP) (5EE NOTE 2)
MANHOLE STORMFILTER - SECTION VIEW %AA�
1 TME. STo MWAR:R MANAGEWNT
0.5. PATENT Na. 5.322,629,
No. 5.707.v22'no. G.027.639
OTHER
6..A 5,-a4IG4.
IJAND O!M[R U5140 ECSEIGN
OMWING
A���ITCA��� PRECAST 72" MANHOLE STORMFILTER
=�` ' PLAN AND SECTION VIEWS 1
STORMWATER STANDARD DETAIL
SOLUTIONSK ll2
W012Chatorm 6t21.00111 DAl E:09126/05 SCALE:NCNE FILE NAME: MHSF7-72PC-DTL I UINWN.MJW CHECNEC:ARG
l7�
GENERAL NOTES
i ) 51ORMPICTFP BY CONTFCH STORMWATER S0LUU01,15; PORTLAND, OR (800) SA8 4GG'7; SCAR130POUGH, ME (577)
907 867(,'; FIARIDGE, MD (8GG) 7403318.
2) PILTFP OAK ROGE(5) TO BF 51FtiON-ACTUATED AIJD SELF -CI EA.NING- STANDARD DETAIL SHOWS MAXIMUM NUMBEP Of-
CARTRIDGE5. ACTUAL NUMPER REQUIREC TO BE 5FECINED ON 51iE PLANS OR IN DATA TABLE BELOW.
3) PRECAST MANHOLF 5TRUCTURF TO BE CONSTRUCTED IN ACCORDANCE WITH ASTM C478. DETAIL PtfLFL;L`> DE:iIGN INTENT
ONLY. ACTUAL DIMEN`ION5 AND CONF-IGUP.ANON Of STRUCTURE WILL E2 S IE)WN ON PRODUCTION OTOP DRAWING,
4) 51PUCIURE AND ACCE55 COVEP5 TO MEET AA51"1011-20 LOAD PATING.
5) STORMfIL-ER PFOUIPES 2.3 FEET OF DROP PROI0 INLET TO QUTLCT. IF 1.1155 DROP 15 AVAIIA.51-E, CONTACT CONTECI'I
,5 ORMWATER 501UTION5. MINIMUM ANGLE BETWEEN INI ET AND OUTLET 15 45°.
G) INLET PIPING TO BF 5FECIFIED BY ENGINEER AND PROVIDED BY CONTRACTOR. PREC/t5T MANHOLT SIORMFII.TER FOIIIPFED
WITH A DUAL DIAMETFP HDFE OUTLET STUB AND 5AND COLLAR, EIGHT INCH. DIANIE ILK OUTLET 5PCIION MAY BE 5FFARATFD
FROM OUTLET 5TU13 AT MOLI)f1) IN CUT LINE TO ACCOMMODATE A 12 INCH OUTLCT PIPE, CONNECTION TO DOWNSTREAM
PIPING TO BE MADE U51NJ A FLEXIBLE COUPLING OR ECCFNTRIC RFDUCFR, A5 REQUIRED. COUPI ING 5Y FERNCO OR EOUAL
AND PROVIDED 13Y CONTRACTOR.
7) PROVIDE MINIMUM CIFARANCE FOR MAINTENANCE ACCE55, IF A 5HAI.I.Oh/ER SY5TEM 15 REQUIRED, CONTAQ COM[CH
51OF.MWA1 ER 5OLUTION5 FOR OTHEP OPTION5,
8) ANTI-PIOTATION RAI 1-45T TO GE 5PFGIfI[D BY FIJGINEFP AND PROVIDED BY CONTRACTOR, IF REQUIRED, PALIAST TO BF SET
AROUND THE PFRIMETER OF THE STRUCTURE.
9) ALJ. 51ORMFII.TFR5 RFOURE REGULAR MAINTENANCE, REFER TO OPERA ON AND MAINTENANCE GUIDFI INE5 FOR tvORE
INFORMATION.
30'0 fDAME
AND COVER (STD)
MANHOLE STORMFILTER- TOPVIEW rl
\2�
OUTLET 5AND'01IAR
R15FP I P`0 OUTLET 5TUB
a MOLOFD-IN CUT LINE
NC
8"0 OUTLET 5TU13
OUTLET FIFE
(DY CONTRACTOR)
COUPLING
(13Y CONTRACTOR)
(5EE NOTE G
13AI.IAST
GROUT (5EE NOTE 8)
(BY CONTRACTOR)
MANHOLE STORMFILTER - OUTLET DETAIL %2)
2IDIlBS't63MGSnf2)r11STormwater Solutions 2
IhE STORWIATCR MAW,[ W111
U 5. PATI NT No. 5,322.G29.
No. 5.707,527, No. 6,027.639
8n. GA4RO-3. No.'i,G2a,57G.
AND OrhER U.5. AND FCU..IGN
FAINTS PENDING
A�UcLIVE^PRECAST 72" MANHOLE STORMFILTER
J" vwval — ° NOW H TOP AND SECTION VIEWS, NOTES AND DATA 2
STORMWATE/R^_ STANDARD DETAIL
Ste/ oLUT�o Ns� 212
oontechmormwetecwm DATE:09126105 I SCALE: NONE FILE NAME: MHSP7-72PC-D1L DMWN: M.NJ CHECKED:ARG
Dcl
41
INLET P
(5EE NOTE5 5 k
MANHOLE STORMFILTER - PLAN VIEW%1�
1
30"0 FRAME
AND COVER(5TD)
CONCRETE (,SFE NOTE 4)
GRADE RING
STEP
(NP)
INLET PIPE HDPE OUTLET 1
(5EE NOTES 5 6 6) P15EP WITH
SCUM BAPPLE
4 6" MdN
r� (SEE NOTE 7)
5TORMFII TER CARTRIDGE
(TYP) (5EE I40TE 2)
BAIL+ST .
(SEE NOTE 8)
HEIGHT a
---� -�— •WIDTH , UNDERDRAIN 5EE DETAIL 2/2
MANIFOLD
MANHOLE STORMFILTER - SECTION VIEW (:A)
1
UTL.ET
55 E Fi)
THL `dTOPW Wh1ER MA NAGTMENI
SW -NO 5.3
U.S. PATCM No. 5,322,629,
No. 5,707,527, N.. G1027 G39
No. D OTHEK U No. 5,624, IGN
AND pinfR 0.5. AND FOREIGN
02006 CONTECH Stonwater Solutions rATrNTs -NDING
A� Umrle^L o PRECAST 48" MANHOLE STORMFILTER DRAWING
STORMWATER PLAN AND SECTION VIEWS
�-SO K STANDARD DETAIL
WrNeCh810"W8ler.WM DAT E: 09126105 SCALE: NONE I FILE NAME: MHSE3�48PGDTL I DRAWN: MJW I CHECKED: ARG
Do
GENERAL NOTES
1) STOKMf11TER BY CONTECH 5TORM`4AAT(_R 501A1TION5t FORTLAN ), OR (800) 548-4667: ,CAPbOKOUGF' ME (877) 907-8676;
EI KP.IDGE. MD (866) '740 33 i 8.
2) PIF?ER CARTRIDGf(51 TO EF 51Fi ION -ACTUATED AND 5EI_P-CLEANING. SANDARD DETAIL SHOWS MAY.IMUM NUIvIl3ER OP
CARTRIDGFS. ACTUAL NUMBER REQUIP.ED TO 5E SPECIFIED ON 511 F PLANS OR IN DATA TABLE BELOW.
3) PRECAST MANHOLE STP.UCIUP.E TO BE C:ONSTRUC'FD IIJ ACCORDANCE `/✓ITH ASTM C4'78. CE?All. P.EPLECTS DESIGN INTENT
ONLY. ACTUAL DIMCN51011S AND CONFIGURATION Of STRUCTURE Witt BF SHOWN ON I-RODUCI'ION SFIOP CRANING.
A) STRUCTURE AND ACCESS COVLPS TO MEET AA511"10 Ii -20 LOAD RATING.
5) 51ORMI'V ER REQUIRES 2.3 FEET OF DROP FROM INLET TO OUTLET. IF LF55 DROP 15 AVAIIA.511. CONTACT COMECIt
j1ORMWNIER 501UTIONS. MINIMUM ANGLF F)FTWFEtl INI E? ANC QUTI'[T 15 45°.
G) INLI' PIPING TO BE 5PECIFIED BY FIJGIPJEER AND PROVIDED 6Y CONTRACTOR. PRECAST MAIJt101.E STORMFIISER EQl11PPED
WITH A DUAL DIAMETER IOPE ONE LET STUB AND SAND COLLAR, EIGHT INCH DIAMETER CUII D SECT ON MAY 51E SEPARATED
FROM OUTLET STUB AT MOLDED -IN CUT LINE TO ACCOMMODATE A 12 INCN OUTLET PIPE. CONNECTION TO DOV✓N5?P.EAM
PIPING TO BE MADE U51NG A fLEX161 E COUPIINC OR ECCENTRIC REDUCER, AS RFQUIRFD. COUP[ ING BY f'ERNCO OR EQUAL AND
PROVIDED BY CONTRACTOR.
7) PROVIDE MINIMUM CLEARANCE FOR MAINTENANCE ACCP. 55. IF A SHALLOWER SYSTEM IS REQUIRED, CONI ACT CONI ECH
STORMWATER SOLUTIONS FOR OTHER OPTIQIJ,
8) ANTI P -I OTA110N BAIJA57 TO BE SPFCIFIED BY FNGINFFR AND FROVIDEG BY CONTRACTOR, IF REQUIRED. DAI I AST TO BE 5[i
AROUND T IIE PERIMETER Of THE STRUCI URF.
9) ALL STORMFILTERS KEQUIKE REGUTAK MAINTENANCE. REFER TO OPERATION AND MAINTENANCE GUIDELINES FOR MORE
INFORMATION.
30'0 FRAME
AND COVEK (STC)
MANHOLE STORMFILTER - TOP VIEW
2
QUTIFT SANG COLIAR
R15ER A / ( 'Jl OUT1 3TUB
LD
a' MOED-IN CUT LINE
i— 8"O OUTIU71 FTSTUB
OUT[ ET PIPE
(t3Y CONTRACTOR)
COUPLING
(EiY CONTRACTOR)
(5EE NOTE G)
HALIAST
GROUT (5EE NOTE 8)
(EiY CONI PACIOR)
MANHOLE STORMFILTER - OUTLET DETAIL (2�
2
STORMWATER
SOIUTIONSK
THE STOJ W WA1 CR MANA6-PJA NT
5W'I,f w
U.`_i. PATENT No. 5.322,619,
ago. 5,707,52V, Ito, 6,02.9,639
No. G,G49,018, No. 5,G24,576,
AND OTHER U.S. AND fCREIGi\'
PAMI T5 P.'.ROIN'G
PRECAST 48" MANHOLE STORMFILTER
TOP AND SECTION VIEWS, NOTES AND DATA
STANDARD DETAIL
DATE:0917.6105 SCALE:NONE TILT NAME MHSfJdBPG)ill DRAWN: MJ
2
CM
APPENDIX E
Conveyance Calculations
Worksheet for Main S® 12" @.4%
Project Description
Friction Method Manning Formula
Solve For Normal Depth
Input Data> -
Roughness Coefficient
0.015
Channel Slope
0.00400
ft/ft
Diameter
1.00
ft
Discharge
1.55
ft3/s
Results
Normal Depth
0.67
If
Flow Area
0.56
ftp
Wetted Perimeter
1.92
it
Top Width
0.94
ft
e'4
Critical Depth
0.53
ft
Percent Full
67.3
f
Critical Slope
0.00839
fUft
INS
2 D
Velocity
2.76
ft/s
f----
2 , i Gx
i
Velocity Head
0.12
ft
hi,n, G�r�_r,h�
Veto<-��� !S MCA,
Specific Energy
0.79
ft
Froude Number
0.63
Maximum Discharge
2.10
l
Discharge Full
1.95
ft'/s
Slope Full
0.00252
ft/ft
Flow Type SubCritical
GVF Input Data
Downstream Depth
0.00
it
Length
0.00
It
Number Of Steps
0
GVF Output Data
Upstream Depth
0.00
ft
Profile Description
Profile Headloss
0.00
it
Average End Depth Over Rise
0.00
Normal Depth Over Rise
67.25
%
Downstream Velocity
Infinity
ft/s
Upstream Velocity
Infinity
fps
Bentley Systems, Inc. Haestad Methods Solution Center Bentley FlowMaster [06.01.071.00]
1111112009 4:41:40 PM 27 Siemens Company Drive Suite 200 W Watertown, CT 06796 USA +1-203455-1666 Page 1 of 2
Worksheet for Main SD 12" @.4%
GVF Output Data
Normal Depth
Critical Depth
Channel Slope
Critical Slope
0.67 ft
0.53 ft
0.00400 ft/ft
0.00839 Wilt
Bentley Systems, Inc. Haestad Methods Solution Center Bentley FlowMaster [08.01.071.00]
11/1112009 4:41:40 PM 27 Slemons Company Drive Suite 200 W Watertown, CT 06795 USA +1-203-755-1666 Page 2 of 2
Worksheet for Roof Lines
Project Description
Friction Method Manning Formula
Solve For Discharge
Input Data
Roughness Coefficient
0.015
Channel Slope
0.01000
ft/ft
Normal Depth
0.50
ft
Diameter
0.50
ft
Results
Discharge
0.49
ft'/s
Flow Area
0.20
fi
Wetted Perimeter
1.57
ft
Top Width
0.00
ft
Critical Depth
0.36
ft
Percent Full
100.0
%
Critical Slope
0.01369
ft/ft
�-{ SV m1n
{1115 2.,0 �5
Velocity
2.48
f/s
<— �`t$
Velocity Head
0.10
ft
G�Pa-✓`h� vt to�bl� �S �^'��'�
Specific Energy
0.60
ft
Froude Number
0.00
Maximum Discharge
0.52
W/s
Discharge Full
0.49
W/s
Slope Full
0.01000
ft/ft
Flow Type SuIrCritical
GVF Input Data
Downstream Depth
0.00
H
Length
0.00
ft
Number Of Steps
0
GVF Output Data
Upstream Depth
0.00
ft
Profile Description
Profile Headloss
0,00
ft
Average End Depth Over Rise
0.00
%
Normal Depth Over Rise
100.00
%
Downstream Velocity
Infinity
ft/s
Upstream Velocity
Infinity
ft/s
Bentley Systems, Inc. Haestad Methods Solution Center Bentley FlowMaster [08.01.071.001
11/11/2009 4:41:57 PM 27 Siemens Company Drive Suite 200 W Watertown, CT 06795 USA +1.203.7551666 Page 1 of 2
Worksheet for hoof tines
GVF Output Data
Normal Depth 0.60 ft
Critical Depth 0.36 ft
Channel Slope 0.01000 ft/ft
Critical Slope 0.01369 ft/ft
Bentley Systems, Inc. Haestad Methods Solution Center Bentley FlowMaster [08.01.071.00)
11/11/2009 4:41:57 PM 27 Siemens Company Drive Suite 200 W Watertown, CT 06795 USA +1-203-755-1666 Page 2 of 2